Where Construction Meets Religion

Sponsored Content Religious Facilities

Where Construction Meets Religion

An Ohio builder was presented with religious requirement challenges while building a temple. But with flexible scheduling and strong communication, he ensured the appropriate blessings and rituals were performed during all stages of construction and that all of the temple’s unique design requirements were met. The outcome: divine success.


By Star Building Systems | September 25, 2015
Builder balances construction and religious schedule in temple completion

The 16,000-sf temple, in the wooded suburbs north of Columbus, OH, utilized a Star Building System. Although it does not look it, it is a single-slope roof structure. 

Maverick Builders, of Grove City, Ohio, has built numerous churches over the years, some of them metal building systems. In recent times, their business has expanded to include houses of worship for a variety of religions. In 2012, they completed their first temple of Sri Saibaba, a sect related to the Hindu religion, with its origins in 19th century India. There are active devotees in many countries, including the US. In 2000, the Sri Saibaba Temple Society of Central Ohio was founded with its primary goal being the construction of a temple in Lewis Center, OH. It took a decade, but they achieved that goal. Design began in 2010, construction began in 2011, and the temple was completed by April 2012. The temple now regularly welcomes 400 worshippers.

Despite Maverick’s extensive experience in the religious sector, this project posed a few unfamiliar challenges. Some of the challenges related to specific religious requirements of the building, which impacted both design and construction. There were also structural aspects that were uncommon for metal building systems that had to be solved.

The 16,000-sf temple, in the wooded suburbs north of Columbus, OH, utilized a Star Building System. Although it does not look it, it is a single-slope roof structure. Parapet wall extensions of various heights create interest and depth to the exterior elevations. The walls are metal wall panels covered with a multi-colored EIFS finish with special accent features. The overall effect is more like a traditional stone-column structure with brightly colored plaster infill walls. A membrane rubber roof was installed over structural metal decking, supported by the Star structure.

The temple is a two-story building, with a basement level that rises 4 feet above grade. The second level is on a suspended precast concrete floor. This is an atypical condition, as many metal building systems are built as slab-on-grade. Engineering to properly transfer the roof and wall loads to the foundation is a little trickier than normal, and was made more complicated by significant point loads of large ornamental structures at several locations on the roof.

There were a number of unusual design features. Maverick Builders’ owner, Paul McKnight, recalls that some of the interior spaces weren’t located where they would be if designed from a purely architectural standpoint. The beliefs of the congregation required specific compass-orientations for certain rooms. The temple sanctuary had to be oriented correctly, as did the direction of staircase travel, and even the bathroom layout. Both interior and exterior designs feature walkways that circle the building and main prayer hall, which are used as part of the religious ceremonies.

The roof bears several heavy ornamental elements, each of which requires a roof curb and appropriate engineering for the increased load. The clear span pre-engineered rafters were designed to support seven point loads. The largest of these is the 2-ton shikhara, the pyramid-like structure that is the most prominent exterior feature of a Hindu temple. It is located directly over the focal point of the sanctuary.

In addition, the construction schedule needed to be coordinated with the owners so that appropriate blessings and religious rituals could be performed at certain stages of construction, such as when sacred objects were being installed. This sometimes involved dozens of people occupying the site while it was still under construction, a challenging and risky situation that contractors usually like to avoid. McKnight, however, recognized the importance of making these ceremonies possible, “to make sure that everything is blessed properly. It will bring good luck on everyone involved,” he says. “In today’s times, you need all the good luck you can get, so we happily cooperated with all of those requirements.”

There was one crucial phase of construction that could not be performed until the entire building was otherwise complete. The 4000 lb., Italian marble statue of Saibaba, the focal point of the sanctuary, was the last thing to be placed in the building. In order to accomplish this, Maverick had to build a framed opening into the roof directly over the intended location of the statue. It was temporarily sealed for weather tightness during construction. When everything else was complete, the roof was opened, and the statue was lowered in by crane. A domed ceiling was placed over the statue, the roof was permanently sealed, and the large shikhara was installed on the roof.

Maverick Builders was awarded a Master Builder Award for “Best Specialty Building,” presented at Star’s annual national sales meeting.

On the website of the Saibaba Temple Society of Central Ohio, there is a page devoted to construction updates, where it says, “It is often told that being able to participate and contribute in a noble activity like building a temple that will serve several thousand people year after year is a once in a lifetime opportunity.” It appears this may not be true for Maverick Builders, however.  Word of the great success of this project has apparently gotten around to other congregations, and there may be more temples and more such opportunities in Maverick’s future.  

Project: Sri Saibaba Temple, Lewis Center, Ohio

Design/Builder – Maverick Builders, Inc., Grove City Ohio
Architect – CDI, Design, LLC, (Maverick’s in-house designer)
Building manufacturer – Star Building Systems
Steel erection – Maverick Builders
HVAC – Command Heating
Plumbing – Command Plumbing
Electric – Westlake Electric
Concrete – Eagle Concrete
Framing & drywall – Fry Drywall
Painting – Listing Painting
EIFS – Damron Finish Systems
Roofing – Harmac Roofing

Related Stories

Market Data | Feb 24, 2021

2021 won’t be a growth year for construction spending, says latest JLL forecast

Predicts second-half improvement toward normalization next year.

Giants 400 | Dec 16, 2020

Download a PDF of all 2020 Giants 400 Rankings

This 70-page PDF features AEC firm rankings across 51 building sectors, disciplines, and specialty services.

Religious Facilities | Sep 17, 2020

Sagrada Familia completion date pushed back due to coronavirus

The project has been under construction since 1882.

Giants 400 | Aug 28, 2020

2020 Giants 400 Report: Ranking the nation's largest architecture, engineering, and construction firms

The 2020 Giants 400 Report features more than 130 rankings across 25 building sectors and specialty categories.

Religious Facilities | Mar 26, 2020

Cathedral design is inspired by a Bishop’s headpiece

RBB Architects designed the building.

Religious Facilities | Jul 30, 2019

Gensler’s temporary Pavillon Notre-Dame uses charred timber as its primary building material

What once destroyed Notre-Dame will now serve to make it stronger.

Architects | Jun 4, 2019

Big design, small budget: These are the best small projects for 2019

Bjarke Ingels Group's prototype mountainside cabin and Fieldwork's forest pedestrian bridges are among 12 projects honored by AIA's Small Project Practitioners group.

Religious Facilities | May 8, 2018

Manhattan’s historic Trinity Church Wall Street is getting its first facelift in 72 years

Improvements will include a new lighting and sound system, and a movable altar.

Reconstruction Awards | Nov 14, 2017

Hallowed ground: A Mormon temple rises from the ashes of a fire-ravaged historic tabernacle

Parts of the tabernacle’s exterior shell were the only things that survived the blaze.

Religious Facilities | Mar 9, 2017

St. Patrick’s Cathedral in NYC launches new geothermal plant

The plant is the first in a series of upgrades planned for 2017 to adapt one of New York’s earliest landmarks.

boombox1 - default
boombox2 -
native1 -

More In Category

Giants 400

Top 40 Religious Facility Construction Firms for 2023

Crossland Construction, Haskell, Big-D Construction, Whiting-Turner, and JE Dunn Construction top BD+C's ranking of the nation's largest religious facility general contractors and construction management (CM) firms for 2023, as reported in the 2023 Giants 400 Report.




Giants 400

Top 115 Architecture Engineering Firms for 2023

Stantec, HDR, Page, HOK, and Arcadis North America top the rankings of the nation's largest architecture engineering (AE) firms for nonresidential building and multifamily housing work, as reported in Building Design+Construction's 2023 Giants 400 Report.

halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021