flexiblefullpage -
billboard - default
interstitial1 - interstitial
catfish1 - bottom
Currently Reading

Massive Chicago parking garage gets overdue waterproofing

Reconstruction Awards

Massive Chicago parking garage gets overdue waterproofing

Millennium Lakeside Garage, the largest underground parking facility in the U.S., hadn’t been waterproofed since the 1970s. The massive project took nearly 2½ years and 33,554 man-hours.


By John Caulfield, Senior Editor | December 1, 2015
Massive Chicago parking garage gets overdue waterproofing maggie daley

Millennium Lakeside Garage in Chicago. Photos: Western Specialty Contractors

Millennium Lakeside Garage—the largest underground parking facility in the U.S., equal in size to 12 football fields—hadn’t been waterproofed since the 1970s. Waterproofing it in support of the construction of the $60 million Maggie Daley Park (named after the late wife of former Mayor Richard M. Daley) took nearly 2½ years and 33,554 man-hours.

BRONZE AWARD

Building Team: Western Specialty Contractors, formerly named Western Waterproofing Company; Desman Associates (architect, engineer); Kenny Construction (construction manager)
General Information: Size: 750,000 sf. Construction cost: $7 million. Construction time: April 2012 to December 2014. Delivery method: Design-bid-build

The waterproofing system (manufactured by American Hydrotech) consisted of seven layers: 1.3 million pounds of melted rubberized asphalt poured onto concrete, which needed to be constantly measured to make sure the spread was even and consistent, plus reinforced felt fabric, sheets of heavy-duty rubberized asphalt protection board, drainage mats, filter fabric, and 400,000 cubic feet of gravel overburden.

Once the garage was waterproofed, no trucks could drive on the surfaces. A large conveyor truck with an extra-long reach was used to shoot gravel over the waterproofing system. At the same time that waterproofing work was being completed on the top side of the garage roof, structural repairs were being performed on the underside of the roof slab. All told, 1,000 cubic feet of concrete were removed and replaced, which required 130,000 pounds of cement.

The garage, which slopes naturally north to south, was still plagued by pooling water problems, due to the lack of drains throughout the garage’s roof. The Building Team rectified this problem by installing numerous new drains and a composite drainage mat system.

 

Related Stories

Reconstruction Awards | Nov 16, 2016

Reconstruction Awards: Bay Area Metro Center

The structure’s 60,000-sf floor plates made the interior dark and foreboding, and BAHA wanted to improve working conditions for its employees and tenants. 

Reconstruction Awards | Nov 16, 2016

Reconstruction Awards: Marilyn I. Walker School of Fine and Performing Arts, Brock University

The five-story brick-and-beam structure is an adaptive reuse of the Canada Hair Cloth Building, where coat linings and parachute silks were once made.

Reconstruction Awards | Nov 16, 2016

Reconstruction Awards: Marwen

Marwen currently offers 100 studio courses to 850 underserved students from 295 schools and 53 zip codes.

Reconstruction Awards | Nov 16, 2016

Reconstruction Awards: The Cigar Factory

The Cigar Factory was originally a cotton mill but became the home of the American Cigar Company in 1912. 

Reconstruction Awards | Nov 16, 2016

Reconstruction Awards: St. Patrick's Cathedral

The cathedral, dedicated in 1879, sorely needed work.

Reconstruction Awards | Nov 15, 2016

Reconstruction Awards: Lovejoy Wharf

After demolishing the rotten wood wharf, Suffolk Construction (GC) built a new 30,000-sf landscaped quay, now known as Lovejoy Wharf.

Reconstruction Awards | Nov 15, 2016

Reconstruction Awards: KETV-7 Burlington Station

The 1898 Greek Revival train terminal, which was listed on the National Register of Historic Places in 1974, had been abandoned for nearly four decades.

Reconstruction Awards | Nov 14, 2016

Reconstruction Awards: The Gallery at the Three Arts Club

On the exterior of the building, masonry and terra cotta were revitalized, and ugly fire escapes on the south façade were removed.

Reconstruction Awards | Nov 14, 2016

Big-box store rescaled to serve as a preventive-care clinic

The hospital was attracted to the big box’s footprint: one level with wide spans between structural columns, which would facilitate a floor plan with open, flexible workspaces and modules that could incorporate labs, X-ray, ultrasound, pharmacy, and rehab therapy functions.

Reconstruction Awards | Nov 14, 2016

Fire-charred synagogue rises to renewed glory

The blaze left the 110-year-old synagogue a charred shell, its structural integrity severely compromised. 

boombox1 - default
boombox2 -
native1 -

More In Category


Giants 400

BD+C Awards Programs

Entry information and past winners for Building Design+Construction's two major awards programs: 40 Under 40 and Giants 400



halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021