World’s tallest modular building rises in Singapore

Modular Building

World’s tallest modular building rises in Singapore

The state has been pushing for improvements in construction management.


By John Caulfield, Senior Editor | July 3, 2019

Two 40-story residential towers in Singapore were built with nearly 1,900 prefabricated modules. Image: Courtesy of Bouygues Bâtiment International

Last week, construction of the world’s tallest modular buildings was completed in Singapore.

The Clement Canopy building consists of two 40-story towers with 505 luxury apartments, located in the heart of this city’s residential and Kent Ridge Education Belt districts. Each tower is 459 ft tall, and combined they are made up of 1,899 modules whose weight ranged from 37,000 to 64,000 lbs.

UOL Group, a leading real estate and property management firm in Singapore, is the project’s client as part of a development joint venture with Singland Homes. ADDP Architects was the project's architect.

Clement Canopy is the first structure on the island to use an all-concrete version of the Prefabricated Prefinished Volumetric Construction (PPVC) system, where freestanding modules, complete with finishes for walls, floors, and ceilings, are produced offsite and then assembled onsite, according to Concrete Construction magazine.

In April 2016, the Singapore government awarded Dragages Singapore, a subsidiary of France-based general contractor Bouygues Bâtiment International, the contract to design and build Clement Canopy. Aurélie Cleraux, Bouygues Bâtiment’s head of modular construction, tells BD+C that more than 60% of the two towers’ superstructure was built offsite. The modules were cast by a concrete precast manufacturer in Senei, Malaysia, in five days. (The project required a total of 48 module shapes.) The fitouts were completed in the contractor’s factory in Tuas, Singapore, within 15 days. The modules included mechanicals and plumbing, plastering, painting, and bathroom fixtures and tiles.

The contractor used two Liebherr 1000 EC-H 40 Litronic High-Top tower cranes to erect the towers. The Clement Canopy project was delivered in 30 months, six months ahead of its initial timeline. Cleraux says most of this period was spent in designing and planning.

Cleraux explains that there’s a big push by the Singapore government to improve construction productivity. And the benefits of modular and prefabrication processes, he says, are that they can reduce construction time by up to 50%, and reduce onsite labor by 30%. Other benefits include reduction of jobsite noise, pollution and neighborhood disruption; improvements in jobsite safety and the quality of the finished product, as well as the possible reuse of the building’s materials down the road.

In February 2018, Dragages Singapore won a €13 million ($9.6 million) contract to build six more 15-story residential buildings in Singapore whose reinforced concrete structures will be 65% factory built.  

“We are going to see a complete disruption in the next few years: our clients expect ever more efficient and faster building solutions,” Nicolas Borit, CEO of Bouygues Bâtiment International, told Global Construction Review last year. “Through the experience we have acquired on a number of projects, we are able to provide modular construction solutions today which fully meet their expectations, from design through to the construction of the final product.”

These six buildings were expected to take 33 months to complete.

Related Stories

Modular Building | Jul 22, 2016

PNC Bank’s 'Tiny Branch' opens on West Virginia University campus

The new branch doesn’t need much space for its ATM and new accounts and personal loans services.

Transit Facilities | Jun 12, 2016

Philippines’ oldest city getting its first public bus system

New York-based CAZA designed the modular bus stops with the city’s extreme weather conditions in mind.

Modular Building | May 17, 2016

Oklahoma’s first modular hotel will begin construction next month

Guerdon Modular Buildings will produce 81 modules for this project. 

Modular Building | Feb 26, 2016

CHPS releases new program, first model for prefab modular classrooms

Provides standards for indoor air quality, energy efficiency, materials, and waste management.

Game Changers | Feb 5, 2016

Asia’s modular miracle

A prefab construction company in China built a 57-story tower in 19 days. Here’s how they did it.  

Game Changers | Feb 4, 2016

GAME CHANGERS: 6 projects that rewrite the rules of commercial design and construction

BD+C’s inaugural Game Changers report highlights today’s pacesetting projects, from a prefab high-rise in China to a breakthrough research lab in the Midwest.

Modular Building | Feb 1, 2016

Hotel developers turn to modular construction to meet demand

A $90 million rebuilding project in Yellowstone National Park exemplifies this trend.

| Jan 14, 2016

How to succeed with EIFS: exterior insulation and finish systems

This AIA CES Discovery course discusses the six elements of an EIFS wall assembly; common EIFS failures and how to prevent them; and EIFS and sustainability.

Modular Building | Dec 13, 2015

Undaunted, Forest City pushes ahead on modular construction

The president of its FC Modular division says new projects are under consideration, even as competitors falter or fall by the wayside. 

Greenbuild Report | Dec 1, 2015

Data centers turn to alternative power sources, new heat controls and UPS systems

Data centers account for 2% of the nation’s electricity consumption and about 30% of the power used annually by the economy’s information and communications technology sector, according to the National Renewable Energy Laboratory.

boombox1 - default
boombox2 -
native1 -

More In Category




Modular Building

Building with shipping containers not as eco-friendly as it seems

With millions of shipping containers lying empty at ports around the world, it may seem like repurposing them to construct buildings would be a clear environmental winner. The reality of building with shipping containers is complicated, though, and in many cases isn’t a net-positive for the environment, critics charge, according to a report by NPR's Chloe Veltman.

halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021