Construction milestone reached for $1B expansion of San Diego International Airport

Construction milestone reached for $1B expansion of San Diego International Airport

Components of the $9-million structural concrete construction phase included a 700-foot-long, below-grade baggage-handling tunnel; metal decks covered in poured-in-place concrete; slab-on-grade for the new terminal; and 10 exterior architectural columns––each 56-feet tall and erected at a 14-degree angle.


By Posted by Tim Gregorski, Senior Editor | May 30, 2012
Bomel Construction Co. recently completed the structural concrete phase of the l
Bomel Construction Co. recently completed the structural concrete phase of the largest construction project ever undertaken at S

Calif.-based Bomel Construction Co. recently completed the structural concrete phase of the largest construction project ever undertaken at San Diego International Airport.

The $1 billion expansion, called Green Build, consists of a 430,000-sf. terminal building with 10 gates on the west side of Terminal 2 West, a dual-level roadway separating arriving and departing passengers, additional security lanes and an expanded concession area. The design-build project will be completed in the first quarter of 2013, with the new terminal opening soon thereafter.

Green Build, which includes a number of energy-saving and environmentally sensitive measures, is being built to achieve LEED Silver certification from the USGBC.

Components of the $9-million structural concrete construction phase included a 700-foot-long, below-grade baggage-handling tunnel; metal decks covered in poured-in-place concrete; slab-on-grade for the new terminal; and 10 exterior architectural columns––each 56-feet tall and erected at a 14-degree angle.

Construction of the baggage-handling tunnel, which preceded construction of the terminal building above it, was completed in January 2011.

The metal decks and incline column phases of the project were completed in October 2011, while the slab-on-grade for the new building was finished in January 2012. Bomel employed between 25 and 30 workers during the duration of the project.

By the time it’s completed next year, Green Build will have employed between 2,500 and 3,000 construction workers. +

Related Stories

| Aug 30, 2013

State Government Report [2013 Giants 300 Report]

Stantec, Jacobs, PCL Construction among nation's top state government design and construction firms, according to BD+C's 2013 Giants 300 Report.

| Aug 28, 2013

Federal Government Report [2013 Giants 300 Report]

Building Design+Construction's rankings of the nation's largest federal government design and construction firms, as reported in the 2013 Giants 300 Report.  

| Aug 26, 2013

What you missed last week: Architecture billings up again; record year for hotel renovations; nation's most expensive real estate markets

BD+C's roundup of the top construction market news for the week of August 18 includes the latest architecture billings index from AIA and a BOMA study on the nation's most and least expensive commercial real estate markets. 

| Aug 22, 2013

Energy-efficient glazing technology [AIA Course]

This course discuses the latest technological advances in glazing, which make possible ever more efficient enclosures with ever greater glazed area.

| Aug 21, 2013

Why research is the ticket to successful airport wayfinding

Wayfinding is more than just signs; it requires a holistic approach based on communicating information that helps people make the right decision at the right time. 

| Aug 19, 2013

Discovery of hidden asbestos complicates DFW terminal renovations

The finding of more asbestos in Terminal B than expected, and the pending merger of US Airways and the airport’s largest tenant, American Airlines, is causing construction delays on a $2.3 billion Dallas/Fort Worth Airport terminal renovation.

| Aug 19, 2013

Integration of solar panels in building skin seen as key net-zero element

Recent high-profile projects, including stadiums in Brazil for the upcoming World Cup and Summer Olympics and a bank headquarters in the U.K., reflect an effort by designers to adopt building-integrated photovoltaics, or BIPV.

| Aug 14, 2013

Green Building Report [2013 Giants 300 Report]

Building Design+Construction's rankings of the nation's largest green design and construction firms. 

| Jul 29, 2013

2013 Giants 300 Report

The editors of Building Design+Construction magazine present the findings of the annual Giants 300 Report, which ranks the leading firms in the AEC industry.

| Jul 22, 2013

Transportation Facility Report [2013 Giants 300 Report]

Building Design+Construction's rankings of design and construction firms with the most revenue from airport terminals and other transportation-related facilities, as reported in the 2013 Giants 300 Report.

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021