It only took 26 days to complete construction on the Crowne Plaza Changi Airport hotel extension

Hotel Facilities

It only took 26 days to complete construction on the Crowne Plaza Changi Airport hotel extension

PPVC techniques allowed the project to save time and manpower.


By David Malone, Associate Editor | July 5, 2017

Photo: Patrick Bingham-Hall

The Singapore Changi Airport is, according to the most recent numbers from the Airports Council International, the 17th busiest airport in the world by passenger traffic. With so many people passing through on a daily basis, it was important for the new addition to the Crowne Plaza Changi Airport hotel to be built in as little time as possible.

The new building was Singapore’s first private sector commercial project to use pre-fabricated, pre-finished volumetric construction (PPVC), which led to the addition being built in just 26 days. WOHA designed the original 320-room hotel as well as the 243-room, 103,495-sf addition.

 

Photo: Patrick Bingham-Hall.

 

The use of the PPVC method slashed manpower requirements on site by as much as 45%, reduced overall construction time by 17%, and accomplished both of these with about 40% in manpower savings.

 

Photo: Patrick Bingham-Hall.

 

“The Crowne Plaza Changi Airport hotel extension (CPEX) demonstrates that it is possible to significantly reduce the number of workers required, shorten construction time, improve building quality and even overcome site constraints by changing the way we build,” says Singapore’s Building and Construction Authority CEO John Keung in a release.

 

Photo: Patrick Bingham-Hall.

Related Stories

Retail Centers | May 10, 2016

5 factors guiding restaurant design

Restaurants are more than just places to eat. They are comprising town centers and playing into the future of brick-and-mortar retail.

Sports and Recreational Facilities | Apr 6, 2016

Las Vegas debuts another new arena, with a number of ‘firsts’

The gambling mecca has its eyes on attracting a pro sports team. 

Hotel Facilities | Mar 30, 2016

The Usonian Inn, a Frank Lloyd Wright-inspired motor lodge, is on the market for $665,000

The Usonian Inn proudly displays many Wright-inspired characteristics, the most prominent of which is the use of cantilevered overhangs.

Hotel Facilities | Mar 18, 2016

Starwood backs away from merger with Marriott

Hotel giant prefers higher, all-cash bid from China’s Anbang

Hotel Facilities | Mar 9, 2016

New hotel rooms generate an intergenerational battle

Hotels are going for a new minimalist look to attract younger guests, but some older business travelers don't like the small "desks"—and they don't want to work in the hotel lobby. But it's really all about trimming construction costs.

Hotel Facilities | Mar 7, 2016

Exclusive villas and spa in China will be built at the center of a lake

The only connection between the complex and the mainland will be a narrow pedestrian bridge.

Market Data | Feb 10, 2016

Nonresidential building starts and spending should see solid gains in 2016: Gilbane report

But finding skilled workers continues to be a problem and could inflate a project's costs.

Multifamily Housing | Feb 1, 2016

Top 10 kitchen design trends for 2016

Charging stations, built-in coffeemakers, and pet stations—these are among the top kitchen design trends for the coming year, according to a new survey of kitchen and bath designers by the National Kitchen & Bath Association.

Modular Building | Feb 1, 2016

Hotel developers turn to modular construction to meet demand

A $90 million rebuilding project in Yellowstone National Park exemplifies this trend.

Casinos | Jan 30, 2016

Boston ends its opposition to a casino, Wynn to build $1.7B resort

A judge’s ruling last year paved the way for Wynn Resorts to begin construction on a 33-acre gambling palace in Everett, Mass. 

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021