flexiblefullpage -
billboard - default
interstitial1 - interstitial
catfish1 - bottom
Currently Reading

Top 10 LEED lessons learned from a green building veteran

Top 10 LEED lessons learned from a green building veteran

M+W Group's David Gibney offers his top lessons learned from coordinating dozens of large LEED projects during the past 13 years.


By David Gibney, LEED AP, M+W Group | November 2, 2014
Photo: M.O. Stevens via Wikimedia Commons
Photo: M.O. Stevens via Wikimedia Commons

I’ve served as the LEED coordinator on dozens of large projects since becoming a LEED AP in 2001. While it’s been a positive experience overall, there have been a few bumps along the way. 

Recently, I jotted down those projects that really stuck out in my mind, and what I learned from them. I included some lessons passed on to me by my sustainability peers. After careful review, I’ve whittled this list down to my top 10 LEED lessons learned:

 

1. The LEED coordinator should be experienced with your project type. 

The role of LEED and sustainable design must enhance, not compromise, a facility design. This especially applies to technical facilities, which one of my first LEED projects, a maximum security prison, happened to be. Being very eager to “green” this correctional facility, I aggressively encouraged the team to incorporate LEED-compliant sustainable features into the design.

While my heart was in the right place, it would have been more productive if I had first spent time learning how prisons work and then come prepared with sustainable concepts that could be accepted by the warden. For example, I was surprised to learn that some prisons actually allow "operable" windows--security fenestration units that allow inmates to regulate air flow through their cells--or that low-flush water closets pose a security risk due to the potential for increased maintenance required from from inmate vandalism. It’s not enough to just be experienced with LEED; experience with the project is also important.

 

2. Review LEED expectations during the pre-bid conference. 

While today’s contractors are much more experienced, even comfortable with LEED, some don’t take enough time to evaluate their required LEED tasks when putting their bid together. One of the best ways to align proposals with a project’s LEED roles and responsibilities is to allow enough time during the pre-bid conference to go over the LEED requirements. This should include a brief review of relevant Division One specifications, the LEED scorecard, the submittal review process, and a stern reminder that each trade is responsible for LEED compliance that may not be expressly indicated in “their” spec division alone.

I learned this the hard way on a Dept. of Energy project, when a mechanical subcontractor used a noncompliant, high-VOC sealant on a fire-rated partition. No one thought to review their submittals for LEED compliance--even if the information on the sealant had been provided. The lesson learned is that a few minutes spent during the pre-bid conference should help reduce these types of oversights. 

 

3. A picture paints a thousand words. 

On more than one project I’ve discovered early in construction that no one was reviewing and tracking submittals for LEED compliance. Too often team members assume “the other guy is doing it,” especially with large, complex projects. 

While the submittal review role is normally under the domain of the project architect, for some projects it often makes sense to have submittal review protocol and training specific to LEED. (The added complexities regarding materials and products in LEED Version 4 will make this even more critical.) 

Over time, I’ve become absolutely convinced that the best way to communicate how submittals should be reviewed for LEED criteria is to distribute a project-specific flow diagram that shows how the submittals should circulate and where/when LEED review(s) occur. Creating this diagram is something I encourage each team to do early on. It still surprises me how often teams, especially design-build entities, have “disconnects” when it comes to reviewing submittals for LEED conformance.

 


Example of a clear submittals review process flow chart. This was for a design/build project. 

 

4. Be very clear: Is LEED certification required or a goal? 

Too many projects list a certain LEED rating level as a project “goal." Technically, this doesn’t compel the design and/or construction team to meet any level of certification. If a company or agency requires projects to earn a specific rating level, then this should be called a “requirement” in the project manual. 

About a decade ago, I was brought into a LEED project at the beginning of construction and discovered there was a discrepancy between what the owner was expecting for the final LEED outcome and what the design-build team had edited in the contract. Achieving LEED Silver certification was originally listed as a “goal” in the agreement but, prior to signing, the design-build team had crossed out “Silver” and wrote in “Certified,” as they were not confident that Silver could be earned without excessive added costs. Fortunately, we did earn Silver certification and avoided any unpleasantries. But this contractual ambiguity left both parties exposed and was a gray cloud during the project, one that could have been avoided by changing just a few words.

 

5. Use a preliminary LEED scorecard in contract documents. 

One of the best ways to guide a design and construction team as to which credits should be pursued is to provide a preliminary LEED Scorecard in the contract documents. This is normally included in Specification 018113 “Sustainable Design Requirements.”

This scorecard should state which credits or credit options the project must (and, in some instances, must not) pursue. However, unless there has been an in-depth LEED workshop with each credit carefully vetted, this scorecard should act as a guideline, informing the team of the parameters it should follow. It shouldn’t limit further exploration of sustainable opportunities without due cause.

 

6. Use established, robust specifications written for your project. 

The importance of thorough, well-coordinated specifications that address the details of LEED cannot be overstated. Regardless of how the specifications are structured, it is imperative that the LEED AP and architect confirm the specifications are edited to apply to your project. (“Recycled” specs aren’t usually very sustainable!) And it’s important to ensure that bid documents have been reviewed and cross-referenced methodically to ensure the LEED information meets the “three ‘C’s of specifications": correct, complete, and coordinated. Failure to meet these criteria is costly to the design team, contractor, and owner. 

 

7. Specify who pays for specialty consultants pertaining to LEED, and be sure their scope is well-defined in contract documents. 

LEED requires project roles that in days gone by were considered “additional.” On an early nanotechnology project (back with LEED Version 2.0), it was not clear in the contract who was responsible to pay for energy modeling. The issue got kicked back and forth between the design team and the owner. Meanwhile, the project started and the design team did not have the benefit provided from early modeling information. 

Finally, the mechanical engineer determined that they were able to absorb the cost in their fee and we were able to reduce the annual energy costs by more than 30%. It’s important that the contract agreement directly states who pays for such specialty LEED consultants.

 

8. Specify who pays for all GBCI fees. 

Though the LEED certification fees paid to the GBCI are small in comparison to other project costs, if it isn’t clear upfront as to who pays these fees, the arguments that may follow can quickly waste more time, and thus money, than the cost of the GBCI fees. 

A colleague of mine found this out with a large, not-to-exceed government project. The construction budget was more than $100 million, but because the issue of LEED certification fees was not addressed in the contract, far too much time was spent arguing over GBCI fees that totaled around $10,000. 

Like so many aspects to LEED, being specific, especially early on, will save everyone time and money.

 

9. Specify criteria and expected outcomes for a front-end LEED/sustainable design workshop. 

Many projects require a sustainable design workshop (aka, “eco-charrette”) or at the very least, a LEED scorecard review by the team. When including this deliverable in your RFP it is important to describe your expectations for the agenda, duration, facilitators, team members expected to participate, meeting location, and even who pays for food and drink, etc. I recall one workshop where the client was expecting the meeting venue to include coffee, which it did not. Emergency! A resourceful assistant found a nearby Starbucks and saved the day.

One critical component of the eco-charrette that is often overlooked is a report of the outcomes. Be very clear in your expectations. Is it just a preliminary LEED scorecard? Do you expect an analysis of the preliminary viability of each credit point? What about affiliated sustainability metrics like energy and water conservation goals and greenhouse gas emissions reduction, etc.? If you don’t describe in some detail what you are expecting, you may be disappointed with what you receive.

 

10. Don’t schedule the LEED plaque unveiling ceremony too soon. 

Probably the most exciting LEED adventure I’ve had occurred right before a LEED plaque unveiling ceremony. Two nights before the ceremony we were distressed when the glass plaque had not yet arrived from the fabricator. (We ordered a custom-made glass plaque, back painted a particular hue of gold to perfectly match the project’s sustainability Learning Wall.) So, that evening I labored at a print shop trying to fabricate a “stand-in” plaque out of foam core and gold mylar. It wasn’t pretty. 

Fortunately, the night before the ceremony the client rep. drove out to the airport UPS shipping distribution center and convinced them to look through their newly received inventory. Whew! It had arrived. (It was pretty. In fact, I’ve never been so happy to see a LEED plaque.) The ceremony the next morning went off without a hitch and everyone was pleased.

In retrospect, we should have given ourselves more time between the day we received our official e-mail award notification from the USGBC until the date we had scheduled for the ceremony. As it turns out, it can take several weeks for a standard plaque to be shipped to a team, and a custom one even more, as we painfully found out. Bottom line: give yourself plenty of time.

 

David Gibney is the Technical Director for Sustainable Design at M+W Group. He can be reached at: david.gibney@mwgroup.net.

Related Stories

Architects | Mar 8, 2024

98 architects elevated to AIA's College of Fellows in 2024

The American Institute of Architects (AIA) is elevating 96 member-architects and 2 non-member-architects to its College of Fellows, an honor awarded to architects who have made significant contributions to the profession. The fellowship program was developed to elevate architects who have achieved a standard of excellence in the profession and made a significant contribution to architecture and society on a national level. 

Sports and Recreational Facilities | Mar 7, 2024

Bjarke Ingels’ design for the Oakland A’s new Las Vegas ballpark resembles ‘a spherical armadillo’

Designed by Bjarke Ingels Group (BIG) in collaboration with HNTB, the new ballpark for the Oakland Athletics Major League Baseball team will be located on the Las Vegas Strip and offer panoramic views of the city skyline. The 33,000-capacity covered, climate-controlled stadium will sit on nine acres on Las Vegas Boulevard. 

Adaptive Reuse | Mar 7, 2024

3 key considerations when converting a warehouse to a laboratory

Does your warehouse facility fit the profile for a successful laboratory conversion that can demand higher rents and lower vacancy rates? Here are three important considerations to factor before proceeding. 

Shopping Centers | Mar 7, 2024

How shopping centers can foster strong community connections

In today's retail landscape, shopping centers are evolving beyond mere shopping destinations to become vibrant hubs of community life. Here are three strategies from Nadel Architecture + Planning for creating strong local connections. 

Market Data | Mar 6, 2024

Nonresidential construction spending slips 0.4% in January

National nonresidential construction spending decreased 0.4% in January, according to an Associated Builders and Contractors analysis of data published today by the U.S. Census Bureau. On a seasonally adjusted annualized basis, nonresidential spending totaled $1.190 trillion.

MFPRO+ Special Reports | Mar 6, 2024

Top 10 trends in senior living facilities for 2024

The 65-and-over population is growing faster than any other age group. Architects, engineers, and contractors are coming up with creative senior housing solutions to better serve this burgeoning cohort. 

Architects | Mar 5, 2024

Riken Yamamoto wins 2024 Pritzker Architecture Prize

The Pritzker Architecture Prize announces Riken Yamamoto, of Yokohama, Japan, as the 2024 Laureate of the Pritzker Architecture Prize, the award that is regarded internationally as architecture’s highest honor.

Office Buildings | Mar 5, 2024

Former McDonald’s headquarters transformed into modern office building for Ace Hardware

In Oak Brook, Ill., about 15 miles west of downtown Chicago, McDonald’s former corporate headquarters has been transformed into a modern office building for its new tenant, Ace Hardware. Now for the first time, Ace Hardware can bring 1,700 employees from three facilities under one roof.

Green | Mar 5, 2024

New York City’s Green Economy Action Plan aims for building decarbonization

New York City’s recently revealed Green Economy Action Plan includes the goals of the decarbonization of buildings and developing a renewable energy system. The ambitious plan includes enabling low-carbon alternatives in the transportation sector and boosting green industries, aiming to create more than 12,000 green economy apprenticeships by 2040.

Lighting | Mar 4, 2024

Illuminating your path to energy efficiency

Design Collaborative's Kelsey Rowe, PE, CLD, shares some tools, resources, and next steps to guide you through the process of lighting design.

boombox1 - default
boombox2 -
native1 -

More In Category

Mass Timber

Charlotte's new multifamily mid-rise will feature exposed mass timber

Construction recently kicked off for Oxbow, a multifamily community in Charlotte’s The Mill District. The $97.8 million project, consisting of 389 rental units and 14,300 sf of commercial space, sits on 4.3 acres that formerly housed four commercial buildings. The street-level retail is designed for boutiques, coffee shops, and other neighborhood services.


Construction Costs

New download: BD+C's May 2024 Market Intelligence Report

Building Design+Construction's monthly Market Intelligence Report offers a snapshot of the health of the U.S. building construction industry, including the commercial, multifamily, institutional, and industrial building sectors. This report tracks the latest metrics related to construction spending, demand for design services, contractor backlogs, and material price trends.



halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021