U.K.’s Manchester Airport tower constructed in nine days

U.K.’s Manchester Airport tower constructed in nine days

Time-lapse video shows construction workers on the jobsite for 222 continuous hours.


By By BBC | March 29, 2012

A 197 ft air traffic control tower has been built in nine days at Manchester Airport in the U.K. The shaft of the £16m tower, which will house air traffic controllers from 2013, was built using a method of continuous concrete pouring.

The process required teams of 20 construction workers to work around the clock for 222 hours, with an average height increase of 10 in per hour. The crews poured 21,188 cf of concrete over 65 tons of reinforced steel to create the tower. The building of the tower coincides with the introduction of a new air traffic control system at the airport, which has seen controllers moving from paper logs to a digital system.

Click here to see time-lapse footage of the construction. BD+C

Related Stories

Libraries | Jan 29, 2018

Commercial plane that skidded off the runway may become Turkey’s newest public library

The plane was removed from its cliffside perch five days after the incident.

Giants 400 | Oct 5, 2017

On wings of gold: Alternative financing schemes are propelling the high-flyin’ air terminals sector

The $4 billion renovation of New York City’s LaGuardia Airport is the first major U.S. aviation project delivered using a public-private partnership (P3) model.

Giants 400 | Oct 3, 2017

Top 30 airport engineering firms

AECOM, Burns & McDonnell, and Arup top BD+C’s ranking of the nation’s largest airport sector engineering and EA firms, as reported in the 2017 Giants 300 Report.

Airports | Sep 11, 2017

Terminal modernization: Why bother? Part I

A terminal modernization program can be a complicated and expensive task that airport operators may be hesitant to undertake unless necessitated by demands for increased capacity. This is the first post in our series examining why airport operators should bother to upgrade their facilities, even if capacity isn’t forcing the issue.   

Hotel Facilities | Jul 5, 2017

It only took 26 days to complete construction on the Crowne Plaza Changi Airport hotel extension

PPVC techniques allowed the project to save time and manpower.

Airports | Jun 26, 2017

Newark Liberty International Airport breaks ground on $2.4 billion redevelopment project

The project includes a new 1 million-sf terminal building with 33 domestic aircraft gates.

Building Team Awards | Jun 8, 2017

Missing link: Denver International Airport and Transit Center

Gold Award: A new mixed-use transit center fulfills Denver’s 28-year plan to improve access to the nation’s fifth-busiest airport.

Airports | May 15, 2017

Five trends for airport retail

CallisonRTKL Vice President Kevin Horn pinpoints how travel retail is changing dramatically.

Reconstruction & Renovation | Mar 16, 2017

Pols are ready to spend $1T on rebuilding America’s infrastructure. But who will pick which projects benefit?

The accounting and consulting firm PwC offers the industrial sector a five-step approach to getting more involved in this process.

Airports | Feb 23, 2017

New Orleans Airport to add five additional gates and $110 million to current expansion

The project is being hailed as the city’s most transformative since the construction of the Superdome.

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021