Washington, D.C.’s first modular apartment building breaks ground

Multifamily Housing

Washington, D.C.’s first modular apartment building breaks ground

Eric Colbert & Associates designed the building.


By David Malone, Associate Editor | September 29, 2020

Modo, the first modular apartment building in Washington, D.C. has begun construction. In a period of only eight days 44 custom designed modular boxes shipped from Pennsylvania were lifted into place by crane to create 16 of Modo’s 17 three-bedroom apartments.

The modules arrived onsite 80% finished. Each three-bedroom Modo apartment features built-in custom closets, shelving, desks meant to facilitate remote working, and a spacious living room with a pre-installed jumbo flat-screen TV. 

“We were looking for more efficient and environmentally-friendly alternatives to typical construction types,” said Grant Epstein, President of Community Three, the project’s developer, in a release. “Modular construction can reduce construction time by almost one-third, while generating far less onsite construction waste. Construction components typically exposed to the elements – such as windows and wood framing – are built with higher quality because they are assembled indoors. As a result, these modular units offer superior insulation, weather barriers, sound attenuation, and indoor finishes compared with those constructed traditionally.”

The community is designed to appeal to the twenty-somethings of Generation Z, with enough bedrooms to accommodate multiple roommates. An automated entry system will allow tenants to use a smartphone app to access both the building and their apartments.

In addition to the apartments, a concrete-and-steel podium, under construction since April, will house the building’s lobby and a 3,000-sf street-level retail space that can provide over 100 outdoor cafe seats. The lobby will be furnished with a seating area for relaxing, eating, and remote working. A green roof deck with seating and grilling areas will also be included, along with a single penthouse apartment with a private outdoor terrace that is being built on the roof level.

Urban Pace will begin pre-leasing the apartments in March, 2021. Community Three is partnering with Washington, DC-based Rooney Properties on the project. The team worked with the Modular Mobilization Coalition to select Philadelphia-based VBC Construction as modular contractor. VBC in turn partnered with Scranton, PA-based Simplex Homes as the modular fabricator. The manufacturing team worked closely with DC-based project architect Eric Colbert & Associates to ensure seamless integration of market focus and construction methodology.

Related Stories

| May 2, 2014

Norwegian modular project set to be world's tallest timber-frame apartment building [slideshow]

A 14-story luxury apartment block in central Bergen, Norway, will be the world's tallest timber-framed multifamily project, at 49 meters (160 feet). 

| May 1, 2014

Tight on space for multifamily? Check out this modular kitchen tower

The Clei Ecooking kitchen, recently rolled out at Milan's Salone de Mobile furniture fair, squeezes multiple appliances into a tiny footprint.

| Apr 30, 2014

Visiting Beijing's massive Chaoyang Park Plaza will be like 'moving through a urban forest'

Construction work has begun on the 120,000-sm mixed-use development, which was envisioned by MAD architects as a modern, urban forest.

| Apr 29, 2014

Best of Canada: 12 projects nab nation's top architectural prize [slideshow]

The conversion of a Mies van der Rohe-designed gas station and North Vancouver City Hall are among the recently completed projects to win the 2014 Governor General's Medal in Architecture. 

| Apr 29, 2014

USGBC launches real-time green building data dashboard

The online data visualization resource highlights green building data for each state and Washington, D.C.

| Apr 23, 2014

Developers change gears at Atlantic Yards after high-rise modular proves difficult

At 32 stories, the B2 residential tower at Atlantic Yards has been widely lauded as a bellwether for modular construction. But only five floors have been completed in 18 months.

| Apr 17, 2014

Online mapping tool helps teams determine multifamily project tax credit eligibility

Accounting and advisory firm Baker Tilly has launched a new, interactive online mapping tool that helps users determine if a business or development project may qualify for the New Markets Tax Credit or Low-Income Housing Tax Credit program.

| Apr 11, 2014

ULI report documents business case for building healthy projects

Sustainable and wellness-related design strategies embody a strong return on investment, according to a report by the Urban Land Institute.

| Apr 9, 2014

Steel decks: 11 tips for their proper use | BD+C

Building Teams have been using steel decks with proven success for 75 years. Building Design+Construction consulted with technical experts from the Steel Deck Institute and the deck manufacturing industry for their advice on how best to use steel decking.

| Apr 2, 2014

8 tips for avoiding thermal bridges in window applications

Aligning thermal breaks and applying air barriers are among the top design and installation tricks recommended by building enclosure experts.

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021