Reconstruction Awards: St. Patrick's Cathedral

Reconstruction Awards

Reconstruction Awards: St. Patrick's Cathedral

The cathedral, dedicated in 1879, sorely needed work.


By BD+C Staff | November 16, 2016

The Building Team for St. Patrick’s Cathedral had the National Historic Landmark ready to greet Pope Francis on September 24, 2015, three months ahead of schedule. © John Baer / Building Images Photography

For sheer massiveness, the restoration of New York’s St. Patrick’s Cathedral is hard to beat. It took Structure Tone (CM) seven months just to build the 335-foot-high scaffolding—all the while safeguarding an average 15,000 visitors a day.

The cathedral, dedicated in 1879, sorely needed work. Using BIM 360 Field to track its progress, the Building Team made 300,000 repairs. Thirty-seven hundred stained glass panels were restored; a new, invisible venting system to create air movement was installed to protect the glass. A 200-foot undercroft with eight tunnels was renovated. The two rusted-out main doors, weighing 8,800 pounds each, were conserved using a titanium let for structural support and a coating system derived from the oil industry to prevent future condensation.

The team designed a fire-suppressant system like one used in submarines that employs a nitrogen mist to propel a much smaller amount of water than a conventional system. Structure Tone used a hand-powered trolley to install the fire system in the attic, saving $1.3 million.

 

The 335-foot scaffolding that Structure Tone erected over a seven-month period. © John Baer / Building Images Photography.

 

 

PROJECT SUMMARY 

 

Silver Award Winner | New York, N.Y.

Building Team: Structure Tone (submitting firm, CM); Trustees for the Cathedral of St. Patrick (owner); Zubatkin (owner’s representative); Murphy Burnham & Buttrick Architects (designer); Silman Associates (SE); Landmark Facilities Group (MEP); Langan Engineering, GB Geotechnics USA (geotechnics/surveying); Robin Key Landscape Architecture; Building Conservation Associates; and William Dailey Associates (codes).

Details: 160,000 sf. Construction cost: Confidential. Construction time: March 2012 to September 2015. Delivery method: CM at risk.

Related Stories

Reconstruction Awards | Jan 6, 2021

University of Pennsylvania’s Stemmler Hall forgoes retrofit in favor of complete renovation

The Edward J. Stemmler Hall project has won a Bronze Award in BD+C’s 2020 Reconstruction Awards.

Reconstruction Awards | Dec 29, 2020

The reenvisioned Sazerac House: A delectable cocktail that's just perfect for the Big Easy

The 51,987-sf Sazerac House is an interactive cocktail museum, active distillery, corporate headquarters, and event venue, all under one roof, next to the historic French Quarter of New Orleans.

Reconstruction Awards | Dec 18, 2020

Can converting a landmark office to a clinic raise up a downtrodden Philadelphia neighborhood?

BD+C’s Reconstruction Awards recognize the adaptive reuse of the Kensington Trust building.

Reconstruction Awards | Dec 18, 2020

Spokane Riverfront Park U.S. Pavilion project creates a refreshed gathering place in Spokane

The project has won a Bronze Award in BD+C's 2020 Reconstruction Awards.

Reconstruction Awards | Dec 16, 2020

Voters resuscitate an abandoned high school in northern California

A 2014 bond issue provided financing to seismically stabilize and modernize Historic Alameda High School, a 2020 Silver Reconstruction Award winner.

Reconstruction Awards | Dec 14, 2020

Wyoming Capitol Square renovation project is all about the details

The Wyoming Capitol Square project has won a Gold Award in BD+C's 2020 Reconstruction Awards.

Reconstruction Awards | Dec 12, 2020

A famed dome of a historic glasshouse is revived to its rightful glory

Scaffolding played a critical role in the repair and restoration of the Enid A. Haupt Conservatory’s Palm Dome at the New York Botanical Gardens, a Gold winner of BD&C’s 2020 Reconstruction Awards

Reconstruction Awards | Dec 8, 2020

A synagogue in Toronto is renewed while preserving its history

Holy Blossom Temple is a Platinum winner in BD+C’s 2020 Reconstruction Awards.

boombox1 - default
boombox2 -
native1 -

More In Category


Giants 400

BD+C Awards Programs

Entry information and past winners for Building Design+Construction's two major awards programs: 40 Under 40 and Giants 400



halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021