L.A.’s expedited permitting process credited with faster approvals on $1 billion project

Codes and Standards

L.A.’s expedited permitting process credited with faster approvals on $1 billion project

Parallel Design-Permitting Process includes flagging elements for correction during conceptual design.


By Peter Fabris, Contributing Editor | January 14, 2020

Courtesy Pixabay

The completion of the $1 billion Metropolis development in downtown Los Angeles was aided by the city’s streamlined permitting process, according to the developer.

With the recent completion of the 56-story, 650-unit condominium tower Thea, the development provides 1,500 residences, 350 hotel rooms, and 70,000 sf of retail space. The 6.3-acre Metropolis project broke ground in 2014. Two residential towers, one in 2017 and one in 2018, as well as the Hotel Indigo, are already open.

The developer, Greenland USA, says Los Angeles Department of Buildings and Safety’s Parallel Design-Permitting Process helped it complete the project efficiently and on time. The program allows plan inspectors to check and identify elements that need correction during the conceptual design phase.

Among the benefits to the program:

· Reduces design revisions

· Earlier approvals from other agencies

· Reduced permit processing time

· Earlier starts for contractors   

· Cost savings from a shorter construction timeline

Related Stories

| Nov 26, 2012

Changes in development and building standards needed for health of Potomac River

The Potomac River’s health stands to suffer if the region does not change its development and building standards, according to the Potomac Conservancy.

| Nov 16, 2012

South Dakota prefers LEED over building code on state projects

“(LEED is) much better than a mandatory building code because you get a little wiggle room in these projects,” said Mike Mueller, a spokesman for the South Dakota Bureau of Administration.

| Nov 16, 2012

AAMA publishes quality assurance guidelines for Polyamide Thermal Barriers

The American Architectural Manufacturers Association (AAMA) has published QAG-2-12, Voluntary Quality Assurance Processing Guide for Polyamide Thermal Barriers.

| Nov 16, 2012

New ANSI/BIFMA standards developed for educational seating

The American National Standards Institute (ANSI) has approved the newly developed safety and performance standard for educational seating: ANSI/BIFMA X6.1-2012—the first of its kind.

| Nov 16, 2012

Green building councils in 62 countries expect 60% of their work to be green by 2015

More than half of the respondents to a survey of members of the Green Building Council in 62 countries expect green projects to comprise 60% of their work by 2015.

| Nov 16, 2012

Voters approve fewer construction ballot measures in 2012 than in 2008

Voters passed fewer ballot measures related to construction projects this year than they did in 2008, according to an analysis by the Associated General Contractors of America.

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021