Turner streamlines construction progress tracking using predictive visual data analytics

BIM and Information Technology

Turner streamlines construction progress tracking using predictive visual data analytics

The construction giant teams with a computer science and engineering professor to develop a clever drone- and rover-based construction monitoring tool.


By David Barista, Editorial Director | April 8, 2016
Turner streamlines construction progress tracking using predictive visual data analytics

Using images captured with a drone, the team creates a point cloud that is overlaid atop a 4D as-built model to compare real world to the intended design. The comparison report uses colors to point out problem areas (yellow indicates a missing element). Courtesy Turner.

In the race to develop tech tools to make meaningful efficiency gains in the complex, often-messy commercial construction process, the R&D team at Turner Construction Company has remained keenly focused on one goal: simplicity.

New tools and processes must be easy to execute, by almost anyone in the field, and take advantage of readily accessible data—photos, video—to solve real-world problems. Leave the mind-bogglingly complicated data analysis work to computer scientists like Mani Golparvar-Fard. 

Turner’s multi-year partnership with Golparvar-Fard, an Assistant Professor of Engineering and Computer Science at the University of Illinois at Urbana-Champaign, and a former Turner field engineer, has led to the development of breakthrough analytics tools that use structure from motion (SfM) algorithms to make sense of a job site, in real time, using high-definition photos and video.

Now, the technology is being piloted in the field, on the Sacramento Kings’ new 17,500-seat Golden 1 Center project, currently under construction in downtown Sacramento, Calif.

“Over the past 10 years, we’ve built these amazing 4D and 5D BIM models to help us plan our large commercial construction projects,” says Lincoln Wood, Regional Manager, Virtual Design and Construction, based in Turner’s Oakland, Calif., office. “But we still face the challenge of knowing what’s happening out in the field in real time.”

 

The initial phase of the pilot project involves using aerial drones (right) to document the construction progress. Once the structure goes up, the team will utilize a custom-built rover (left), as well as project engineers, to capture images and video. “The goal is to do this every day,” says Lincoln Wood, Regional Manager, Virtual Design and Construction, with Turner. “With the pilot, we have it down to a week, in time for the weekly work plan.” Courtesy Turner. Click image to enlarge.

 

Using proprietary predictive visual data analytics software developed by Golparvar-Fard, the Building Team for the Golden 1 Center project is conducting near-real-time construction progress monitoring using high-resolution photos and video. The initial phase involves reality capture with an aerial drone. As the arena structure goes up, the team will also rely on a camera-equipped land rover (which will be programmed to navigate the interior spaces) and project engineers, who will use smartphones and tablets to gather photos and video.

Once collected, the visual data is stitched together using the SfM algorithm to form a point cloud. The point cloud is then overlaid atop the project’s 4D BIM model to compare and contrast what is happening in the field versus the intended result in the BIM model. (The point cloud creation and BIM overlay work occurs overnight.)

The resulting report is a color-coded 3D visual production model that provides the Building Team with a snapshot of the construction progress, and, most importantly, the areas of the job site that are at risk of falling behind schedule. 

By streamlining construction progress monitoring, and providing timely reporting, Wood says the project team has a much deeper level of transparency and improved communication.

“A really good superintendent can see everything in their head; they don’t need a BIM model—it’s in their brain,” says Wood. “Unfortunately, the whole project team does not have that brain. This is a great way for the entire team to see where we are and show what we need to do in order to get back on track and improve the schedule.”

Based on the results of the job site scan and analysis, custom reports are generated for each member of the project management team, including key subcontractors, for the weekly planning meetings.

“The goal is to do this every day,” says Wood. “With the pilot, we have it down to a week, in time for the weekly work plan. We give this report to the team, showing the problem areas and the top-10 risks to the job site. It allows us to visualize and mitigate potential risks to our schedule before they happen.”

Wood says that the enhanced construction progress data may eventually be used for faster and more accurate subcontractor payments, “by removing a lot of the administrative work that happens by having to go back and forth between the job site and the office.”

It also equips the Building Team and owner with “smarter” and more-comprehensive visual documentation of the construction work, by automatically organizing and cataloging thousands of photos and video clips. 

“With most jobs, the project engineers are asked to take a bunch of photographs when they’re out in the field, if they have time after their RFIs and submittals are completed for the day,” says Wood. Those images then must be uploaded to the project server, where they are stored with a random code and remain largely unorganized.

“Because our images are stitched together to create a point cloud, we have a better sense of a record of time,” says Wood.

 

Courtesy Turner. Click image to enlarge.

Related Stories

BIM and Information Technology | Apr 24, 2017

Reconciling design energy models with real world results

Clark Nexsen’s Brian Turner explores the benefits and challenges of energy modeling and discusses how design firms can implement standards for the highest possible accuracy.

BIM and Information Technology | Apr 17, 2017

BIM: What do owners want?

Now more than ever, owners are becoming extremely focused on leveraging BIM to deliver their projects.

Sustainable Design and Construction | Apr 5, 2017

A new app brings precision to designing a building for higher performance

PlanIt Impact's sustainability scoring is based on myriad government and research data.

BIM and Information Technology | Mar 28, 2017

Digital tools accelerated the design and renovation of one contractor’s new office building

One shortcut: sending shop drawings created from laser scans directly to a wood panel fabricator.

BIM and Information Technology | Mar 13, 2017

Real-time, high-speed scanning – The latest in reality capture

Here are a few new reality capture products and platforms that caught our eye.

BIM and Information Technology | Mar 10, 2017

'Reality modeling' arrives

Advanced reality capture technologies are breaking down the barriers between the job site and project models.

BIM and Information Technology | Feb 6, 2017

BIM for O+M: Less about the model, more about the data

How one Building Team is giving a university client what its facilities staff really wants from BIM: information, please.

Codes and Standards | Jan 13, 2017

New BIM guide for owners released

National Institute of Building Sciences releases a manual for developing standard set of BIM documents.

Designers | Jan 13, 2017

The mind’s eye: Five thoughts on cognitive neuroscience and designing spaces

Measuring how the human mind responds to buildings could improve design.

Architects | Oct 11, 2016

A good imagination and a pile of junk: How maker culture is influencing the way AEC firms solve problems

“Fail” is no longer a dirty four-letter word: for maker culture, it has become a crucial stop along the way

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021