COVID-19 alert: Missouri’s first Alternate Care Facility ready for coronavirus patients

Coronavirus

COVID-19 alert: Missouri’s first Alternate Care Facility ready for coronavirus patients

Tarlton Corp. completes hotel convertion in less than 100 hours to support hospitals in case more beds are needed.


By TARLTON CORP. | April 14, 2020
USACE general Mark Toy briefed by Tarlton Corp. officials

U.S. Army Corps of Engineers Maj. Gen. R. Mark Toy is briefed by Tarlton construction executives on the site of the alternate care facility. From left: Senior Project Manager Cameron Denison, who managed the night team; Vice President Joe Scarfino, who led the effort and managed the day team; and EVP John Doerr. 

ST. LOUIS (April 14, 2020) – The design-build team of Tarlton Corp., a St. Louis-based general contracting and construction management firm, working for the U.S. Army Corps of Engineers, completed conversion April 11 of a Florissant, Mo., hotel into an alternate healthcare facility to treat non-acute COVID-19 patients. The facility, if needed, would serve as backup for patients referred by St. Louis-area hospitals and would be staffed by members of the Missouri National Guard.

The project yielded more than 100 patient rooms on the four floors of the 130-room hotel. The team built a nurses’ station on each floor and turned the existing phone system into a nurse call system. Beds and furniture were moved. Extra furniture was put into temporary storage. PTAC units in rooms were inspected and repaired or replaced as necessary. Hardware was changed on hotel room doors and bathroom doors to disable locks. All rooms were deep cleaned. In 13 rooms, carpet was removed and walls and ceilings were painted.

Project scope also included steps to ensure proper ventilation for a patient care facility: inspection and cleaning of HVAC units; relocation of exhaust fans within 25 feet of HVAC intakes; extension of plumbing vents within 25 feet of HVAC intakes; and construction of isolation barriers in the corridors (three per floor) to separate the elevator/nurse station areas from the three patient wings.

 

100+ WORKERS ON THE DESIGN-BUILD TEAM

More than 100 employees from the design-build team, including 50 from Tarlton, worked on site at the Quality Inn from April 8 to 11 to help USACE complete its mission in less than 100 hours. The team consisted of Tarlton (design-build contractor), Ross & Baruzzini (architectural/engineering services), Rock Hill Mechanical Corp., and Guarantee Electrical Co. 

Subcontractors working on the conversion included C&R Mechanical’s Plumbing Division, Collins & Hermann, Dynamic Air Solutions, Flooring Systems Inc., Jos. Ward Painting Co., Midwest Elevator, Stanley Steemer, Tech Electronics, Waterhout Construction, and Woodard Cleaning and Restoration.

 

Workers inspect rooftop units in support of ensuring healthy air circulation in the facility

Workers inspect rooftop units in support of ensuring healthy air circulation in the alternate care facility. 

 

Government, health, and hospital officials toured the facility at 55 Dunn Road over the weekend and Monday morning. USACE Maj. Gen. R. Mark Toy recognized all the participants for their work. State agencies involved included the Missouri National Guard, Department of Public Safety, State Emergency Management Agency, Department of Health and Senior Services, Office of Administration and the Missouri Hospital Association, in partnership with FEMA and the U.S. Department of Health and Human Services.

“I’m proud of the quick and thorough response our team put together and executed,” said Tracy Hart, President of Tarlton. “We feel honored to be trusted by the Army Corps of Engineers for this critical project that is so important to our community.”

Becky Mehaffy, Tarlton workforce manager, said, “Our group jumped right in there with the single goal to get it done safely and on time. I’ve seen a lot in my years in this industry—never anything like this.”

“Our design-build partners, subcontractors, and consultants were critical to the project’s success,” said Tarlton COO Dirk Elsperman. “Everyone brought ideas and the will to succeed—a strong commitment to the 12:01 a.m. Sunday turnover."

"It was an extraordinary integrated design-build effort,” said Michael Shea, AIA, Ross & Baruzzini SVP/Director of Government. Guarantee Electrical President Dave Gralike added: “We are especially proud of our team and all the contractors and tradespeople involved in this quick turnaround project.”

 

Individual room at ACF in Florissant, Mo.

Individual patient room at ACF in Florissant, Mo.

Related Stories

Office Buildings | Jun 28, 2023

When office-to-residential conversion works

The cost and design challenges involved with office-to-residential conversions can be daunting; designers need to devise creative uses to fully utilize the space.

Arenas | May 18, 2023

How can we reimagine live sports experiences?

A Gensler survey finds what sports fans' experiences have been like returning to arenas, and their expectations going forward.

Headquarters | May 15, 2023

The new definition of Class A property

Dan Cheetham, Managing Director and Founder of FYOOG, believes organizations returning to a "hub and spoke" model could have a profound effect on properties once considered Class B.

Office Buildings | May 5, 2023

9 workplace design trends for 2023

HOK Director of WorkPlace Kay Sargent and Director of Interiors Tom Polucci discuss the trends shaping office design in 2023.

Multifamily Housing | Apr 4, 2023

Acing your multifamily housing amenities for the modern renter

Eighty-seven percent of residents consider amenities when signing or renewing a lease. Here are three essential amenity areas to focus on, according to market research and trends.

Urban Planning | Mar 16, 2023

Three interconnected solutions for 'saving' urban centers

Gensler Co-CEO Andy Cohen explores how the global pandemic affected city life, and gives three solutions for revitalizing these urban centers.

Laboratories | Mar 9, 2023

5 laboratory design choices that accelerate scientific discovery

Stephen Blair, director of CannonDesign's Science & Technology Practice, identifies five important design strategies to make the most out of our research laboratories.

Augmented Reality | Jan 27, 2023

Enhancing our M.O.O.D. through augmented reality therapy rooms

Perkins Eastman’s M.O.O.D. Space aims to make mental healthcare more accessible—and mental health more achievable.

K-12 Schools | Nov 30, 2022

School districts are prioritizing federal funds for air filtration, HVAC upgrades

U.S. school districts are widely planning to use funds from last year’s American Rescue Plan (ARP) to upgrade or improve air filtration and heating/cooling systems, according to a report from the Center for Green Schools at the U.S. Green Building Council. The report, “School Facilities Funding in the Pandemic,” says air filtration and HVAC upgrades are the top facility improvement choice for the 5,004 school districts included in the analysis.

Giants 400 | Nov 14, 2022

4 emerging trends from BD+C's 2022 Giants 400 Report

Regenerative design, cognitive health, and jobsite robotics highlight the top trends from the 519 design and construction firms that participated in BD+C's 2022 Giants 400 Report.

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021