Reconstruction Awards: St. Patrick's Cathedral

Reconstruction Awards

Reconstruction Awards: St. Patrick's Cathedral

The cathedral, dedicated in 1879, sorely needed work.


By BD+C Staff | November 16, 2016

The Building Team for St. Patrick’s Cathedral had the National Historic Landmark ready to greet Pope Francis on September 24, 2015, three months ahead of schedule. © John Baer / Building Images Photography

For sheer massiveness, the restoration of New York’s St. Patrick’s Cathedral is hard to beat. It took Structure Tone (CM) seven months just to build the 335-foot-high scaffolding—all the while safeguarding an average 15,000 visitors a day.

The cathedral, dedicated in 1879, sorely needed work. Using BIM 360 Field to track its progress, the Building Team made 300,000 repairs. Thirty-seven hundred stained glass panels were restored; a new, invisible venting system to create air movement was installed to protect the glass. A 200-foot undercroft with eight tunnels was renovated. The two rusted-out main doors, weighing 8,800 pounds each, were conserved using a titanium let for structural support and a coating system derived from the oil industry to prevent future condensation.

The team designed a fire-suppressant system like one used in submarines that employs a nitrogen mist to propel a much smaller amount of water than a conventional system. Structure Tone used a hand-powered trolley to install the fire system in the attic, saving $1.3 million.

 

The 335-foot scaffolding that Structure Tone erected over a seven-month period. © John Baer / Building Images Photography.

 

 

PROJECT SUMMARY 

 

Silver Award Winner | New York, N.Y.

Building Team: Structure Tone (submitting firm, CM); Trustees for the Cathedral of St. Patrick (owner); Zubatkin (owner’s representative); Murphy Burnham & Buttrick Architects (designer); Silman Associates (SE); Landmark Facilities Group (MEP); Langan Engineering, GB Geotechnics USA (geotechnics/surveying); Robin Key Landscape Architecture; Building Conservation Associates; and William Dailey Associates (codes).

Details: 160,000 sf. Construction cost: Confidential. Construction time: March 2012 to September 2015. Delivery method: CM at risk.

Related Stories

Government Buildings | Jan 9, 2023

Blackstone, Starwood among real estate giants urging President Biden to repurpose unused federal office space for housing

The Real Estate Roundtable, a group including major real estate firms such as Brookfield Properties, Blackstone, Empire State Realty Trust, Starwood Capital, as well as multiple major banks and CRE professional organizations, recently sent a letter to President Joe Biden on the implications of remote work within the federal government.

Giants 400 | Aug 11, 2021

BD+C Awards Programs

Entry information and past winners for Building Design+Construction's two major awards programs: 40 Under 40 and Giants 400

Reconstruction Awards | Mar 12, 2021

Call for entries: 2021 Reconstruction Awards

The 2021 Reconstruction Awards recognize the best reconstructed, renovated, or remodeled projects, based on overall design, engineering, and construction project quality. Entries are due July 16, 2021. 

Reconstruction Awards | Mar 12, 2021

2021 Reconstruction Awards Entry Information

Only projects completed or occupied between January 1, 2020 and July 16, 2021 are eligible.

Reconstruction Awards | Mar 12, 2021

2021 Reconstruction Awards 'How to Win' Tip Sheet

Keep this tip sheet handy when preparing your Reconstruction Awards entry, as these are some items on which your project will be judged.

Reconstruction Awards | Feb 5, 2021

The historic Maryland Theatre is reborn in Hagerstown

The Maryland Theatre project has won a Bronze Award in BD+C's 2020 Reconstruction Awards.

Reconstruction Awards | Jan 30, 2021

Repositioning of historic Sears Roebuck warehouse enlivens Boston’s Fenway neighborhood

Developer Samuels & Associates asked Elkus Manfredi Architects to reimagine the former Sears Roebuck & Co. warehouse in Boston’s Fenway neighborhood as a dynamic mixed-use destination that complements the high-energy Fenway neighborhood while honoring the building’s historical significance.

boombox1 - default
boombox2 -
native1 -

More In Category


Giants 400

BD+C Awards Programs

Entry information and past winners for Building Design+Construction's two major awards programs: 40 Under 40 and Giants 400



halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021