Hallowed ground: A Mormon temple rises from the ashes of a fire-ravaged historic tabernacle

Reconstruction Awards

Hallowed ground: A Mormon temple rises from the ashes of a fire-ravaged historic tabernacle

Parts of the tabernacle’s exterior shell were the only things that survived the blaze.


By John Caulfield, Senior Editor | November 14, 2017
The Sealing Room

The Sealing Room is where couples are married and sealed to one another in the LDS faith. Interior finishes needed to capture purity, eternity, and love. All photos © Intellectual Reserve, Inc.

December 17, 2010. That was the day a 300-watt light fixture carelessly placed on a wooden speaker box caused a fire that burned down the 35,000-sf Utah Stake Tabernacle in Provo, which the LDS Church had dedicated in 1898.

Parts of the tabernacle’s exterior shell were the only things that survived the blaze. A few months later, Thomas Monson, the LDS Church’s President, announced at the Mormon Church’s annual General Conference that the tabernacle walls would be preserved and the building rebuilt as a temple. This was completed in late 2015 and dedicated on March 20, 2016, the 115th anniversary of the death of William H. Folsom, the tabernacle’s original designer.

Unlike a tabernacle, which along with weekly church services can be used to host civic events like lectures and concerts, temples are holy places that are closed to all but devout members of the Church. Temples typically house small rooms used primarily for the faith’s essential rituals, such as baptisms and marriages.

 

the Celestial Room signifies the union between God and the family.In the LDS faith the Celestial Room signifies the union between God and the family. It is viewed as the most glorious room in the temple. The art glass, furnishings, carpets, and light fixtures pay homage to the time when the original tabernacle was built.

 

The reconstruction of Provo City Center Temple, as the building is now called, broke ground on May 12, 2012. The project expanded Provo Tabernacle’s size to 93,000 sf, primarily by creating two below-grade floors that include underground parking. The excavation went 40 feet down and required extensive shoring and water removal. The Building Team stabilized the 6.8-million-pound exterior walls in order to place the structure onto a network of 146 steel pipes, nine inches in diameter and 90 feet long.

Smaller micropiles also held up the main structure. This was the first time in Utah, and only the third time in the world, that construction crews used steel shoring and needle beams to support a complete building.

During reconstruction, what remained of the tabernacle was fortified with up to 10 inches of reinforced concrete. The project team removed two interior wythes of historic brick and secured three others with steel helical ties. Shotcrete was applied to two layers of rebar that were erected around the interior perimeter. The shotcrete walls function as reinforced shear walls to resist lateral earthquake and wind loads.

Because interior space was at a premium, the Building Team needed to apply the shotcrete as thin as possible.

 

 

More than 20,000 bricks, including original brick from the 1880s building that the crew salvaged and restored, were used. Crews also drew from other local stockpiles of brick that either came from the same era, or looked close enough to produce a consistent exterior.

Although the reconstruction expanded the building footprint, it also maintained aspects of the tabernacle’s floor plan. For example, vertical circulation still occurs at the corner stair towers.

Considerable attention was paid to historical accuracy. Perhaps the temple’s most glorious space is its Celestial Room, whose art glass, furnishings, carpets, and light fixtures combine to pay homage to the period when the original tabernacle was constructed.

The interior lower and main levels favor design details from the 19th-century Eastlake architectural movement, whereas and the upper levels feature Higher Gothic Revival design.

The above-ground levels include a chapel, instruction rooms, offices, lobbies, and five rooms where marriages are performed.

 

The baptismal fontThe baptismal font rests on the backs of 12 oxen. The symbol of the oxen holds special meaning in the LDS Church.

 

The temple’s custom-made walnut and mahogany millwork and trim were based on the tabernacle’s original faux-painted wood trim. The temple’s art glass windows follow the design and colors of the tabernacle’s windows, which were installed around 1917. Paint colors reflect common colors used in the tabernacle as well as popular colors from 1880s Utah.

The reconstruction restored the roofs of the tabernacle’s four corner towers, which had collapsed during the fire, and rebuilt a historic center tower, which had been removed in 1915. Natural light streaming through windows around the tower illuminate an art glass ceiling in the temple’s upper main lobby.

Upon completion of the temple, Provo became the LDS Church’s second city with two temples. (South Jordan, Utah, is the other.) The Provo City Center Temple has alleviated some of the overcrowding at the Provo Utah Temple, one of LDS Church’s busiest. The reconstruction of Provo City Center Temple has also been a boon to nearby restaurants and businesses that are benefiting from the foot traffic the temple has generated.

Among the temple’s many accolades: the 2017 Utah Heritage Award and the 2016 IIDA BEST Award.

 

A carved wood staircaseThe use of carved wood, primarily custom-made walnut and mahogany millwork and trim, is prevalent throughout the temple.

 

Project Summary

 

Platinum Award Winner

Building Team: FFKR Architects (submitting firm, architect) The Church of Jesus Christ of Latter-day Saints (owner) Reaveley Engineers + Associates (S/PE), Van Boerum & Frank Associates (ME) Envision Engineering (EE) Jacobsen Construction (GC/CM).

Details: 93,000 sf. Construction cost: Confidential. Construction time: March 2012 to November 2015. Delivery method: CM/GC.

 

See all of the 2017 Reconstruction Award winners here

Related Stories

Government Buildings | Jan 9, 2023

Blackstone, Starwood among real estate giants urging President Biden to repurpose unused federal office space for housing

The Real Estate Roundtable, a group including major real estate firms such as Brookfield Properties, Blackstone, Empire State Realty Trust, Starwood Capital, as well as multiple major banks and CRE professional organizations, recently sent a letter to President Joe Biden on the implications of remote work within the federal government.

Giants 400 | Aug 11, 2021

BD+C Awards Programs

Entry information and past winners for Building Design+Construction's two major awards programs: 40 Under 40 and Giants 400

Reconstruction Awards | Mar 12, 2021

Call for entries: 2021 Reconstruction Awards

The 2021 Reconstruction Awards recognize the best reconstructed, renovated, or remodeled projects, based on overall design, engineering, and construction project quality. Entries are due July 16, 2021. 

Reconstruction Awards | Mar 12, 2021

2021 Reconstruction Awards Entry Information

Only projects completed or occupied between January 1, 2020 and July 16, 2021 are eligible.

Reconstruction Awards | Mar 12, 2021

2021 Reconstruction Awards 'How to Win' Tip Sheet

Keep this tip sheet handy when preparing your Reconstruction Awards entry, as these are some items on which your project will be judged.

Reconstruction Awards | Feb 5, 2021

The historic Maryland Theatre is reborn in Hagerstown

The Maryland Theatre project has won a Bronze Award in BD+C's 2020 Reconstruction Awards.

Reconstruction Awards | Jan 30, 2021

Repositioning of historic Sears Roebuck warehouse enlivens Boston’s Fenway neighborhood

Developer Samuels & Associates asked Elkus Manfredi Architects to reimagine the former Sears Roebuck & Co. warehouse in Boston’s Fenway neighborhood as a dynamic mixed-use destination that complements the high-energy Fenway neighborhood while honoring the building’s historical significance.

boombox1 - default
boombox2 -
native1 -

More In Category


Giants 400

BD+C Awards Programs

Entry information and past winners for Building Design+Construction's two major awards programs: 40 Under 40 and Giants 400



halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021