It only took 26 days to complete construction on the Crowne Plaza Changi Airport hotel extension

Hotel Facilities

It only took 26 days to complete construction on the Crowne Plaza Changi Airport hotel extension

PPVC techniques allowed the project to save time and manpower.


By David Malone, Associate Editor | July 5, 2017

Photo: Patrick Bingham-Hall

The Singapore Changi Airport is, according to the most recent numbers from the Airports Council International, the 17th busiest airport in the world by passenger traffic. With so many people passing through on a daily basis, it was important for the new addition to the Crowne Plaza Changi Airport hotel to be built in as little time as possible.

The new building was Singapore’s first private sector commercial project to use pre-fabricated, pre-finished volumetric construction (PPVC), which led to the addition being built in just 26 days. WOHA designed the original 320-room hotel as well as the 243-room, 103,495-sf addition.

 

Photo: Patrick Bingham-Hall.

 

The use of the PPVC method slashed manpower requirements on site by as much as 45%, reduced overall construction time by 17%, and accomplished both of these with about 40% in manpower savings.

 

Photo: Patrick Bingham-Hall.

 

“The Crowne Plaza Changi Airport hotel extension (CPEX) demonstrates that it is possible to significantly reduce the number of workers required, shorten construction time, improve building quality and even overcome site constraints by changing the way we build,” says Singapore’s Building and Construction Authority CEO John Keung in a release.

 

Photo: Patrick Bingham-Hall.

Related Stories

Hotel Facilities | Jul 29, 2020

COVID-19 hasn’t put hotel construction or renovations on hold

Los Angeles tops five metros that accounted for 15% of the country’s pipeline.

Hotel Facilities | Jun 25, 2020

Restoration of 1930s El Paso hotel completes

The project represented a cross-collaboration of Cooper Carry’s Hospitality studio and The Johnson Studio at Cooper Carry.

Coronavirus | May 27, 2020

Clean is the new Green as U.S. hospitality sector inches closer to reopening

Three design firms share their takes on what will make customers more comfortable about returning.

Hotel Facilities | May 5, 2020

Video: Fresh ideas for converting idle hotel rooftops to amenity spaces

From fire pits to infinity pools to urban gardens, hotel design experts with Base4 offer smart ideas for making the most of hotel rooftop amenity spaces. 

Coronavirus | Apr 14, 2020

COVID-19 alert: Missouri’s first Alternate Care Facility ready for coronavirus patients

Missouri’s first Alternate Care Facility ready for coronavirus patients

Coronavirus | Apr 10, 2020

COVID-19: Converting existing hospitals, hotels, convention centers, and other alternate care sites for coronavirus patients

COVID-19: Converting existing unused or underused hospitals, hotels, convention centers, and other alternate care sites for coronavirus patients 

Wood | Apr 1, 2020

HDR will design a mass timber Ramada Hotel

The hotel will be located in Kelowna, British Columbia.  

Hotel Facilities | Mar 25, 2020

Chicago's new Sophy Hotel

Completed in 2018, the seven-story, 98-guest room hotel complements the local museums, cultural attractions, and University of Chicago campus.

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021