flexiblefullpage -
billboard - default
interstitial1 - interstitial
catfish1 - bottom
Currently Reading

Jefferson Would Be Proud

Jefferson Would Be Proud

Extensive testing of materials, historical research, and delicate construction coordination went into the restoration and expansion of the nation's oldest continuously operating capitol building, originally designed by our third president.


By By Barbara Horwitz-Bennett, Contributing Editor | August 11, 2010
This article first appeared in the 200709 issue of BD+C.

The Virginia State Capitol Building—originally designed by Thomas Jefferson and almost as old as the nation itself—has proudly served as the oldest continuously used Capitol in the U.S.

But more than two centuries of wear and tear put the historical landmark at the head of the line for restoration.

The Building Team—led by the Gilbane Building and Christman Companies—installed entirely new M/E/P systems and added a 27,000-sf underground expansion featuring a visitors' center and ADA-compliant main entrance, office space and meeting rooms, and improved centralized security management.

However, digging near the building's foundation to create the underground expansion was no simple task. To prevent the building from moving, a slurry wall had to be constructed in a six-month process that involved excavating 10-foot sections, pumping bentonite grout to prevent the soil from collapsing, and then replacing the grout with concrete once each section was completed.

With the new entrance, visitors pass through the surrounding landscape, avoid climbing stairs, and are treated to a spectacular view from the south portico—the way Jefferson originally intended for the building to be viewed.

“Getting the tunnel in and making it work was quite a feat,” observed BD+C Renovation Awards judge K. Nam Shiu, P.E., S.E., MISE, VP, Walker Restoration Consultants, Chicago. “This project involved a great degree of discipline.”

To preserve the Capitol's historical splendor, dating back to 1906 when the east and west wings were added, extensive inspection, study, and research had to be conducted. Core samples were taken from the portico columns and key interior locations to assess the building's condition. Radar, metal detection, thermography, and ultrasound were utilized to assess the building's structure and layout. Scientists even chiseled away at the rotunda walls to determine the original paint color.

While working on the building's exterior, it was discovered that the stucco had been sealed with paint that prevented the building from breathing, thereby creating moisture and mold problems. Every speck of paint had to be removed, but due to the building's historical significance, only free-standing scaffolding could be utilized.

The stucco also had to be stripped so that damaged bricks could be replaced. Deteriorated mortar joints had to be tuck pointed with fresh, waterproof mortar. Finally, natural hydraulic lime stucco was applied to allow the building to breathe.

While all of the exterior doors were replaced and the building received a new roof, the original windows were temporarily removed, shipped to Kansas City, and restored. Even the original doorknobs bearing the Great Seal of Virginia were restored.

As for the Capitol's century-old granite steps, they had to be temporarily removed in sections weighing around 1,400 pounds in order to be repaired and restored. Once all the construction was completed, the steps were carefully returned to their original location.

During the meticulous process of restoring the Capitol, some areas of the building were found to be more deteriorated than projected. In addition, extensive testing of historic materials, in-depth historical research, and the application of specialized preservation techniques added to the project's complexity.

Judge Nam Shiu also pointed out the challenge of working on a hill and recognized the team's restoration efforts: “They also preserved all the environments and did not disturb the original entrance.”

The Building Team preserved Jefferson's legacy so future generations can enjoy this important American landmark.

Related Stories

Cultural Facilities | Sep 19, 2016

International competition recognizes insect-inspired design for Moscow Circus School

The proposal would make the school’s activities more transparent to the public.

Cultural Facilities | Sep 16, 2016

Competition to design Shanghai’s Pudong Art Museum is down to four firms

OPEN, SANAA Ateliers Jean Nouvel and David Chipperfield Architects are the final four firms competing for the opportunity to design the project.

Steel Buildings | Sep 15, 2016

New York’s Hudson Yards to feature 16-story staircase sculpture

The installation is designed by British architect Thomas Heatherwick and will be the centerpiece of the $200 million plaza project

Cultural Facilities | Sep 13, 2016

REX reveals The Perelman Center, the final structure for the World Trade Center campus

The cube-shaped building is clad in translucent book-matched marble.

Designers | Sep 13, 2016

5 trends propelling a new era of food halls

Food halls have not only become an economical solution for restauranteurs and chefs experiencing skyrocketing retail prices and rents in large cities, but they also tap into our increased interest in gourmet locally sourced food, writes Gensler's Toshi Kasai.

| Sep 1, 2016

CULTURAL SECTOR GIANTS: A ranking of the nation's top cultural sector design and construction firms

Gensler, Perkins+Will, PCL Construction Enterprises, Turner Construction Co., AECOM, and WSP | Parsons Brinckerhoff top Building Design+Construction’s annual ranking of the nation’s largest cultural sector AEC firms, as reported in the 2016 Giants 300 Report.

Events Facilities | Aug 31, 2016

New York State Pavilion re-imagined as modern greenhouse

The design proposal won a competition organized by the National Trust for Historic Preservation and People for the Pavilion group to find new uses for the abandoned structure.

Performing Arts Centers | Aug 31, 2016

Sydney Opera House scheduled for $200 million upgrade

Acoustical improvements will be made alongside upgrades in accessibility, efficiency, and flexibility.

| Aug 30, 2016

CONVENTION CENTER GIANTS: A ranking of the nation's top convention center sector design and construction firms

Gensler, LMN Architects, AECOM, Turner Construction Co., and WSP | Parsons Brinckerhoff top Building Design+Construction’s annual ranking of the nation’s largest convention center sector AEC firms, as reported in the 2016 Giants 300 Report.

Cultural Facilities | Aug 27, 2016

Yellowstone Park Foundation receives $1 million donation from Toyota

The money will support new eco-friendly and efficient buildings on the park’s Youth Campus.

boombox1 - default
boombox2 -
native1 -

More In Category

Cultural Facilities

Multipurpose sports facility will be first completed building at Obama Presidential Center

When it opens in late 2025, the Home Court will be the first completed space on the Obama Presidential Center campus in Chicago. Located on the southwest corner of the 19.3-acre Obama Presidential Center in Jackson Park, the Home Court will be the largest gathering space on the campus. Renderings recently have been released of the 45,000-sf multipurpose sports facility and events space designed by Moody Nolan.




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021