9/11 museum triumphs over controversy

Building Team Awards

9/11 museum triumphs over controversy

The Building Team for this highly visible project had much more than design, engineering, and construction problems to deal with.


By John Caulfield, Senior Editor | April 9, 2015
9/11 museum triumphs over controversy

The National September 11 Memorial Museum incorporates evocative artifacts of the destroyed Twin Towers, including the skyscapers’ slurry wall and the “Last Column.” Photos: James Ewing Photography / courtesy Davis Brody Bond

This article first appeared in the April 2015 issue of BD+C.

The National September 11 Memorial Museum may have been a relatively small part of the 16-acre World Trade Center mega-project, which included the building of four commercial towers and a massive transportation hub. But the museum’s construction was no less complex, and was complicated by enormous—and at times conflicting—political, public, and emotional considerations that ultimately influenced its design, budget, and scheduling.

PROJECT SUMMARY
GOLD AWARD
National September 11 Memorial Museum
New York, N.Y.

BUILDING TEAM
Submitting firm: Davis Brody Bond (architect)

Owner/developer: National September 11 Memorial and Museum
Structural engineer: WSP Cantor Seinuk (slurry wall): Simpson Gumpertz & Heger; Guy Nordenson & Associates Structural Engineers
Geotechnical engineer: Langan Engineering & Environmental Services (slurry wall): Mueser Rutledge Consulting Engineers
MEP engineer/vertical transport: Jaros Baum & Bolles
Blast design: Weidlinger Associates
Code consultant: Code Consultants, Inc.
Acoustical/vibration design: Cerami & Associates
Lighting design: Fisher Marantz Stone
Graphic design: C&G Partners
Cost estimating: Faithful + Gould
Historic preservation: Higgins Quasebarth & Partners
Security design: Arup
Building envelope/waterproofing: Wiss, Janney, Elstner Associates
Specifications: Construction Specifications, Inc.
GC/CM: Lend Lease

GENERAL INFORMATION
Project size: 775,000 sf (Museum: 268,000 sf; chiller plant: 163,000 sf)
Construction cost: $700 million (museum and memorial)
Construction period: August 2006 to May 2014
Delivery method: Construction management

“The 9/11 Museum combines all of the building trades, as well as collective memory, bureaucracy, and ideology,” says SmithGroupJJR’s Bill Kline, AIA, EDAC, LEED AP, a Building Team Awards judge. “It is a design and technical achievement in a context fraught with controversy and contradiction.”

The design needed to take into account the various opinions and agendas of more than 30 consulting parties, including government agencies, preservationists, and groups that represented the surrounding community and survivors and victims of the attacks.

Through that process, the Building Team, led by architect Davis Brody Bond, became acutely aware of the importance of preserving certain artifacts of the former Twin Towers, notably its north and south footprints and the remaining slurry wall. The design evolved into a series of spaces that evokes both the scale of the loss and the still-resonant physical impressions left by the towers.

Some of the artifacts—specifically, the “Survivors’ Stair” and “Last Column”—were so large and heavy that GC/CM Lend Lease had to install them in their designated exhibition locations before the walls, floors, and roof could be constructed around them.

The Building Team’s architectural and materials choices centered on enhancing the visitor experience and articulating four core design principles: Memory, Authenticity, Scale, and Emotion.

Within the museum’s excavation are two new insertions: the Tower Volumes, which align with the footprints of the original Twin Towers and the reflecting pools within the 9/11 Memorial; and the Ribbon, a ramp between the Tower Volumes that brings visitors to the bedrock level.

The museum lies 70 feet below street level, beneath the eight-acre 9/11 Memorial that doubles as the museum’s green roof. Politicians had committed to opening the Memorial Plaza on the 10th anniversary of the attacks. So the museum and memorial needed to define project boundaries and coordinate shared superstructure and site utilities for economy and logistics, as well as coordinate project schedules and shared costs.

Project planning and coordination also helped avert what could have been a crippling blow when Hurricane Sandy blew into New York in late October 2012.

The superstorm flooded the primary level of the museum with eight feet of water, threatening to delay the museum’s opening by six months. By adjusting work schedules and reallocating work forces to higher levels of the museum while flood remediation was under way, the cleanup and reconstruction efforts were completed in only three months.

In that process, the cooperation of the full Building Team, including materials suppliers, vendors, and fabricators, minimized Sandy’s impact and helped this project hit its completion target.

 

The Last Column needed to be lowered into its position before the street-level Memorial Plaza could be completed. 

 

Visitors to the museum enter its main spaces through a ramped descent that offers them “Progressive Disclosure” of exhibits that are not quite close enough to touch and, therefore, enhance “Emotion,” one of the museum’s four core design principles, along with Memory, Authenticity, and Scale. 

Related Stories

Building Team Awards | Jun 14, 2017

17 projects earn BD+C's 2017 Building Team Awards

Of the 17 projects, one received a Platinum Award, six received Gold Awards, six received Silver Awards, two received Bronze Awards, and two received Honorable Mentions.

Building Team Awards | Jun 14, 2017

3D-printed office: Office of the Future

Dubai kicks off 3D-printing tech initiative with a novel office project.

Building Team Awards | Jun 14, 2017

A space for all: Lighthouse for the Blind and Visually Impaired

Nonprofit HQ fitout improves functionality, accessibility for blind and low-vision individuals.

Building Team Awards | Jun 13, 2017

Government campus reimagined: Intelligence Community Campus

Building Team converts 1940s campus into a sleek, modern home for U.S. intelligence agencies.

Building Team Awards | Jun 13, 2017

Secluded sanctuary: Alnoba leadership training center

Leadership training center becomes New England’s first Passive House building.

Building Team Awards | Jun 12, 2017

Circles and squares: Faena Arts Center

Silver Award: The Faena Arts Center’s forum is divided into two volumes, one a cylinder, the other a cube.

Building Team Awards | Jun 12, 2017

The right prescription: University of North Dakota School of Medicine & Health Sciences

Silver Award: North Dakota builds a new medical/health sciences school to train and retain more physicians.

Building Team Awards | Jun 12, 2017

Texas technopark: TechnipFMC John T. Gremp Campus

Silver Award: TechnipFMC’s new campus marks the start of a massive planned community in north Houston.

Building Team Awards | Jun 8, 2017

Quick turnaround: Partners HealthCare

Silver Award: A 2½-year project brings Partners HealthCare’s sprawling administrative functions under one roof.

Building Team Awards | Jun 8, 2017

Raising the bar: Zurich North American Headquarters

Silver Award: Forgoing a typical center-core design, the Zurich North America Headquarters rises 11 stories across three stacked bars.

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021