flexiblefullpage -
billboard - default
interstitial1 - interstitial
catfish1 - bottom
Currently Reading

Nave restored at Yale’s Sterling Memorial Library

Reconstruction Awards

Nave restored at Yale’s Sterling Memorial Library

Turner Construction and Helpern Architects revived the 150-foot-long nave, which was embellished with stained glass windows by G. Owen Bonawit, stone carvings by René P. Chambellan, and decorative ironwork by Samuel Yellin.


By Robert Cassidy, Executive Editor | November 19, 2015
Nave restored at Yale’s Sterling Memorial Library

Yale's Sterling Memorial Library. Photo: Brian Rose.

When Yale University’s Sterling Library, designed by James Gamble Rogers (Class of 1889), opened in 1931, it was clear that the Collegiate Gothic structure had fulfilled the architect’s vision of a “temple of learning and a cathedral of knowledge.” The quasi-religious experience began right at the main entrance, the 150-foot-long nave, which was embellished with stained glass windows by G. Owen Bonawit, stone carvings by René P. Chambellan, and decorative ironwork by Samuel Yellin.

Four years ago, the university determined that the nave had suffered considerable deterioration and needed to be restored to its original condition. A Building Team led by Turner Construction Company and Helpern Architects was given a strict set of mandates: Make the new nave indistinguishable from the old. Take nothing away from the historic character of the original masonry, metal, finishes, painted surfaces, and stained glass. Improve library operations and update its technology to accommodate Sterling’s physical and digital collections.

SILVER AWARD

Sterling Memorial Library, Yale University  New Haven, Conn.

Building Team
Submitting firms: Turner Construction Company (CM); Helpern Architects (architect)
Owner: Yale University
SE: Robert Silman Associates
MEP engineer: AKF Group
Acoustics/AV: Jaffe Holden

General Information
Size: 13,000 sf
Construction cost: $13.5 million
Construction time: June 2013 to August 2014
Delivery method: CM at risk

These tasks were complicated by the further requirement to modernize the nave’s MEP systems—upgrading the lighting to current standards, inserting air-conditioning, concealing the fire alarm system, etc. This had to be accomplished without disturbing the load-bearing stone walls, piers, and columns, which offered no room to incorporate pipes, conduit, and other key infrastructure.

Without any existing cavity wall or chase wall spaces in which to route new mechanical services, the Building Team had to figure out how to jam in critical infrastructure anywhere it could while preserving the existing architectural elements.

Early in the design phase, Turner suggested moving the proposed new mechanical room from its original position in the library stack to unused attic space. The CM hung an aluminum catwalk system from the wood roof framing and created a temporary opening in the stone façade just large enough to fit the air-handling unit. Mechanical piping was installed by opening the roof and craning new risers in from above, the risers running the full length of the shaft.

The last piece of the MEP puzzle had to do with the new fan coil units. Millwork subcontractor CW Keller & Associates created a system of hidden doors within the existing millwork that concealed the fan coil units while maintaining the historic appearance of the card catalog fixtures.

With the MEP matter behind them, the Building Team attacked the remaining problems. Femenella & Associates, working with Helpern Architects, restored the Bonawit stained glass windows. Kugler Ning Lighting Design installed new LED lighting to brighten the interior. The architect reorganized the functions of the three service desks into a single unit, created small meeting spaces in the nave’s north aisle, and reconfigured the circulation desk for easier entry to the stacks.

 

Sterling Memorial Library, originally designed by Yale alumnus James Gamble Rogers, opened in 1931. The Alma Mater mural rises at the end of the 150-foot-long nave (below). Twenty-seven original stained glass windows by G. Owen Bonawit in the nave were restored. Photos: Brian Rose.

Related Stories

Reconstruction Awards | Nov 12, 2018

Cincinnati Music Hall: Saving a cultural anchor

Cincinnati uses ‘skillful triage’ to bring its endangered Music Hall up to date.

Reconstruction Awards | Dec 1, 2017

Rescue mission: Historic movie palace is now the centerpiece of Baltimore’s burgeoning arts hub

In restoring the theater, the design team employed what it calls a “rescued ruin” preservation approach.

Reconstruction Awards | Dec 1, 2017

Gothic revival: The nation’s first residential college is meticulously restored

This project involved the renovation and restoration of the 57,000-sf hall, and the construction of a 4,200-sf addition.

Reconstruction Awards | Dec 1, 2017

Rockefeller remake: Iconic New York tower is modernized for its next life

To make way for new ground-floor retail and a more dramatic entrance and lobby, the team removed four columns at the ground floor.

Reconstruction Awards | Nov 30, 2017

BD+C's 2017 Reconstruction Award Winners

Provo City Center Temple, the Union Trust Building, and the General Motors Factory One are just a few of the projects recognized as 2017 Reconstruction Award winners.

Reconstruction Awards | Nov 29, 2017

College credit: Historic rehab saves 50% on energy costs

The project team conducted surveys of students, faculty, and staff to get their input.

Reconstruction Awards | Nov 29, 2017

Amazing grace: Renovation turns a church into elegant condos

The windows became The Sanctuary’s chief sales edge.

Reconstruction Awards | Nov 28, 2017

Broadway melody: Glass walls set just the right tone for a historic lobby in Lower Manhattan

The adaptation of the 45,000-sf neoclassical lobby at 195 Broadway created three retail spaces and a public walkway.

Reconstruction Awards | Nov 27, 2017

Higher education: The rebirth of a Washington, D.C., high school

The project team, led by architect Perkins Eastman, restored the original cupola.

Reconstruction Awards | Nov 27, 2017

Bank statement: A project team saves a historic bank, yielding 100% leaseup for the developer

The project team had to fix poor renovations made in the ’50s.

boombox1 - default
boombox2 -
native1 -

More In Category


Giants 400

BD+C Awards Programs

Entry information and past winners for Building Design+Construction's two major awards programs: 40 Under 40 and Giants 400



halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021