Lake Washington STEM school combines modular and site-built construction to meet ambitious schedule

Lake Washington STEM school combines modular and site-built construction to meet ambitious schedule

New high school built in just seven months thanks to modular construction


By M SPACE | June 10, 2013
When the Lake Washington School District outside Seattle needed a new high school built on an ambitious permitting and construction schedule of seven months, modular construction proved to be an ideal solution.
 
“Conventional construction just wasn’t an option,” said Allan Long, Sr. Project Manager for M SPACE, the modular contractor for the project.
 
The LWSD ran into various permitting issues restricting site work on a new Science, Technology, Engineering and Math (STEM) school that was set to open in the fall of 2012. Since the modular process allows the bulk of construction to be done offsite in a factory, with minimal site disruption, the LWSD chose modular as the solution to its challenges.
 
The school is now serving 300 students, and by 2014, will be at near capacity with 600 9th-12th graders.
 
Integrus Architects, the designer on the project, began working the modular aspect of the project into it from the beginning, according to Yong Sun Lee, project manager with Integrus.
 
 
 
 
“In schematic design, we met with and toured various modular manufacturers’ facilities to understand the fabrication process,” Lee said. 
 
“It was in the early stages that we were sensitive to issues of modular dimensions (transportation widths and heights), structure and material types.  In design development, we maintained communication with the participating modular manufacturers and dealers with constructability/design insight,” she said. 
 
Blazer Industries in Oregon began building the “mods” in April 2012, and M SPACE started craning them into place in July 2012.  The school was constructed in two phases, with the first phase ending in August 2012. M SPACE contracted with Absher Construction as the onsite GC for the civil work, modular construction, roofing, sprinkler system and mechanical, electrical and plumbing.
 
 
 
 
M SPACE began setting the second phase in September 2012 and finished the following month, with the remaining site work completed by March 2013. With the two phases combined, the permanent 65,000 square-foot two-story school has 24 classrooms, a presentation hall, common areas, administrative offices and a nurse’s office. Additional features include photovoltaic panels in part of the roof, storefront windows, power cord reels in the science studios, two-hour rated walls, and light dimming ballasts in fixtures.
 
Four spaces in the school were site built, allowing modular and traditional construction to be combined to best suit the client’s need. The site-built commons has 22-foot ceilings, offering an open and inviting space for students. The top of the commons – the roof mods – were built in the factory, reducing the amount of time that workers had to spend at significant heights, according to Alan Duer, M SPACE Pacific Northwest Territory Manager.
 
“Mixing modular construction with conventional construction proved to be a valid alternative to the old ways of building,” Duer said. 
 
To learn more about the school, please visit the M SPACE website.
 
 
 

Related Stories

| Apr 11, 2012

Shawmut appoints Tripp as business development director

Tripp joined Shawmut in 1998 and previously held the positions of assistant superintendent, superintendent, and national construction manager.

| Apr 11, 2012

Corgan & SOM awarded contract to design SSA National Support Center

The new SSA campus is expected to meet all Federal energy and water conservation goals while achieving LEED Gold Certification from the United States Green Building Council.

| Apr 11, 2012

C.W. Driver completes Rec Center on CSUN campus

The state-of-the-art fitness center supports university’s goal to encourage student recruitment and retention.

| Apr 10, 2012

JE Dunn completes two medical office buildings at St. Anthony’s Lakewood, Colo. campus

Designed by Davis Partnership Architects, P.C., Medical Plaza 1 and 2 are four-story structures totaling 96,804-sf and 101,581-sf respectively.

| Apr 10, 2012

THINK [about architecture] Scholarship enters 15th year

Students are invited to submit two-minute creative videos that illustrate how they interact with their school's design and what the space makes possible.

| Apr 10, 2012

Structured Development & Bucksbaum close on new retail site in Chicago

The site is the location of New City, a mixed-use development that will feature 370,000-sf of retail space and 280 residential rental units.

| Apr 10, 2012

Moriarty & Associates selected as GC for Miami’s BrickellHouse Condo

Construction of the 46-story development is schedule to get underway this summer and be completed in 2014.

| Apr 6, 2012

Flat tower green building concept the un-skycraper

A team of French designers unveil the “Flat Tower” design, a second place winner in the 2011 eVolo skyscraper competition.

boombox1 - default
boombox2 -
native1 -

More In Category



AEC Tech

Lack of organizational readiness is biggest hurdle to artificial intelligence adoption

Managers of companies in the industrial sector, including construction, have bought the hype of artificial intelligence (AI) as a transformative technology, but their organizations are not ready to realize its promise, according to research from IFS, a global cloud enterprise software company. An IFS survey of 1,700 senior decision-makers found that 84% of executives anticipate massive organizational benefits from AI. 


Codes and Standards

Updated document details methods of testing fenestration for exterior walls

The Fenestration and Glazing Industry Alliance (FGIA) updated a document serving a recommended practice for determining test methodology for laboratory and field testing of exterior wall systems. The document pertains to products covered by an AAMA standard such as curtain walls, storefronts, window walls, and sloped glazing. AAMA 501-24, Methods of Test for Exterior Walls was last updated in 2015. 

halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021