flexiblefullpage -
billboard - default
interstitial1 - interstitial
catfish1 - bottom
Currently Reading

Mercedes-Benz Stadium delayed until late August

Sports and Recreational Facilities

Mercedes-Benz Stadium delayed until late August

The stadium is now scheduled to open on Aug. 26 in a preseason game between the Falcons and the Jaguars.


By David Malone, Associate Editor | April 19, 2017

Rendering courtesy HOK

Mercedes-Benz Stadium is destined to become one of the best and most visually striking stadiums in sports when it finally opens. When the stadium will open, however, is starting to become a talking point, as the date has been pushed back again to Aug. 26.

The $1.6 billion-stadium, designed by HOK, was originally planned to open on March 1, 2017. Since that time the opening has been delayed three times to June 1, 2017, then to July 30, 2017, and more recently (and hopefully finally) to Aug. 26, 2017.

Originally, it was thought the delays were related to issues with getting the unique retractable roof to work correctly. While retractable roofs aren’t new to sports stadiums, most slide open like a large garage door. The roof of Mercedes-Benz Stadium takes a more complicated approach and opens in a circular motion, more closely resembling a blooming flower than a garage door.

Steve Cannon, CEO of AMB Group, the stadium’s owner, addressed concerns about the roof in a statement after the most recent delay. “No concerns about the operability of the roof have ever been expressed to us by the design or construction teams,” Cannon said in the statement.

Cannon went on to explain the reason for the delays. “Normal surveying and analysis of the roof structure, as well as steelwork in the roof, have both taken longer than planned. Those two things have had a cascading effect on overall workflows related to the roof, and that is the reason for the new timeline.”

The 71,000-seat stadium will be home to the Atlanta Falcons and the Atlanta United. It will also host the NCAA Peach Bowl and the Celebration Bowl. The stadium will host Super Bowl LIII on Feb. 3, 2019.

HOK collaborated on the design with tvsdesign, Goode Van Slyke Architecture, and Stanley Beaman & Sears. BuroHappold Engineering and Hoberman Associates handled structural engineer duties for the project.

Related Stories

Giants 400 | Oct 12, 2018

Sports venues reach outside their walls

Professional and collegiate facilities invite fans to engage with the community.

Sports and Recreational Facilities | Aug 9, 2018

Populous-designed Buffalo Bills training center expansion will begin construction this fall

Arc Building Partners will lead construction efforts on the project.

| May 24, 2018

Accelerate Live! talk: Security and the built environment: Insights from an embassy designer

In this 15-minute talk at BD+C’s Accelerate Live! conference (May 10, 2018, Chicago), embassy designer Tom Jacobs explores ways that provide the needed protection while keeping intact the representational and inspirational qualities of a design.

Building Team Awards | May 16, 2018

Game, set, match: United States Tennis Association National Campus

Gold Award: With 100 courts and more than 260,000 sf of vertical construction, the USTA National Campus is a sanctuary for tennis enthusiasts.

Sports and Recreational Facilities | May 15, 2018

Is this the most environmentally sustainable arena in the country?

The university arena was designed by Architectural Resources Cambridge.

Sports and Recreational Facilities | Apr 19, 2018

Watch a time-lapse of Wrigley Field’s most recent phase of renovations

The renovations took place between October 2017 and April 2018.

Sports and Recreational Facilities | Apr 3, 2018

Westminster College’s new athletic stadium includes a turf field and seating for 2,000

The project is the largest capital improvement project on the campus in over a decade.

Sports and Recreational Facilities | Mar 30, 2018

Final Four excitement? Here are two collegiate sports facilities to check out before your weekend of hoops

CannonDesign recently shared new images of two collegiate sports projects with interesting ties to college basketball past, present and future.

boombox1 - default
boombox2 -
native1 -

More In Category


Mixed-Use

A surging master-planned community in Utah gets its own entertainment district

Since its construction began two decades ago, Daybreak, the 4,100-acre master-planned community in South Jordan, Utah, has been a catalyst and model for regional growth. The latest addition is a 200-acre mixed-use entertainment district that will serve as a walkable and bikeable neighborhood within the community, anchored by a minor-league baseball park and a cinema/entertainment complex.


Cultural Facilities

Multipurpose sports facility will be first completed building at Obama Presidential Center

When it opens in late 2025, the Home Court will be the first completed space on the Obama Presidential Center campus in Chicago. Located on the southwest corner of the 19.3-acre Obama Presidential Center in Jackson Park, the Home Court will be the largest gathering space on the campus. Renderings recently have been released of the 45,000-sf multipurpose sports facility and events space designed by Moody Nolan.


halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021