Patient friendly: The University of Chicago Medicine Center for Care and Discovery adds 203 new beds

Reconstruction Awards

Patient friendly: The University of Chicago Medicine Center for Care and Discovery adds 203 new beds

Strict infection control and life safety measures were implemented to protect patients on other floors as work proceeded.


By Robert Cassidy, Executive Editor | November 27, 2017
A nurse station
A nurse station

Gilbane Building Company and Albert Kahn Associates completed the 204,000-sf buildout of two vacant floors at The University of Chicago Medicine Center for Care and Discovery, adding 203 new beds. Through the use of six-week, look-ahead planning, adherence to Lean construction principles, Gilbane’s own Quality in Construction program, and prefabrication (for headwalls, dialysis boxes, soffits, and ductwork and plumbing assemblies), the team was able to bring the job in two months ahead of schedule.

The trades used on-site monitors to access documents via Bluebeam Studio. UPC coding and BIM 360 also greased the flow of documents. Mockups of various rooms (med-surg, isolation, observation, ICU) gave medical staff the opportunity to offer input on headwall layouts, tile colors, soffit details, and flooring types.

Existing critical exhaust hoods in 24/7 support spaces were found to be inadequately sized for anticipated airflow. One option—to change the motors and sheaves on the exhaust fans—was ruled out as too disruptive to the operations of clinical departments. Instead, the team incorporated readily obtainable new fans into the existing exhaust system so that the original fans could be removed and modified. The solution saved the hospital considerable operational impacts.

Strict infection control risk assessment (ICRA) and interim life safety measures were put in place to meet the demands of eight separate hospital departments. Halfway through the project, the hospital required that all differential pressure monitors have remote monitoring capability. Gilbane engaged Primex Wireless, which tied a web-based reporting system into the hospital’s existing wireless network. This assured that any possible ICRA breach would be addressed instantaneously.

 

A patient room in the University of Chicago Medicine Center for Care and DiscoveryUnion construction crews put in 460,000 man-hours on the buildout of two patient floors at the University of Chicago Medicine Center for Care and Discovery without a lost-time incident. Nearly half (48%) of all trades workers were minorities, females, or both. Photo: Jon Miller / Hedrich Blessing Photographers.

 

Project Summary

 

Silver Award Winner

Building Team: Gilbane Building Company (submitting firm CM) Albert Kahn Associates (architect, SE, M/E engineer).

Details: 204,000 sf. Total cost: $98.3 million. Construction time: February 2015 to August 2016. Delivery method CM at risk.

 

See all of the 2017 Reconstruction Award winners here

Related Stories

Reconstruction Awards | Nov 16, 2016

Reconstruction Awards: Marilyn I. Walker School of Fine and Performing Arts, Brock University

The five-story brick-and-beam structure is an adaptive reuse of the Canada Hair Cloth Building, where coat linings and parachute silks were once made.

Reconstruction Awards | Nov 16, 2016

Reconstruction Awards: Marwen

Marwen currently offers 100 studio courses to 850 underserved students from 295 schools and 53 zip codes.

Reconstruction Awards | Nov 16, 2016

Reconstruction Awards: The Cigar Factory

The Cigar Factory was originally a cotton mill but became the home of the American Cigar Company in 1912. 

Reconstruction Awards | Nov 16, 2016

Reconstruction Awards: St. Patrick's Cathedral

The cathedral, dedicated in 1879, sorely needed work.

Reconstruction Awards | Nov 15, 2016

Reconstruction Awards: Lovejoy Wharf

After demolishing the rotten wood wharf, Suffolk Construction (GC) built a new 30,000-sf landscaped quay, now known as Lovejoy Wharf.

Reconstruction Awards | Nov 15, 2016

Reconstruction Awards: KETV-7 Burlington Station

The 1898 Greek Revival train terminal, which was listed on the National Register of Historic Places in 1974, had been abandoned for nearly four decades.

Reconstruction Awards | Nov 14, 2016

Reconstruction Awards: The Gallery at the Three Arts Club

On the exterior of the building, masonry and terra cotta were revitalized, and ugly fire escapes on the south façade were removed.

Reconstruction Awards | Nov 14, 2016

Big-box store rescaled to serve as a preventive-care clinic

The hospital was attracted to the big box’s footprint: one level with wide spans between structural columns, which would facilitate a floor plan with open, flexible workspaces and modules that could incorporate labs, X-ray, ultrasound, pharmacy, and rehab therapy functions.

Reconstruction Awards | Nov 14, 2016

Fire-charred synagogue rises to renewed glory

The blaze left the 110-year-old synagogue a charred shell, its structural integrity severely compromised. 

Reconstruction Awards | Nov 11, 2016

Adaptive reuse juices up an abandoned power plant

The power plant was on the National Register of Historic Places and is a Recorded Texas Historic Landmark.

boombox1 - default
boombox2 -
native1 -

More In Category


Giants 400

BD+C Awards Programs

Entry information and past winners for Building Design+Construction's two major awards programs: 40 Under 40 and Giants 400



halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021