TSX Broadway is a 550,000-sf 46-story mixed-use tower that’s been under construction in New York City’s Times Square since 2019. This $2.5 billion project—whose development partners include L&L Holding, Maefield Development, Fortress Investment, and The Nederlander Organization—has retained 25 percent of site’s existing structure that included 16 stories of what had been a DoubleTree hotel, and the iconic Palace Theater, which on January 7 began its journey from the ground floor of this site to being lifted and repositioned 30 ft above grade to make way for 75,000 sf of street-level retail.
The lift of the 7,000-plus-ton, 27,000-sf theater with landmark status was expected to take six to eight weeks, at which point the Palace Theater will undergo a $50 million renovation that includes a new entrance on 47th Street with an 80-ft marquee, the addition of 10,000 sf of front-of-house space with a new lobby, a new orchestra pit for the 1,700-seat theater, and more back-of-house space.
Last week, the project’s Building Team poured the 43rd floor of TSX Broadway, which along with the theater is scheduled for completion in the fourth quarter of 2022, according to Robert Israel, Executive Vice President of L&L Holding and the firm’s project manager, with whom BD+C spoke earlier this week.
Also see: An animation of the demolition, excavation, and theater lift
HEAVY LIFTING
This project, he said, required a new permanent foundation, a new subcellar level, and a lifting foundation. The lift itself is utilizing a mechanism, devised by Urban Foundation Engineering, that combines 34 structural lifting posts and 136 hydraulic jacks. Israel said that the developers hired the structural engineering consultant Howard Shapiro & Associates to ensure the security and stability of the structure and theater, which was originally built in 1913 and remodeled in 1988.
The 580-ft-tall tower, when completed, will also feature a 669-key hotel (Israel said the developers were close to signing a branding and property management deal, but could not disclose the hotelier).
RISING ABOVE THE NOISE
The building will also have several signage and lighting systems, all designed for marketing purposes: the exterior of floors three through nine will be distinguished by an 18,000-sf LED podium sign into which is integrated an indoor-outdoor stage with a 30x30-ft opening and a 35-ft depth that extends 10 ft outside beyond the LED lights. Israel suggested that this space could be used for New Year’s Eve events, and all manner of performances and broadcasts.
There will also be crown signage at the top of the building, and a full-tower lighting system, dubbed The Beacon, that will be able to project programmed messages and images.
Also see: How TSX Broadway will become the world’s largest billboard
TSX Broadway’s Building Team includes Mancini Duffy (AOR core and shell and hotel), PBDW Architects (AOR theater design and historic preservation), Jablonski Building Conservation (historic preservation consultant), Wise Janney Elsner Engineers & Architects (plaster structural support consultant), Cosentini (MEP), Langan (SOE/foundation engineering consultant), Severud (SE), and Perkins Eastman (lead design of building envelope).
Related Stories
| Aug 11, 2010
AASHE releases annual review of sustainability in higher education
The Association for the Advancement of Sustainability in Higher Education (AASHE) has announced the release of AASHE Digest 2008, which documents the continued rapid growth of campus sustainability in the U.S. and Canada. The 356-page report, available as a free download on the AASHE website, includes over 1,350 stories that appeared in the weekly AASHE Bulletin last year.
| Aug 11, 2010
Girl Scouts of San Jacinto Council Program Place Project
Houston, Texas
The Girl Scouts of San Jacinto Council Program Place is the headquarters for the largest Girl Scout Council in the U.S., with 63,000 scouts. The building houses the council’s administrative offices, a Girl Scout museum, and activity space. When an adjacent two-story office building became available, the council jumped at the chance to expand its museum and program space.
| Aug 11, 2010
Burt Hill, HOK top BD+C's ranking of the nation's 100 largest university design firms
A ranking of the Top 100 University Design Firms based on Building Design+Construction's 2009 Giants 300 survey. For more Giants 300 rankings, visit http://www.BDCnetwork.com/Giants
| Aug 11, 2010
PBK, DLR Group among nation's largest K-12 school design firms, according to BD+C's Giants 300 report
A ranking of the Top 75 K-12 School Design Firms based on Building Design+Construction's 2009 Giants 300 survey. For more Giants 300 rankings, visit http://www.BDCnetwork.com/Giants
| Aug 11, 2010
Turner Building Cost Index dips nearly 4% in second quarter 2009
Turner Construction Company announced that the second quarter 2009 Turner Building Cost Index, which measures nonresidential building construction costs in the U.S., has decreased 3.35% from the first quarter 2009 and is 8.92% lower than its peak in the second quarter of 2008. The Turner Building Cost Index number for second quarter 2009 is 837.
| Aug 11, 2010
AGC unveils comprehensive plan to revive the construction industry
The Associated General Contractors of America unveiled a new plan today designed to revive the nation’s construction industry. The plan, “Build Now for the Future: A Blueprint for Economic Growth,” is designed to reverse predictions that construction activity will continue to shrink through 2010, crippling broader economic growth.
| Aug 11, 2010
Section Eight Design wins 2009 Open Architecture Challenge for classroom design
Victor, Idaho-based Section Eight Design beat out seven other finalists to win the 2009 Open Architecture Challenge: Classroom, spearheaded by the Open Architecture Network. Section Eight partnered with Teton Valley Community School (TVCS) in Victor to design the classroom of the future. Currently based out of a remodeled house, students at Teton Valley Community School are now one step closer to getting a real classroom.