Rescue mission: Historic movie palace is now the centerpiece of Baltimore’s burgeoning arts hub

Reconstruction Awards

Rescue mission: Historic movie palace is now the centerpiece of Baltimore’s burgeoning arts hub

In restoring the theater, the design team employed what it calls a “rescued ruin” preservation approach.


By David Barista, Editorial Director | December 1, 2017

Photos: Karl Connolly Photography

Situated at the heart of Baltimore’s budding Arts & Entertainment District, the 1915 Italian Renaissance–style Parkway Theatre for years was representative of the city’s economic and social troubles.

Abandoned and neglected for decades (a grocery store once resided in the lobby), the theater was the first of its kind to show “synchronized sound” films, where sound and picture are recorded simultaneously.

In restoring the theater, the design team employed what it calls a “rescued ruin” preservation approach. Rather than identify a single period of significance, the team chose to recognize all eras of the past. In some instances, layers were removed to reveal hidden periods of history, while other instances incorporated fresh design elements—or a mix of old and new.

 

 

The marquee and original display cases were recreated from historic photographs from the original 1915 era. The cornice lights were restored and refashioned with modern LEDs.

The team downsized the main theater to optimize sight lines for larger screens and seats, and built a new projection booth to accommodate old and new technologies: 35mm film, projection, and HD.

 

 

Project Summary

 

Honorable Mention

Building Team: Ziger/Snead Architects (submitting firm, architect) Maryland Film Festival (owner) Structura (SE) James Posey Associates (MEP) Southway Builders (GC).

Details: 22,885 sf. Total cost: $9.9 million. Construction time: December 2015 to April 2017. Delivery method: CM at risk.

 

 

SEE ALL OF THE 2017 RECONSTRUCTION AWARD WINNERS HERE

Related Stories

Reconstruction Awards | Nov 16, 2016

Reconstruction Awards: Marilyn I. Walker School of Fine and Performing Arts, Brock University

The five-story brick-and-beam structure is an adaptive reuse of the Canada Hair Cloth Building, where coat linings and parachute silks were once made.

Reconstruction Awards | Nov 16, 2016

Reconstruction Awards: Marwen

Marwen currently offers 100 studio courses to 850 underserved students from 295 schools and 53 zip codes.

Reconstruction Awards | Nov 16, 2016

Reconstruction Awards: The Cigar Factory

The Cigar Factory was originally a cotton mill but became the home of the American Cigar Company in 1912. 

Reconstruction Awards | Nov 16, 2016

Reconstruction Awards: St. Patrick's Cathedral

The cathedral, dedicated in 1879, sorely needed work.

Reconstruction Awards | Nov 15, 2016

Reconstruction Awards: Lovejoy Wharf

After demolishing the rotten wood wharf, Suffolk Construction (GC) built a new 30,000-sf landscaped quay, now known as Lovejoy Wharf.

Reconstruction Awards | Nov 15, 2016

Reconstruction Awards: KETV-7 Burlington Station

The 1898 Greek Revival train terminal, which was listed on the National Register of Historic Places in 1974, had been abandoned for nearly four decades.

Reconstruction Awards | Nov 14, 2016

Reconstruction Awards: The Gallery at the Three Arts Club

On the exterior of the building, masonry and terra cotta were revitalized, and ugly fire escapes on the south façade were removed.

Reconstruction Awards | Nov 14, 2016

Big-box store rescaled to serve as a preventive-care clinic

The hospital was attracted to the big box’s footprint: one level with wide spans between structural columns, which would facilitate a floor plan with open, flexible workspaces and modules that could incorporate labs, X-ray, ultrasound, pharmacy, and rehab therapy functions.

Reconstruction Awards | Nov 14, 2016

Fire-charred synagogue rises to renewed glory

The blaze left the 110-year-old synagogue a charred shell, its structural integrity severely compromised. 

Reconstruction Awards | Nov 11, 2016

Adaptive reuse juices up an abandoned power plant

The power plant was on the National Register of Historic Places and is a Recorded Texas Historic Landmark.

boombox1 - default
boombox2 -
native1 -

More In Category


Giants 400

BD+C Awards Programs

Entry information and past winners for Building Design+Construction's two major awards programs: 40 Under 40 and Giants 400



halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021