flexiblefullpage -
billboard - default
interstitial1 - interstitial
catfish1 - bottom
Currently Reading

A Look Back at the Navy’s First LEED Gold

A Look Back at the Navy’s First LEED Gold

Building Design+Construction takes a retrospective tour of a pace-setting LEED project.


By By Robert Cassidy, Editorial Director | November 2, 2010
This article first appeared in the November 2010 issue of BD+C.

There is one thing that every sailor in the U.S. Navy shares with every other sailor: For the first eight weeks of their Navy careers, every one of them will have gone through basic training at Camp John Paul Jones, Naval Station Great Lakes, in North Chicago, Illinois. Every year, more than 40,000 young men and women graduate from the Recruit Training Camp, en route to assignments around the world.

For the last three years or so, recruits have spent a considerable amount of their boot camp training in the Atlantic Fleet Drill Hall, a 56,840-sf facility designed by Wight & Company, Darien, Ill., that achieved LEED-NC v2.2 Gold, the first Navy construction project to earn that award. Recently, I was given a tour of the facility by Lt. Vincent Dasta, USN, Atlantic Fleet Commander, to inspect the sustainable aspects of the project.

The Navy, through its construction arm, the Naval Facilities Engineering Command (NAVFAC), was an early leader in green building among Federal departments. In fact, the Bachelor Enlisted Quarters at the Great Lakes Naval Training Center (also designed by Wight) was the first U.S. government project to be LEED certified, earning LEED-NC v1.0 Bronze in 2000—practically at the birth of LEED. Currently, the Navy requires all applicable projects to achieve a minimum LEED Silver rating.

Construction of the drill hall was part of a large-scale plan to modernize and upgrade facilities at Camp John Paul Jones, according to Dasta. “When we reorganized the base, this building fit in really well,” says Dasta. “This is the headquarters of the Atlantic Fleet, and we try to simulate to the recruits what the Fleet Navy is like.” Instead of using the term “barracks” for living quarters, the camp is divided into five “ships,” and the entry to the drill hall is known as the quarterdeck.

The massive drill hall itself is “a big, open space, very flexible, but the details make it useful to us,” says Dasta. It is used for physical training, drill exercises, and weekly Olympic-style sports competitions. The recruits are assigned to 14 divisions of 88 sailors; the drill hall can hold 10 divisions comfortably for marching exercises, says Dasta, but it can handle the full complement of divisions.

One of the major uses of the space is for running, and the resilient floor provides a pliant surface to reduce stress on recruits’ knees. The runners’ direction is reversed every day to keep the floor from developing a wear pattern. The facility is open 24/7, so it gets a great deal of use.

Dasta says the drill hall’s combined daylighting, lighting control, and shade control system has worked well over the last three years to keep the facility at a comfortable temperature while providing the health benefits associated with sunlight. Elsewhere in the drill hall are offices, a conference room, and classrooms.

Maintaining the building has been easy, according to Dasta. “Sustainment of facilities has become a big push in the last year or so, with the completion of the last of our major buildings” at Camp John Paul Jones.

The LEED Gold rating was achieved while conforming to the Navy’s Base Exterior Architectural Plan, which provides guidelines for upgrading the overall appearance of Navy shore facilities.

Key LEED milestones: a 41.7% reduction in water use and a 37.2% reduction in energy over a conventionally designed building. High-efficiency air-cooled water chillers with non-CFC refrigerant, energy recovery coils, and a direct digital control system for operator-programmable systems were employed, as well as occupancy sensors and scheduling to control outdoor air. The Building Team even anticipated the U.S. Green Building Council’s requirement for data collection on LEED projects by installing meters in the drill hall.

Other green elements: a solar white standing-seam metal roof, a motorized window shading system to control heat gain, and a five-year maintenance program for building operations, maintenance, and repairs.

The joint venture contractor of Pacific Construction Services and Old Veteran Construction Services Inc. (the latter a “service-disabled, veteran-owned” business) achieved an 89.6% rate of diversion of construction waste from landfill.

“We used a lot of smart conventional equipment to achieve the goals for the project,” says Lois Vitt Sale, AIA, LEED Faculty, and SVP/Chief Sustainability Officer at Wight & Company. BD+C

Low-impact Development Guides Stormwater Plan

Site planning for the Atlantic Fleet Drill Hall at Naval Station Great Lakes utilized the concept of low-impact development, or LID, to control stormwater runoff.

According to Tom Powers, PE, LEED AP, CRM, CPESC, a project manager with Wight, the basic principle of low-impact development is to model stormwater systems after nature—to manage rainfall at the source, using distributed small-scale stormwater management systems.

The goal, says Powers, is to “mimic the site’s hydrology as it existed before development began, using stormwater features that infiltrate, filter, store, evaporate, and detain runoff close to its source,” with particular attention to smaller, more frequent storms. Major infrastructure improvements at Camp John Paul Jones were designed to handle the much larger 100-year storms.

Since December 2007, with the passage of the Energy Independence and Security Act, controlling runoff is not a choice in almost all Federal construction projects. EISA states that “any development or redevelopment project involving a Federal facility with a footprint that exceeds 5,000 sf shall use site planning, design construction, and maintenance strategies for the property to maintain, or restore, to the maximum extent technically feasible, the predevelopment hydrology of the property with regard to the temperature, rate, volume, and duration of flow.” That pretty much mandates low-impact development for Federal projects.

The strategy for the Atlantic Fleet Drill Hall site had three prongs: 1) disconnect impervious areas where possible; 2) filter and infiltrate the average annual runoff; and 3) reduce nonpoint runoff through the use of native plantings.

The drill hall is situated on top of a small hill, with the building itself representing the largest source of concentrated stormwater runoff on the site. Under LID principles, the stormwater treatment areas were also located close to the building. The drill hall does not have a basement, so it was possible to excavate below-grade infiltration zones around the four corners of the building and fill them with gap-graded stone to create catchment basins with a 40% void ratio.

According to Powers, the roof runoff is then piped into the upper-layer infiltration zones and the water is allowed to percolate down through the stone following the groundwater gradient. The stormwater is daylighted and discharged to the infiltration zones via perforated pipes connected to the downspouts. The underground catchments are designed to hold a one-year 24-hour storm event and most of a two-year event; any spillover gets directed into the regional system and ultimately into the base detention facility.

For the bulk of the site, says Powers, the landscaping choice was to go with native plantings and buffalo grass, whose root systems can extend as far as eight feet deep into the soil, as opposed to only a few inches for Kentucky bluegrass. Buffalo grass needs only a quarter-inch of water per week and does not require mowing, pesticides, or fertilizers. Not having to irrigate the buffalo grass and other native decorative plantings contributed to the 41.7% reduction in water use for the drill hall compared to a conventional project. Moreover, buffalo grass grows to a maximum height of about five inches in the Great Lakes region and therefore does not present a security problem, which is important in a military facility.

Without the LID plan, the one-acre site would have had an unrestricted runoff rate of 6-7 cfs, says Powers. With LID, that has been reduced to 1.77 cfs for a one-year 24-hour storm and 2.03 cfs for a two-year storm. “We captured all the one-year storms and 99% of the two-year storms, and that’s before you count in the benefit of the buffalo grass,” says Powers.

Related Stories

| Aug 11, 2010

New hospital expands Idaho healthcare options

Ascension Group Architects, Arlington, Texas, is designing a $150 million replacement hospital for Portneuf Medical Center in Pocatello, Idaho. An existing facility will be renovated as part of the project. The new six-story, 320-000-sf complex will house 187 beds, along with an intensive care unit, a cardiovascular care unit, pediatrics, psychiatry, surgical suites, rehabilitation clinic, and ...

| Aug 11, 2010

Colonnade fixes setback problem in Brooklyn condo project

The New York firm Scarano Architects was brought in by the developers of Olive Park condominiums in the Williamsburg section of Brooklyn to bring the facility up to code after frame out was completed. The architects designed colonnades along the building's perimeter to create the 15-foot setback required by the New York City Planning Commission.

| Aug 11, 2010

Wisconsin becomes the first state to require BIM on public projects

As of July 1, the Wisconsin Division of State Facilities will require all state projects with a total budget of $5 million or more and all new construction with a budget of $2.5 million or more to have their designs begin with a Building Information Model. The new guidelines and standards require A/E services in a design-bid-build project delivery format to use BIM and 3D software from initial ...

| Aug 11, 2010

Opening night close for Kent State performing arts center

The curtain opens on the Tuscarawas Performing Arts Center at Kent State University in early 2010, giving the New Philadelphia, Ohio, school a 1,100-seat multipurpose theater. The team of Legat & Kingscott of Columbus, Ohio, and Schorr Architects of Dublin, Ohio, designed the 50,000-sf facility with a curving metal and glass façade to create a sense of movement and activity.

| Aug 11, 2010

Residence hall designed specifically for freshman

Hardin Construction Company's Austin, Texas, office is serving as GC for the $50 million freshman housing complex at the University of Houston. Designed by HADP Architecture, Austin, the seven-story, 300,000-sf facility will be located on the university's central campus and have 1,172 beds, residential advisor offices, a social lounge, a computer lab, multipurpose rooms, a fitness center, and a...

| Aug 11, 2010

News Briefs: GBCI begins testing for new LEED professional credentials... Architects rank durability over 'green' in product attributes... ABI falls slightly in April, but shows market improvement

News Briefs: GBCI begins testing for new LEED professional credentials... Architects rank durability over 'green' in product attributes... ABI falls slightly in April, but shows market improvement

| Aug 11, 2010

Luxury Hotel required faceted design

Goettsch Partners, Chicago, designed a new five-star, 214-room hotel for the King Abdullah Financial District (KAFD) in Riyadh, Saudi Arabia. The design-build project, with Saudi Oger Ltd. as contractor and Rayadah Investment Co. as developer, has a three-story podium supporting a 17-story glass tower with a nine-story opening that allows light to penetrate the mass of the building.

| Aug 11, 2010

Three Schools checking into L.A.'s Ambassador Hotel site

Pasadena-based Gonzalez Goodale Architects is designing three new schools for Los Angeles Unified School District's Central Wilshire District. The $400 million campus, located on the site of the former Ambassador Hotel, will house a K-5 elementary school, a middle school, a high school, a shared recreation facility (including soccer field, 25-meter swimming pool, two gymnasiums), and a new publ...

boombox1 - default
boombox2 -
native1 -

More In Category



AEC Tech

Lack of organizational readiness is biggest hurdle to artificial intelligence adoption

Managers of companies in the industrial sector, including construction, have bought the hype of artificial intelligence (AI) as a transformative technology, but their organizations are not ready to realize its promise, according to research from IFS, a global cloud enterprise software company. An IFS survey of 1,700 senior decision-makers found that 84% of executives anticipate massive organizational benefits from AI. 


Codes and Standards

Updated document details methods of testing fenestration for exterior walls

The Fenestration and Glazing Industry Alliance (FGIA) updated a document serving a recommended practice for determining test methodology for laboratory and field testing of exterior wall systems. The document pertains to products covered by an AAMA standard such as curtain walls, storefronts, window walls, and sloped glazing. AAMA 501-24, Methods of Test for Exterior Walls was last updated in 2015. 

halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021