It only took 26 days to complete construction on the Crowne Plaza Changi Airport hotel extension

Hotel Facilities

It only took 26 days to complete construction on the Crowne Plaza Changi Airport hotel extension

PPVC techniques allowed the project to save time and manpower.


By David Malone, Associate Editor | July 5, 2017

Photo: Patrick Bingham-Hall

The Singapore Changi Airport is, according to the most recent numbers from the Airports Council International, the 17th busiest airport in the world by passenger traffic. With so many people passing through on a daily basis, it was important for the new addition to the Crowne Plaza Changi Airport hotel to be built in as little time as possible.

The new building was Singapore’s first private sector commercial project to use pre-fabricated, pre-finished volumetric construction (PPVC), which led to the addition being built in just 26 days. WOHA designed the original 320-room hotel as well as the 243-room, 103,495-sf addition.

 

Photo: Patrick Bingham-Hall.

 

The use of the PPVC method slashed manpower requirements on site by as much as 45%, reduced overall construction time by 17%, and accomplished both of these with about 40% in manpower savings.

 

Photo: Patrick Bingham-Hall.

 

“The Crowne Plaza Changi Airport hotel extension (CPEX) demonstrates that it is possible to significantly reduce the number of workers required, shorten construction time, improve building quality and even overcome site constraints by changing the way we build,” says Singapore’s Building and Construction Authority CEO John Keung in a release.

 

Photo: Patrick Bingham-Hall.

Related Stories

| Jan 15, 2012

Smith Consulting Architects designs Flower Hill Promenade expansion in Del Mar, Calif.

The $22 million expansion includes a 75,000-square-foot, two-story retail/office building and a 397-car parking structure, along with parking and circulation improvements and new landscaping throughout.

| Dec 5, 2011

SchenkelShultz Architecture designs Dr. Phillips Charities Headquarters building in Orlando

The building incorporates sustainable architectural features, environmentally friendly building products, energy-efficient systems, and environmentally-sensitive construction practices.

| Nov 28, 2011

Leo A Daly and McCarthy Building complete Casino Del Sol expansion in Tucson, Ariz.

Firms partner with Pascua Yaqui Tribe to bring new $130 million Hotel, Spa & Convention Center to the Tucson, Ariz., community.

| Nov 11, 2011

How Your Firm Can Win Federal + Military Projects

The civilian and military branches of the federal government are looking for innovative, smart-thinking AEC firms to design and construct their capital projects. Our sources give you the inside story.

| Nov 9, 2011

American Standard Brands joins the Hospitality Sustainable Purchasing Consortium

  American Standard will collaborate with other organizations to build an industry-wide sustainability performance index.

| Nov 3, 2011

GREC Architects announces opening of the Westin Abu Dhabi Golf Resort and Spa

The hotel was designed by GREC and an international team of consultants to enhance the offerings of the Abu Dhabi Golf Club without imposing upon the dramatic landscapes of the elite golf course.

| Nov 3, 2011

Hardin Construction tops out Orlando Embassy Suites

The project began in April 2011 and is expected to open in fall 2012.

| Nov 2, 2011

John W. Baumgarten Architect, P.C, wins AIA Long Island Chapter‘s Healthcare Award for Renovation

The two-story lobby features inlaid marble floors and wood-paneled wainscoting that pays homage to the building’s history.

| Sep 26, 2011

Energy efficient LED flat panels installed at N.Y. metro hospitals

LED Flat Panels deliver fully dimmable, energy efficient high quality lighting with even, shadow-free distribution, and excellent 85 Color Rendering Index. 

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021