They don’t call New York the Big Apple for nothing. Its new Police Training Academy is Big Apple big. At 720,000 sf, the academy can train two thousand recruits and law enforcement personnel at a time. It is arguably the most advanced self-contained facility of its kind in the world.
The 480,000-sf academic/administration building (classrooms, library, admin/faculty offices) is linked via an aerial pedestrian bridge to the 240,000-sf physical training facility (running track, tactical gymnasium, scuba pool, mock situation environments), a central utility plant, and a muster court.
BRONZE AWARD
New York City Police Training Academy
Queens, N.Y.
The joint venture CM of Turner Construction/STV had to build on a 35-acre city landfill in the College Point section of Queens, near LaGuardia Airport. This led to one of the most stringent environmental compliance efforts ever for a public facility in the city. Decades of household, industrial, and commercial waste had to be dug up and remediated. The entire infrastructure was propped up above the 100-year flood plain so that it could remain operational under extreme weather conditions. The project earned LEED Gold certification.
The project required 65 prime contractors and more than 300 subcontractors. To manage all this, the NYC Department of Design and Construction set up an integrated project office for 100 stakeholders. “Zones of expertise” were formed to enable disciplinary leaders—architecture, structural engineering, interior design, etc.—to communicate readily and make timely decisions. This enabled the Building Team to start work on the foundation and order almost 9,000 tons of structural steel before designs were 100% finalized. It was the first time the NYCDDC had ever used a “big room” on a project, and it worked.
In the night view of the main building, the LED light sculpture in the atrium is by Erwin Redl. Photo: Ed Hueber/Archphoto. Click to enlarge.
BUILDING TEAM
+Submitting firm: Turner Construction Co./STV Joint Venture (CM)
+Owner: New York City Department of Design and Construction
+Architect: Perkins+Will, with Michael Fieldman Consulting Architects
+Structural: Robert Silman Associates; Guy Nordenson and Associates Structural Engineers; Weidlinger Associates
+Civil, geotechnical consultant: Langan Engineering and Environmental Services
+MEP: WSP Global
+Interior storefront systems consultant: Permasteelisa
+Lighting consultants: Bartenbach; Hillman Dibernardo & Associates
+Land use review consultant: FXFOWLE Architects
+Landscaping consultants: Balmori Associates; HMWhite
GENERAL INFORMATION
Project size: 720,000 sf
Construction cost: confidential at client’s request
Construction period: December 2009 to
December 2015
Delivery method: Design-bid-build
Related Stories
Building Team Awards | May 31, 2016
Gonzaga's new student center is a bustling social hub
Retail mall features, comfortable furniture, and floor-to-ceiling glass add vibrancy to the new John J. Hemmingson Center.
Building Team Awards | May 26, 2016
Cimpress office complex built during historically brutal Massachusetts winter
Lean construction techniques were used to build 275 Wyman Street during a winter that brought more than 100 inches of snow to suburban Boston.
Building Team Awards | May 25, 2016
New health center campus provides affordable care for thousands of Northern Californians
The 38,000-sf, two-level John & Susan Sobrato Campus in Palo Alto is expected to serve 25,000 patients a year by the end of the decade.
Building Team Awards | May 24, 2016
Los Angeles bus depot squeezes the most from a tight site
The Building Team for the MTA Division 13 Bus Operations and Maintenance Facility fit 12 acres’ worth of programming in a multi-level structure on a 4.8-acre site.
Building Team Awards | May 23, 2016
'Greenest ballpark' proves a winner for St. Paul Saints
Solar arrays, a public art courtyard, and a picnic-friendly “park within a park" make the 7,210-seat CHS Field the first ballpark to meet Minnesota sustainable building standards.
Building Team Awards | May 20, 2016
Pittsburgh's Tower at PNC Plaza raises the bar on high-rise greenness
The Building Team designed the 800,000-sf tower to use 50% less energy than a comparable building. A 1,200-sf mockup allowed the team to test for efficiency, functionality, and potential impact on the building’s occupants.
Building Team Awards | May 19, 2016
Chinatown library unites and serves two emerging Chicago neighborhoods
The 16,000-sf, pebble-shaped Chinatown Branch Library was built at the intersection of new and old Chinatown neighborhoods. The goal is for the building to unite the communities and serve as a catalyst for the developing area.
Building Team Awards | May 19, 2016
NYC subway station lights the way for 300,000 riders a day
Fulton Center, which handles 85% of the riders coming to Lower Manhattan, is like no other station in the city’s vast underground transit web—and that’s a good thing.
Building Team Awards | May 16, 2016
Upstate New York performing arts center revives once-toxic lakefront site
Early coordination, prefabrication, and judicious value engineering contributed to the accelerated completion of the Onondaga Lakeview Ampitheater, a Upstate New York design-build project.