PPP gets the job done: Three-party deal saves time and money for client

Building Team Awards

PPP gets the job done: Three-party deal saves time and money for client

Bronze Award: Weitz, acting as developer and design-builder, leased the land and borrowed the money for the project.


By Robert Cassidy, Executive Editor | June 20, 2019

The 330-room Hilton Des Moines Downtown was developed through a three-party public-private partnership. Inset: Pivotek delivers one of 300 bath pods use in the project. Photos: Michael Robinson.

Four years ago, The Weitz Company formed a public-private partnership with the city of Des Moines and Polk County, Iowa, for a $101 million hotel/convention center in downtown Des Moines.

Weitz, acting as developer and design-builder, leased the land and borrowed the money for the project. The city and county formed the nonprofit Iowa Events Center Hotel Corp. to create a lease-purchase agreement for the property upon completion.

Weitz, DLR Group (design architect), RDG Planning & Design (AOR), and Raker Rhodes Engineering (SE) employed upfront planning to create parallel paths of construction. They used virtual reality to integrate 3D design models with the 3D construction model. The VR model served as a sales tool for Hilton and Greater Des Moines Convention & Visitors Bureau.

To address the shortage of skilled labor, Weitz, M/P engineer Waldinger, and Pivotek installed 300 bathroom pods that were built off site at Pivotek’s West Chester, Ohio, factory. This saved 11% in labor hours for each prefabbed bathroom and saved 7.5% in total construction costs.

 

Photo: Phillip Nicolino.

 

The team used 12 modular components—drain assemblies, PEX risers, aquatherm pressurized piping, framing, and pre-hardware doors. Weitz calculates the use of prefab components saved 3,750 trips to collect materials or remove trash from the job site.

The project was delivered 10 days ahead of schedule. Hilton took occupancy 30 days sooner than planned.+

 

Building Team — Submitting firm The Weitz Company (developer/design-builder) Owner Polk County, Iowa Hotel consultant Project Management Consultants Design architect DLR Group AOR RDG Planning & Design SE Raker Rhodes Engineering CE Snyder and Associates M/P The Waldinger Corp. EE Baker Electric Interior framing/finish Allied Construction Services

General information — Size 336,000 sf with conference space Cost $101 million Construction time April 2016 to March 2018 Delivery method Design-build lump-sum public-private partnership

 

Return to the Building Team Awards landing page

Related Stories

Architects | Jan 18, 2016

EHDD’s Monterey Bay Aquarium wins AIA Twenty-five Year Award

The aquarium set new technical standards for the building type, which still influence today, such as the flow-through seawater-based heat pump system, naturalistic exhibitions, and corrosion protection.

Building Team Awards | Apr 10, 2015

14 projects that push AEC teaming to the limits

From Lean construction to tri-party IPD to advanced BIM/VDC coordination, these 14 Building Teams demonstrate the power of collaboration in delivering award-winning buildings. These are the 2015 Building Team Award winners.

Building Team Awards | Apr 10, 2015

Prefab saves the day for Denver hospital

Mortenson Construction and its partners completed the 831,000-sf, $623 million Saint Joseph Hospital well before the January 1, 2015, deadline, thanks largely to their extensive use of offsite prefabrication.

Building Team Awards | Apr 10, 2015

Anaheim’s soaring intermodal hub

Anaheim's Regional Transportations Intermodal Center is the largest ETFE project in North America.

Building Team Awards | Apr 10, 2015

Virtual collaboration helps complete a hospital in 24 months

PinnacleHealth needed a new hospital STAT! This team delivered it in two years, start to finish.

Building Team Awards | Apr 10, 2015

New arts venue reinvigorates Virginia Tech's campus

The STV-led Building Team creates a world-class performance and arts venue with learning and entrepreneurial dimensions.

Building Team Awards | Apr 9, 2015

Multifaced fitness center becomes campus landmark

A sloped running track and open-concept design put this Building Team to the test. 

Building Team Awards | Apr 9, 2015

Nation's first LEED-certified bus depot

A bus garage in Harlem shows that even the most mundane of facilities can strut its environmentally sensitive stuff.

Building Team Awards | Apr 9, 2015

Setting the bar for port-of-entry design

Whenever you eat a tomato from Mexico, there’s a one-in-three chance it came through this LEED Gold gateway.

Building Team Awards | Apr 9, 2015

Big D’s billion-dollar baby: New Parkland Hospital Tops the Chart | BD+C

Dallas’s new $1.27 billion public hospital preserves an important civic anchor, Texas-style.

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021