The contractor’s role in promoting job site sustainability [AIA course]

Contractors

The contractor’s role in promoting job site sustainability [AIA course]

Robins & Morton’s Jackie Mustakas offers specific actions that contractors and construction managers can take to green every job site.


By Jackie Mustakas, LEED AP BD+C, Robins & Morton | December 1, 2015
The contractor’s role in promoting job site sustainability [AIA course]

Courtesy Robins & Morton

Building occupants and users increasingly expect that environmental responsibility—conserving natural resources, providing healthy building environments, reducing operating costs—will be a top priority for building owners and project teams.

Most sustainable strategies are decided during project design. As the project moves into the construction phase, a few key construction efforts—erosion and pollution control, waste management, and indoor air quality management—are consistently implemented. But when it comes to sustainable practices during the construction phase itself, contractors are not always exploring all of the available opportunities.

Because most of the credits available within LEED BD+C rating systems are the responsibility of the building owner and design team, contractors usually are left with limited opportunity to directly control and achieve sustainability success. They are resigned to following the formulas for managing sustainability in line with prescribed LEED credits. The usual result: a narrowly focused sustainability effort on the construction site. Yet there are opportunities for contractors to go beyond LEED and achieve even greater outcomes by committing to healthier and more efficient job site practices.

LEARNING OBJECTIVES
After reading this article, you should be able to:
+ Discuss the opportunities a construction manager has to enhance sustainability during construction.
+ Explain how to structure a construction sustainability program to facilitate successful implementation on the job site.
+ List feasible and cost-appropriate activities to reduce environmental impact and carbon footprint during the construction process.
+ Describe the communication/education process the construction manager should implement to ensure success of the project’s sustainability efforts.

 

EDITOR’S NOTE
To earn 1.0 AIA CES learning units, study the article carefully and take the exam posted at www.BDCnetwork.com/
ContractorSustainability

At Robins & Morton, we have developed an internal program to examine opportunities to green every job site. Based on that experience, this course will review specific actions that contractors and construction managers can take to:
1. Generate a menu of feasible and cost-appropriate activities to reduce the project’s environmental impact and carbon footprint during construction
2. Enhance the project’s success by demonstrating a deep commitment to sustainability on the job site

These standards can guide building owners’ decision making on sustainability efforts during construction and what they should expect from their construction partners—and, conversely, what contractors should be expected to provide their clients.

 

FIRST THINGS FIRST: CREATE STANDARDS

To be sustainable during construction of every project, contractors must create a companywide policy to guide project teams and streamline the process. Such a policy hinges on: 1) developing an appropriate policy structure, 2) requiring realistic and feasible activities, and 3) creating buy-in and accountability. 

To set the foundation, we recommend establishing a focus group of respected superintendents and project managers—individuals working on project sites full time, who understand where the sustainability opportunities lie and which of these could result in the greatest beneficial impact. They should be familiar with sustainability principles and have the experience and wisdom to judge the feasibility of newly proposed ideas. They must also be respected by others in the company, to gain buy-in at all levels of the firm.

The workshop should be led by a team member with considerable experience in environmental design and construction. This person will start the workshop with an overview of the general principles of sustainability, followed by a facilitated brainstorming session focused on those aspects of a project where the contractor makes decisions without extensive input or commitment from the owner or design team.

Our company has found three contractor-controlled areas that meet these criteria: 1) general requirements, such as temporary utilities and construction, 2) site controls and utilization, and 3) field office operation. From our experience, developing program standards using these criteria avoids ambiguity from other project team members’ roles and opinions and is easier to adopt.

Workshop subgroups should brainstorm actions within contractor-controlled criteria to: 1) minimize water usage, 2) save power and optimize fuel usage, 3) protect air quality and enhance human health, and 4) conserve natural resources and select healthier materials.

Next, analyze each idea not only by environmental benefit, but also by its impact on project requirements, including budget, schedule, safety, site constraints, labor, and equipment requirements. Activities or ideas that are determined to be cost-neutral, have no impact on safety or schedule, and produce minimal impact on site utilization, labor, and equipment requirements can likely be designated as mandatory for every project. Ideas where the environmental benefits outweigh the minimal impact on other project requirements may be designated as optional. Any activities or ideas that require a significant cost or impact on other project requirements should probably be eliminated.

Mandatory and optional activities should cultivate the company’s standard. They can be organized within the policy draft by:
• Area of environmental impact (water, energy, human health, or materials)
• Requirement level (optional or mandatory)
• Physical scope (construction site or job site office)

To ensure accountability and consistency, the project team should also be required to report to senior managers at construction start-up, at 50% construction completion, and at project closeout. We have also found it valuable to educate all individuals involved in the construction process about sustainability and the environmental efforts that will be implemented on site.

Construction job sites present numerous opportunities for environmental stewardship. Contractors must move beyond prescriptive methods and practices and embrace a commitment to develop a more dynamic program to greening every job site.

Contractors should work toward developing customized programs that target sustainable opportunities within the scope of their responsibilities, while considering cost, schedule, site utilization, and safety. Contractors must then commit to implementing, educating, and continuously improving their efforts.

Such a holistic approach to sustainability on the project site can produce a measurable reduction in the carbon footprint and environmental impacts of construction. It can also produce new benchmarks and replicable practices that can be shared across the industry. By documenting success and sharing knowledge, contractors can play a larger role in the green building movement.

 

Core Areas for Environmental Performance
on the Project Site

ENERGY CONSERVATION: HIGH PRIORITY

Minimizing energy usage is usually the highest priority in sustainable construction. The U.S. EPA estimates that 30% of energy used in the built environment is inefficiently used or wasted. Improving the energy efficiency of commercial and industrial buildings by 10% would result in a savings of $20 billion a year and prevent greenhouse gas emissions equivalent to those generated by 30 million vehicles.

Fueling generators to provide temporary power, powering a job site trailer, temporary lighting for the site and building, fueling earth-moving equipment, powering hand tools, and testing building equipment—all these activities consume fuel or electricity during construction.

TIPS FOR MINIMIZING WATER USAGE DURING CONSTRUCTION
• Recycle stormwater for dust control on site
• Install low-flow toilets and aerators at sinks in the job site trailer
• Implement a detailed stormwater pollution protection plan (SWPPP) to minimize water pollution and protect the neighboring community
• Collect rainwater for bootwash at the project trailer

 

TIPS FOR MINIMIZING ENERGY USAGE DURING CONSTRUCTION
• Hang temporary lighting separate from safety and egress lighting to shut down most lighting at the end of the workday
• Use LED lamps for temporary site lighting
• Orient the job site trailer to maximize daylighting
• Install a programmable thermostat in the trailer

With many construction projects running 24/7 to meet their schedules, energy use and monitoring becomes even more important—and the opportunities for savings even greater. An energy use analysis should be performed before construction begins to customize the project’s approach and actions for conservation.

Temporary lighting is one of the more demanding energy-consuming requirements during construction. Temporary lighting is necessary for safety and security and for interior work until the electrical contractor has installed fixtures and bulbs later in the schedule.

To reduce energy consumption, general contractors should work with the electrical subcontractor to ensure temporary lighting is hung to separate safety and egress lighting from all other temporary lighting. This should not require extra cost, just extra thought and coordination. At the end of each workday, most of the lighting can be turned off without affecting safety, egress, or security.

The use of LED lamps is highly recommended. The construction manager and electrical subcontractor should perform a cost analysis to determine if it makes sense to use LED lamps for temporary uses, since these lamps can be reused for future projects.

There are even opportunities to cut energy usage in your trailer or site office, just as you would in your corporate office. Selecting Energy Star appliances and equipment, shutting down lights and computers at the end of the workday, using LED lamps, and installing programmable thermostats are effective strategies. Wherever possible, trailers should be positioned in the shade in hotter climates and oriented to maximize daylighting and solar heat gain in cooler climates.

More-elaborate (and possibly more costly) strategies—use of solar-powered equipment and tools, diesel-electric or hybrid equipment, and renewable energy sources for temporary power—should be considered for their feasibility on a project-by-project basis.

 

WATER CONSERVATION AND MANAGEMENT

Building strategies like wet-curing and pressurizing fire protection systems require water usage during construction. Temporary activities—maintaining a clean job site, hydrating workers, and cleaning equipment and tools—also require water. Homing in on low-cost or cost-neutral activities is the easiest way to save water on your job.

Construction sites are constantly plagued by water connections and hoses that leak or are left running. By providing closable nozzles for all hoses and assigning a field employee to inspect connections and hoses daily, the construction manager can make an immediate, positive impact by eliminating unacceptable water wastage on the construction site. The cost will be marginal.

Another best practice: implement a stormwater pollution prevention plan. Most construction projects where a significant area of soil is disturbed must enforce an SWPPP. These plans are designed to minimize runoff from the site to protect nearby communities and water supplies from pollutants resulting from construction activities.

Preparing the plan and installing control techniques, such as silt fence stabilization, rock bag inlet protection, and geotextile erosion controls, will add some marginal costs, but can result in significant environmental and health benefits. 

For sites that do not have temporary water sources, rainwater collection and reuse can yield measurable results. Water collected in rain barrels can be used at a tool or boot cleaning station. More sophisticated (and more costly) collection systems that can store and pump water may be appropriate on larger projects that require temporary irrigation or dusting-down of the site to protect air quality.

 

IMPROVING AIR QUALITY PROTECTION AND ENHANCING HUMAN HEALTH

It is the construction manager’s responsibility to support construction workers’ health by protecting job site air quality and enforcing healthy housekeeping standards. Typical sources of air pollution during construction include off-gassing of building materials, activities that create dust and particulates, emissions from fuel-powered equipment, and toxic cleaning products.

5 KEY ACTIONS FOR CONTRACTORS IN DEVELOPING A SUSTAINABILITY PLAN
• Focus on areas where the contractor can make the most impact and make decisions without extensive input or commitment from the owner or design team.
• Utilize key employees who have the experience and leadership necessary for analysis and implementation.
• Encourage the team to brainstorm without limitations; this will assist with identifying creative approaches and unique ideas.
• Develop analysis criteria that will minimize conflict or obstacles during the implementation process.
• Generate a plan to continuously review the program for improvement and update it at least annually.

 

CONDUCT SUSTAINABILITY EDUCATION DURING THE CONSTRUCTION PROCESS
• Assign an employee on site to enforce policy requirements and educate workers in weekly job site meetings
• Encourage the project owner to attend the weekly sustainability staff meetings
• Provide signage to reiterate project goals and update workers on progress

 

MAXIMIZE HUMAN HEALTH AND IMPROVE INDOOR AIR QUALITY DURING CONSTRUCTION
• Maintain a clean, organized site
• Hardscape temporary roads and pathways to minimize airborne dust
• Maintain a smoke-free job site
• Implement a no-idling policy to reduce emissions from equipment and vehicles
• Establish a detailed indoor air quality plan that utilizes sweeping compounds, temporary enclosures to isolate dust, and green cleaning products
• Identify opportunities to prefabricate building systems (e.g., headwalls, bathrooms, patient rooms)
• Implement a noise/vibration control plan to protect workers, neighbors, and nearby buildings from disturbance or damage
• Station an EMT on site to ensure quick response to any possible safety issues
• Provide a quality break area for workers

 

SELECT THE RIGHT MATERIALS DURING CONSTRUCTION
• Select cardboard product with recycled content for casework and flooring protection
• Use FSC-certified wood for blocking and temporary uses
• Utilize reusable fencing on site and reusable formwork for concrete structure
• Require vendors to reduce packaging for deliveries
• Implement a detailed waste management plan that diverts more than 80% of waste generated on site
• Salvage furniture for use in temporary on site office
• Install hand dryers within job site trailer to minimize use of paper towels
• Use tablet-stored documents to go paperless

It is important to develop an air quality plan for both indoor and outside activities. Such a plan must be tailored to each project. It can be developed to be cost-neutral or low-cost and can implement a full range of protection and confirmation testing activities.

Construction activities to protect indoor air quality:
-  Utilize temporary enclosures to isolate work areas and limit migration of dust and airborne materials
-  Use environmentally friendly cleaning products
-  Utilize sweeping compound, when necessary
-  Encourage workers to prefabricate as much work on the exterior of the building as possible

Construction activities to protect air quality on the exterior:
-  Establish a no-idling policy for operated equipment, requiring equipment operators to shut off equipment after two minutes of idling
-  Properly maintain equipment and construction vehicles to reduce emissions
-  Dust down or hardscape pathways within the project site
-  Enforce a no-smoking policy on the job site

Maintaining a clean and well-organized site and providing a quality break area for workers on site can also enhance worker well-being. For the temporary office or trailer, inspecting and cleaning air filters and providing rugs at the office entrance are simple, inexpensive, and effective ways to support worker health and improve air quality.

Protecting air quality and supporting human health should align with the goals of construction safety programs. Any cost-neutral or low-cost actions should be implemented. These activities should be a starting point for construction managers to consider and to generate other innovative ideas to protect air quality and improve human health on site.

 

MANAGING MATERIALS MORE EFFECTIVELY

A typical construction project deals with huge quantities of concrete, metal, wood, drywall, finishes, and all the concomitant packaging. Each material has to be purchased, handled, stored, installed, or disposed of. The constant influx of materials and their differing characteristics and requirements make it difficult for the contractor to green the total material handling process. Yet the variety and volume of materials provides a range of opportunities for improvement.

While contractors have less control over the materials that will be permanently installed in the building, they do have the ability and responsibility to select materials that are used temporarily on site. The contractor should review all materials that will be selected by the construction team to consider purchasing temporary materials that mirror LEED recommendations, such as reused materials, materials with recycled content, materials from within a 500-mile radius of the project, and materials with green certifications.

Materials purchased for construction techniques or as general requirements include temporary fencing, site signage, flooring or casework protection, and safety and scaffolding supplies. The contractor should consider purchasing reusable fencing in lieu of a one-time use fence. Signage should be designed to be reusable on future projects. Cardboard for flooring or casework protection should be ordered with 100% recycled content. FSC-certified wood can be selected for scaffolding or safety barriers.

The contractor should determine which materials can be selected more sustainably and at what, if any, additional cost. The contractor should purchase cost-neutral product alternatives and work with the owner to determine if there is an interest in paying a premium to select more sustainable construction materials.

The construction manager should also develop a plan to ensure appropriately timed material deliveries and suitable storing conditions for any materials on site. Accurately timed materials delivery minimizes the duration materials are on site before installation. If materials must be stored, they must be kept clean, dry, and away from other work activities. These recommendations are cost-neutral practices that will prevent materials from being damaged and becoming waste.

According to the EPA, building-related construction and demolition activities account for nearly 26% of non-industrial waste generation in the U.S., totaling about 160 million tons per year. Although 20-30% of building-related C&D debris is recovered for processing and recycling, the opportunity exists to recover more than twice this amount through better planning and management.

A construction waste management plan can minimize the waste generated on site and divert the waste that is generated away from landfill. Waste management plans have become a best practice for LEED projects, but they have yet to become a mandatory requirement for contractors on every project. This is another example of a contractor’s opportunity to manage materials sustainably on site and make a significant impact on the environment.

Development and implementation of an appropriate waste management program can result in waste diversion of 90% or more. Feasible diversion percentages rely heavily on the materials that will be used for the project, require a full commitment from on-site workers and waste haulers, and vary depending on the recycling and diversion options within the geographic region of the project.

Before any construction activities begin, the contractor should analyze the materials that will be used for the project and determine what types of material waste will be generated. The contractor can then locate local haulers and recyclers that can recycle the waste.

Contractors should also consider which of the waste materials can be reused on site—for example, concrete waste can be crushed and reused as subbase or temporary roadways. Developing an appropriate plan for the anticipated waste and verifying haulers’ and recyclers’ diversion processes before construction begins will smooth the coordination of the waste management plan and ensure maximum diversion from landfill.

There are opportunities in the temporary office or job site trailer to improve material selection as well. Batteries and electronics can be recycled. The team may be able to salvage or reuse office furniture instead of purchasing new furniture. Installing a water filtration system within the trailer will minimize waste generated from water bottles. Going paperless (or as paperless as possible) will save paper and minimize waste. The rapidly growing use of tablets and other portable digital devices is making this transition easier.

 

ADDRESSING COMMUNICATION AND EDUCATION

Successful execution of a construction sustainability program depends heavily on communication and education. The contractor’s team, subcontractors, trade workers, building owner’s staff, vendors, and suppliers must be aware of the goals and must commit to making the applicable improvements in their work practices.

The contractor should provide a list of the sustainable activities to be implemented, along with their requirements and benefits, and request feedback and confirmation from all players on the job site.

Continuous education and commitment can be accomplished by: 1) posting a list of the project’s sustainability rules in the break area or other prominent location, 2) reminding workers of the sustainability goals in weekly meetings, and 3) periodically announcing sustainability targets and environmental benefits the project has achieved.

Finally, it is extremely beneficial to designate a team member to act as on-site champion of the initiative. This individual should coordinate orientation and worker education and oversee implementation of the sustainable activities. The on-site coordinator should communicate up the chain as well. Monthly progress reports should be provided to the building owner and construction company managers, to reinforce the commitment to sustainability within the company culture and to communicate developing sustainability trends and any gaps within the sustainability program.

 

About the Author: Jackie Mustakas is Sustainability Manager at Robins & Morton. Based in the Orlando, Fla., office, she chairs the firm’s Sustainability Council. She holds an MS in building construction from the University of Florida.

Related Stories

AEC Innovators | Apr 26, 2024

National Institute of Building Sciences announces Building Innovation 2024 schedule

The National Institute of Building Sciences is hosting its annual Building Innovation conference, May 22-24 at the Capital Hilton in Washington, D.C. BI2024 brings together everyone who impacts the built environment: government agencies, contractors, the private sector, architects, scientists, and more. 

Contractors | Apr 26, 2024

AGC releases decarbonization playbook to help assess, track, reduce GHG emissions

The Associated General Contractors of America released a new, first-of-its-kind, decarbonization playbook designed to help firms assess, track, and reduce greenhouse gas emissions on projects. The AGC Playbook on Decarbonization and Carbon Reporting in the Construction Industry is part of the association’s efforts to make sure construction firms play a leading role in crafting carbon-reduction measures for the industry.

Mass Timber | Apr 25, 2024

Bjarke Ingels Group designs a mass timber cube structure for the University of Kansas

Bjarke Ingels Group (BIG) and executive architect BNIM have unveiled their design for a new mass timber cube structure called the Makers’ KUbe for the University of Kansas School of Architecture & Design. A six-story, 50,000-sf building for learning and collaboration, the light-filled KUbe will house studio and teaching space, 3D-printing and robotic labs, and a ground-level cafe, all organized around a central core.

Senior Living Design | Apr 24, 2024

Nation's largest Passive House senior living facility completed in Portland, Ore.

Construction of Parkview, a high-rise expansion of a Continuing Care Retirement Community (CCRC) in Portland, Ore., completed recently. The senior living facility is touted as the largest Passive House structure on the West Coast, and the largest Passive House senior living building in the country.

Hotel Facilities | Apr 24, 2024

The U.S. hotel construction market sees record highs in the first quarter of 2024

As seen in the Q1 2024 U.S. Hotel Construction Pipeline Trend Report from Lodging Econometrics (LE), at the end of the first quarter, there are 6,065 projects with 702,990 rooms in the pipeline. This new all-time high represents a 9% year-over-year (YOY) increase in projects and a 7% YOY increase in rooms compared to last year.

ProConnect Events | Apr 23, 2024

5 more ProConnect events scheduled for 2024, including all-new 'AEC Giants'

SGC Horizon present 7 ProConnect events in 2024.

75 Top Building Products | Apr 22, 2024

Enter today! BD+C's 75 Top Building Products for 2024

BD+C editors are now accepting submissions for the annual 75 Top Building Products awards. The winners will be featured in the November/December 2024 issue of Building Design+Construction. 

Resiliency | Apr 22, 2024

Controversy erupts in Florida over how homes are being rebuilt after Hurricane Ian

The Federal Emergency Management Agency recently sent a letter to officials in Lee County, Florida alleging that hundreds of homes were rebuilt in violation of the agency’s rules following Hurricane Ian. The letter provoked a sharp backlash as homeowners struggle to rebuild following the devastating 2022 storm that destroyed a large swath of the county.

Mass Timber | Apr 22, 2024

British Columbia changing building code to allow mass timber structures of up to 18 stories

The Canadian Province of British Columbia is updating its building code to expand the use of mass timber in building construction. The code will allow for encapsulated mass-timber construction (EMTC) buildings as tall as 18 stories for residential and office buildings, an increase from the previous 12-story limit. 

Standards | Apr 22, 2024

Design guide offers details on rain loads and ponding on roofs

The American Institute of Steel Construction and the Steel Joist Institute recently released a comprehensive roof design guide addressing rain loads and ponding. Design Guide 40, Rain Loads and Ponding provides guidance for designing roof systems to avoid or resist water accumulation and any resulting instability.

boombox1 - default
boombox2 -
native1 -

More In Category


Contractors

AGC releases decarbonization playbook to help assess, track, reduce GHG emissions

The Associated General Contractors of America released a new, first-of-its-kind, decarbonization playbook designed to help firms assess, track, and reduce greenhouse gas emissions on projects. The AGC Playbook on Decarbonization and Carbon Reporting in the Construction Industry is part of the association’s efforts to make sure construction firms play a leading role in crafting carbon-reduction measures for the industry.


Mass Timber

Bjarke Ingels Group designs a mass timber cube structure for the University of Kansas

Bjarke Ingels Group (BIG) and executive architect BNIM have unveiled their design for a new mass timber cube structure called the Makers’ KUbe for the University of Kansas School of Architecture & Design. A six-story, 50,000-sf building for learning and collaboration, the light-filled KUbe will house studio and teaching space, 3D-printing and robotic labs, and a ground-level cafe, all organized around a central core.


halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021