Stalled Conference House Park pavilion renovation moving forward

Reconstruction & Renovation

Stalled Conference House Park pavilion renovation moving forward

The pavilion has been awaiting repair since storm damage in 2011 rendered the structure unsafe for the public.


By David Malone, Associate Editor | February 16, 2017

Rendering courtesy of Sage and Coombe

In 2002, the pavilion in Staten Island’s Conference House Park, which is located in an area that makes it very prone to storm damage, was rebuilt as part of a $14 million park renovation project. But not even 10 years later, in 2011, the pavilion was closed due to weather damage to the roof and deck that forced the city to deem the structure unsafe for the public. Almost six full years later, the pavilion is still closed and awaiting repair.

A $3.7 million renovation has been in place for the pavilion, but, as Curbed New York reports, a series of setbacks has kept the project from progressing. The project received funding in 2015, but stalled due to inter-agency conflict. Later, in 2016, construction was also set to begin, but was once again delayed.

However, it appears as though construction on the project will finally get underway this year, as the Department of Parks has issued an invitation for construction bids.

Once completed (if another delay is indeed avoided) the new pavilion will provide 4,200 sf of space and can be used for weddings, concerts, or other public events. Sage and Coombe designed the new pavilion.

Related Stories

| Apr 13, 2011

Office interaction was the critical element to Boston buildout

Margulies Perruzzi Architects, Boston, designed the new 11,460-sf offices for consultant Interaction Associates and its nonprofit sister organization, The Interaction Institute for Social Change, inside an old warehouse near Boston’s Seaport Center.

| Mar 11, 2011

Holiday Inn reworked for Downtown Disney Resort

The Orlando, Fla., office of VOA Associates completed a comprehensive interior and exterior renovation of the 14-story Holiday Inn in the Downtown Disney Resort in Lake Buena Vista, Fla. The $25 million project involved rehabbing the hotel’s 332 guest rooms, atrium, swimming pool, restaurant, fitness center, and administrative spaces.

| Mar 11, 2011

Blockbuster remodel transforms Omaha video store into a bank

A former Hollywood Video store in Omaha, Neb., was renovated and repurposed as the SAC Federal Credit Union, Ames Branch. Architects at Leo A Daly transformed the outdated 5,000-sf retail space into a modern facility by wrapping the exterior in poplar siding and adding a new glass storefront that floods the interior with natural light.

| Mar 11, 2011

Historic McKim Mead White facility restored at Columbia University

Faculty House, a 1923 McKim Mead White building on Columbia University’s East Campus, could no longer support the school’s needs, so the historic 38,000-sf building was transformed into a modern faculty dining room, graduate student meeting center, and event space for visiting lecturers, large banquets, and alumni organizations.

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021