Good neighbor: Wentz Science Center at North Central College

Building Team Awards

Good neighbor: Wentz Science Center at North Central College

Bronze Award: A conscientious Building Team takes steps to minimize the impact of this large-scale science center project in a historic neighborhood.


By David Barista, Editorial Director | May 24, 2018
The science center is situated along a pedestrian walkway

The science center is situated along a pedestrian walkway that connects the north and south ends of campus. Steve Woltmann Photography.

Located in the heart of the third-largest suburb of Chicago—and one of its most prominent cities—North Central College has been an anchor and dedicated community member in Naperville for more than 155 years. The 3,000-student, 65-acre campus is surrounded by historic residential neighborhoods, just blocks from the quaint downtown.     

The school’s newest addition, the 124,000-sf Wentz Science Center, sits on the edge of campus and was designed to engage the surrounding neighborhoods, as well as students and faculty. Public areas and flexible spaces—including a sandwich shop and events space—were incorporated into the facility to draw in the general public.

To address concerns over the size and scale of the science building, the project team worked closely with community leaders to optimize the design and programming for minimal disruption to the neighborhood. On the building’s east façade, which faces the residential neighborhood, the windows were downsized and the overall architectural expression was restrained to reflect the scale of the historic homes across the street. To minimize noise and movement, the building’s quiet functions—namely academic offices—were located along this perimeter.

By contrast, the west façade, which faces the center of campus, is designed to showcase the action within the facility. Public areas, labs, classrooms, and other lively spaces were placed along this perimeter. Large windows and three-story glass curtain wall elements maximize transparency, daylighting, and views of the campus. Electrochromic glass was installed along this façade to control solar heat gain, glare, and daylighting. The construction team built full-scale mockups to determine the best approach and to work through design and installation issues related to the dynamic glazing.

After construction commenced, the client requested that the project schedule be compressed by six weeks so that the building could be occupied by the spring semester. To meet the condensed schedule, the team employed a variety of Lean tactics, including pull-planning and streamlined overtime budgets. Rather than tracking overtime by trade, each company condensed all overtime in one collective budget. Each week during pull-planning, the team assessed what critical path trades made the most sense to work weekends based on how that work would advance the overall schedule and where the team could deliver the maximum value.

As a result, the project opened ahead of the revised schedule, and under budget.

 

Students gather in front of the Golden Ratio Wall art installationStudents gather in front of the Golden Ratio Wall art installation, which symbolizes the building’s goal: to connect the arts and history with math and science. Steve Woltmann Photography.

 

Building Team — Submitting firm, general contractor Pepper Construction Owner North Central College Architect, structural engineer Holabird & Root Civil engineer Cemcon MEP engineer Ketchmark & Associates Owner’s rep. CBRE

General Information — Size 139,000 sf Construction cost $60 million Construction time July 2015 to March 2017 Delivery method CM at risk

 

RETURN TO THE 2018 BUILDING TEAM AWARDS LANDING PAGE

Related Stories

Giants 400 | Aug 11, 2021

BD+C Awards Programs

Entry information and past winners for Building Design+Construction's two major awards programs: 40 Under 40 and Giants 400

Building Team Awards | Mar 12, 2021

2021 Building Team Awards Entry Information

Only new construction projects completed on or after January 1, 2020 are eligible. Deadline for submissions: May 14, 2021.

Building Team Awards | Mar 12, 2021

Deadline extended for the 2021 Building Team Awards

BD+C's Building Team Awards is the industry's only recognition program to honor projects that achieve excellence in both design/construction and collaboration of the AEC/O team. Deadline for entries: May 14, 2021.

Building Team Awards | Nov 4, 2020

12 projects earn BD+C's 2020 Building Team Awards

The Statue of Liberty Museum, Allianz Field, and the Long Beach Civic Center are three of the projects awarded with BD+C's 2020 Building Team Awards.

Building Team Awards | Nov 3, 2020

Birmingham's haven for the homeless

A coalition of ministries raised millions to build a new home for homeless men in Alabama’s largest city. The Firehouse Shelter wins Honorable Mention in the 2020 Building Team Awards.

Building Team Awards | Nov 2, 2020

It's back to the future for this contractor

Poettker Construction’s new headquarters in rural Breese, Ill., is recognized with a Bronze Award in BD+C’s 2020 Building Team Awards.

Building Team Awards | Nov 2, 2020

Long Beach gets a municipal marvel

The Long Beach Civic Center is honored with a Bronze Award in the 2020 Building Team Awards.  

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021