It only took 26 days to complete construction on the Crowne Plaza Changi Airport hotel extension

Hotel Facilities

It only took 26 days to complete construction on the Crowne Plaza Changi Airport hotel extension

PPVC techniques allowed the project to save time and manpower.


By David Malone, Associate Editor | July 5, 2017

Photo: Patrick Bingham-Hall

The Singapore Changi Airport is, according to the most recent numbers from the Airports Council International, the 17th busiest airport in the world by passenger traffic. With so many people passing through on a daily basis, it was important for the new addition to the Crowne Plaza Changi Airport hotel to be built in as little time as possible.

The new building was Singapore’s first private sector commercial project to use pre-fabricated, pre-finished volumetric construction (PPVC), which led to the addition being built in just 26 days. WOHA designed the original 320-room hotel as well as the 243-room, 103,495-sf addition.

 

Photo: Patrick Bingham-Hall.

 

The use of the PPVC method slashed manpower requirements on site by as much as 45%, reduced overall construction time by 17%, and accomplished both of these with about 40% in manpower savings.

 

Photo: Patrick Bingham-Hall.

 

“The Crowne Plaza Changi Airport hotel extension (CPEX) demonstrates that it is possible to significantly reduce the number of workers required, shorten construction time, improve building quality and even overcome site constraints by changing the way we build,” says Singapore’s Building and Construction Authority CEO John Keung in a release.

 

Photo: Patrick Bingham-Hall.

Related Stories

| Aug 11, 2010

Gold Award: Westin Book Cadillac Hotel & Condominiums Detroit, Mich.

“From eyesore to icon.” That's how Reconstruction Awards judge K. Nam Shiu so concisely described the restoration effort that turned the decimated Book Cadillac Hotel into a modern hotel and condo development. The tallest hotel in the world when it opened in 1924, the 32-story Renaissance Revival structure was revered as a jewel in the then-bustling Motor City.

| Aug 11, 2010

Silver Award: Palmer House Hilton Hotel & Shops Chicago, Ill.

Chicago's Palmer House Hilton holds the record for the longest continuously operated hotel in North America. It was originally built in 1871 by Potter Palmer, one of America's first millionaire developers. When it was rebuilt after the Great Chicago Fire it became the first hotel in the U.S. to put a telephone in every room.

| Aug 11, 2010

Gulf Coast Hotel's Stormy Road to Recovery

After his initial tour of the dilapidated 1850s-era Battle House Hotel, Ron Blount, construction manager with Retirement Systems of Alabama, said to his boss: “You need a priest more than you need a contractor.” Those words were more prescient to RSA's restoration of the historic Mobile landmark than he could have known at the time.

| Aug 11, 2010

Lifestyle Hotel Trends Around the World

When the Rocco Forte Collection opens the Verdura Golf & Spa Resort in Sicily in early 2009, the 200-room luxury property will be one of the world's newest lifestyle hotels. Lifestyle hotels cater to guests seeking a heightened travel experience, which they deliver by offering distinctive—some would say avant-garde, or even outrageous—architecture, room design, amenities, and en...

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021