Early coordination, prefabrication, and judicious value engineering contributed to the accelerated completion of this Upstate New York design-build project.   


By John Caulfield, Senior Editor | May 16, 2016
Upstate New York performing arts center revives once-toxic lakefront site

The Onondaga Lakeview Amphitheater, near Syracuse, N.Y., seats 17,500. It is the first phase of a more extensive revitalization initiative that will benefit two nearby communities. Photo: David Revette/Revette Studio. Click here to enlarge.

In September 2014, New York Governor Andrew Cuomo signed legislation that allowed for the construction of a new performing arts venue on Onondaga Lake, about five miles northwest of Syracuse.

One year later, on September 3, 2015, the Onondaga Lakeview Amphitheater, a gleaming, 74,000-sf outdoor event complex with a seating capacity of 17,500, held its first performance, featuring country singer Miranda Lambert. This summer, the facility will host 25 concerts.

PLATINUM AWARD
Onondaga Lakeview Amphitheater
Geddes, N.Y.

BUILDING TEAM
+ Submitting firm: Gilbane Building Company (GC); Westlake Reed Leskosky (lead designer, executive architect, interior design, SE/MEP engineer)
+ Owner: Onondaga County, N.Y.
+ Architects: QPK Design, Westlake Reed Leskosky
+ Structural: QPK Design, Westlake Reed Leskosky
+ Landscape: QPK Design
+ Civil: Savin Engineers
+ Acoustics: Jaffe Holden

GENERAL INFORMATION
Project size: 74,000 sf
Construction cost: $49.5 million 
Construction period: January 2015 to August 2015
Delivery method: Design-build

The state-of-the-art amphitheater transformed an EPA-designated Superfund site into a destination that honors its surroundings and encourages a celebration of arts and culture. The facility was the first step in a larger community revitalization initiative along the lake’s western shore, involving the village of Solvay and the town of Geddes. It’s the only vertical design-build contract that the Empire State has let go forward.

With an accelerated construction period, early and constant Building Team collaboration and cooperation were essential for the on-time and on-budget completion of this project. That collaboration began even before the county awarded the contract, with the structural design team working at risk to deliver the steel mill order only eight days after the contract was signed.

Project planning and early identification of subcontractors were critical to the success of this project. BIM played a seminal role in delivering accurate documents on time. The integration of structural analysis software (ETABS) and modeling software (Revit Structure) quantitatively reduced the drawing production time, while increasing the accuracy of the information.

“The Building Team did a terrific job of melding with a stunning landscape, but not overpowering it,” said awards judge Beau Sanders, PE, SE, Associate and Project Manager with engineering firm Graef. “It’s apparent that they thought through all the details, from design to construction. It’s a beautiful project that is not just for concertgoers, but for the whole community to enjoy and appreciate.”

 

The performing arts center was designed to blend in with its surroundings. A bicycle path that encircles the nearby lake runs through the facility. The backlit fascia is meant to match the natural light at dusk. Illuminated panels mimic the local landscape. Photo: David Revette/Revette Studio. Click to enlarge.

 

Blending in with the natural landscape

The site consists of capped industrial waste. Any attempt to remove it could have resulted in further environmental damage. To avoid this, the design minimized the need for significant cut and fill. Gilbane Building Company, the general contractor, mandated 40-hour Hazardous Waste Operations and Emergency Response training for anyone who would be working in potential areas of contamination. Gilbane also calibrated on a daily basis air-monitoring workstations that tracked contaminants on site or dissipating outside the work perimeter.

Over 80,000 cubic yards of existing industrial waste were excavated and relocated to an onsite staging area. Another 130,000 cubic yards of infill were brought in. More than 230 steel piles were driven to support the amphitheater’s back-of-house and pavilion structures.

To deliver power, water, and other services to the facility, Gilbane drilled horizontally underneath Interstate 690 without needing to close down any lanes.

The building’s design and orientation take advantage of the natural land contours and lake views. So integrated is the building’s design with its environment that a bicycle path which circles the lake passes directly through the pavilion, underscoring the site’s function as a county park. The covered pavilion’s fascia, when backlit, correlates to the natural light at dusk on the lake waves.

The pavilion façade has 198 steel-supported, 20-foot-high mesh panels that, when illuminated, play off the natural landscape beyond the amphitheater’s lawn.

The fascia allows the transmission of highly amplified sound from speakers at the stage and from behind the mesh to reach patrons with clarity. The rear lawn loudspeakers—12,500 of the amphitheater’s seating capacity is on an 80,000-sf lawn—are positioned directly behind the unobtrusive open mesh system, which is not only designed for sound integrity but also to provide a clean look at the rear skirt of the shed roof.

Westlake Reed Leskosky’s in-house theatrical and A/V specialists conducted thorough reviews of the amphitheater’s audiovisual requirements throughout the design and construction stages. Acoustical consultant Jaffe Holden assisted on the sound parameters of the design.

 

The covered area of the amphitheater is supported by eight trusses (each weighing 84,000 pounds) with four unique end conditions to achieve a maximum span of 190 feet. The covered area is designed to provide patrons with unobstructed views of the lake. Acoustically transparent fascia allows sound from the stage to reach the audience on the lawn with clarity. Photo: David Revette/Revette Studio. Click to enlarge.

 

Value Engineering beats the budget limits

The amphitheater’s original program was valued at over $80 million, but the taxpayer-funded contract was less than $50 million. Smart engineering and construction were imperative to meet the county’s goals for the building.

The signature feature of the amphitheater is the pavilion canopy, which covers more than 5,000 seats and provides unobstructed views of Lake Onondaga. The design called for maintaining bolted connections in the field, which allowed for swift erection to meet the project’s schedule.

The pavilion’s roof design utilizes eight trusses with four unique end conditions; this system achieves a maximum span of 190 feet. Each truss weighs over 84,000 pounds and is supported by the steel at the stage and columns infilled with 10,000-psi concrete. Ninety percent of the trusses are identical in their configuration.

Gilbane prefabricated the trusses off site. They arrived at the site in no more than three sections and were set in movable cradles for final connection detailing. Completed trusses were erected in one pick, using a pair of cranes in tandem.

Systems and spaces were shifted to save money. Relocating the fourth-floor Event Center to a lower level provides panoramic views of the lake and eliminated the need for two elevators. The third-floor mechanical room was moved as well, allowing the pavilion to be reduced in size from four stories to two, which saved considerably on costs.

An average of 230 tradespeople were on site every day during construction. The project exceeded 200,000 total worker-hours without a single recordable or lost-time incident.

Related Stories

Architects | Jan 18, 2016

EHDD’s Monterey Bay Aquarium wins AIA Twenty-five Year Award

The aquarium set new technical standards for the building type, which still influence today, such as the flow-through seawater-based heat pump system, naturalistic exhibitions, and corrosion protection.

Building Team Awards | Apr 10, 2015

14 projects that push AEC teaming to the limits

From Lean construction to tri-party IPD to advanced BIM/VDC coordination, these 14 Building Teams demonstrate the power of collaboration in delivering award-winning buildings. These are the 2015 Building Team Award winners.

Building Team Awards | Apr 10, 2015

Prefab saves the day for Denver hospital

Mortenson Construction and its partners completed the 831,000-sf, $623 million Saint Joseph Hospital well before the January 1, 2015, deadline, thanks largely to their extensive use of offsite prefabrication.

Building Team Awards | Apr 10, 2015

Anaheim’s soaring intermodal hub

Anaheim's Regional Transportations Intermodal Center is the largest ETFE project in North America.

Building Team Awards | Apr 10, 2015

Virtual collaboration helps complete a hospital in 24 months

PinnacleHealth needed a new hospital STAT! This team delivered it in two years, start to finish.

Building Team Awards | Apr 10, 2015

New arts venue reinvigorates Virginia Tech's campus

The STV-led Building Team creates a world-class performance and arts venue with learning and entrepreneurial dimensions.

Building Team Awards | Apr 9, 2015

Multifaced fitness center becomes campus landmark

A sloped running track and open-concept design put this Building Team to the test. 

Building Team Awards | Apr 9, 2015

Nation's first LEED-certified bus depot

A bus garage in Harlem shows that even the most mundane of facilities can strut its environmentally sensitive stuff.

Building Team Awards | Apr 9, 2015

Setting the bar for port-of-entry design

Whenever you eat a tomato from Mexico, there’s a one-in-three chance it came through this LEED Gold gateway.

Building Team Awards | Apr 9, 2015

Big D’s billion-dollar baby: New Parkland Hospital Tops the Chart | BD+C

Dallas’s new $1.27 billion public hospital preserves an important civic anchor, Texas-style.

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021