flexiblefullpage -
billboard - default
interstitial1 - interstitial
catfish1 - bottom
Currently Reading

Ken Soble Tower becomes world’s largest residential Passive House retrofit

Multifamily Housing

Ken Soble Tower becomes world’s largest residential Passive House retrofit

The project team for the 18-story high-rise for seniors slashed the building’s greenhouse gas emissions by 94 percent and its heating energy demand by 91 percent.


By Robert Cassidy, Editor, Multifamily Design+Construction | April 7, 2022
Ken Soble Tower becomes world’s largest residential Passive House retrofit Photo: Codrin Talaba
ERA Architects and PCL Construction led the project team that delivered 114 studios, 31 one-bedroom units, and one two-bedroom apartment for CityHousing Hamilton at Ken Soble Tower. Photo: Codrin Talaba

Ken Soble Tower, an affordable housing high-rise for seniors in Hamilton, Ont., is now arguably the world’s largest residential building retrofitted to the Passive House standard.

Led by ERA Architects and PCL Construction, the project team slashed the 80,000-sf, 18-story building’s greenhouse gas emissions by 94% and its heating energy demand by 91% en route to achieving EnerPHit certification. The total energy needed to heat and cool one of its 146 units is now equivalent to that needed to power three 100-watt light bulbs.

Built in 1967 as part of the “North End Renewal” of West Harbour, an industrial neighborhood on Lake Ontario, the tower and an accompanying three-story walkup provided one-bedroom and bachelor apartments for families and single workingmen.

At the time, the complex, named after the founder of a local radio station and a local TV station, was considered a showcase property in the portfolio of CityHousing Hamilton, the municipal housing authority.

By 2012, however, the property was showing its age. The elevators constantly failed; so, too, the heating and cooling system. Mold, peeling paint, and water damage were apparent everywhere.

Worst of all: the pest problem. Forty-two percent of maintenance calls were for cockroaches, rodents, and bedbugs. The bedbug infestation was so bad the housing agency had to move whole floors of tenants to temporary housing on the 16th floor while crews tried to kill the critters. The bedbugs kept coming back.

The housing agency started relocating tenants. In less than four years, two-thirds of the apartments in Ken Soble Tower were vacant, despite a citywide waitlist of 6,000 families seeking affordable housing.

Ken Soble Tower becomes world’s largest residential Passive House retrofit 1.jpg

In 2015, CityHousing Hamilton, which manages 7,000 apartments in 1,265 properties, for 13,000 residents, surveyed the tower’s remaining residents about the future of the property; 83% responded. Their message to the agency: “Keep Ken Soble Tower.” A year later, the financial consulting firm Deloitte, acting on behalf of CityHousing Hamilton, studied the options—sell, demolish and rebuild, perform basic capital repairs, or refurbish—and came to the same conclusion: renovate. 

The housing agency gave the go-ahead to completely retrofit Ken Soble Tower, a project that became part of Canada’s National Housing Strategy to modernize and decarbonize older affordable apartments. The project was folded into the Tower Renewal Partnership, an initiative by the nonprofit Centre for Urban Growth and Renewal (cugr.ca) to transform Southern Ontario’s stock of post-war apartment towers into more healthy, resilient, and complete communities.

A FIVE-PRONGED APPROACH TO RESTORATION

The renewal effort had five objectives:

  1. Modernize all 146 dwelling units.
  2. Attain EnerPHit certification, based on 2050 temperature projections, to cut GHG emissions by 94% and energy intensity by 70%.
  3. Allow for aging-in-place, by creating 31 barrier-free residences and reconfiguring elevators, doorways, and residential garbage areas to allow for barrier-free movement throughout the building.
  4. Address the housing authority’s 30-year capital repair program.
  5. Maintain “deep affordability,” through Hamilton’s Rent Geared to Income subsidy.

The building envelope consisted of composite masonry walls with minimal interior insulation and vapor control layers; it was sorely deteriorated. The design team’s first thought was to build an entire wall assembly outside the brick. Instead, the team overcladded the structure: first, with a liquid-applied air barrier; followed by a DuROCK PUCCS NC noncombustible rainscreen EIFS system, which incorporated 50,000 sf of a six-inch-thick layer of Rockwool stone wool insulation into the façade; finally, a stucco finish. Another four inches of mineral wool was added to the interior.

The EIFS system helped the project realize the R-38 effectiveness required to achieve EnerPHit certification. The retrofit resulted in a 94% reduction in GHG emissions and a 91% cut in heating energy demand. In practical terms, it meant that the building would stay warm in winter for up to two days and below dangerous heat levels in summer for up to four days.

Ken Soble tower
Ken Soble Tower (at right in photo), an 18-story high-rise (with three-story secondary building), overlooks Lake Ontario, in Hamilton, Ont.

Concrete slab balconies were replaced with juliettes to meet maintenance and accessibility requirements and eliminate thermal bridging. Easily operable triple-glazed windows and doors were installed to encourage natural ventilation. The roof membranes and below-grade waterproofing were replaced with fluid-applied products and upgraded with up to 16 inches of insulation. 

Mechanical systems were completely overhauled with new central systems that provide tempered fresh air to each suite from rooftop energy recovery ventilators (ERVs), and individual control with in-suite variable-air volume (VAV) dampers with reheat. Common areas are served by smaller ERVs that are activated by occupancy sensors. A sophisticated building automation system will measure and verify that all building systems are functioning as designed.

The project came in at $34 million ($233,000/unit), 70% of which was for base building renewal, 30% for low-energy initiatives.

COMPREHENSIVE AIR TIGHTNESS TESTING

To achieve EnerPHit certification from Passive House Canada, the team developed a comprehensive air tightness testing and quality management program, led by PCL’s in-house building envelope engineering and construction team. Final operational whole building air tightness tests came in at 0.235 air changes/hr at 50 pa, beating the target by more than 50%.

One novel effort was that all building trades’ foremen and supervisors participated in a Passive House trades training session, with a focus on airtightness and reducing thermal bridging.

Ken Soble Tower becomes world’s largest residential Passive House retrofit 2.jpg

“Social sustainability” also played a part in the retrofit program. A dingy laundry room on the 18th floor was turned into a solarium, with views of the harbor. High-contrast wayfinding and bright color palettes were added to support community cohesion. Higher delivery of fresh air directly to units and the selection of low-VOC interior finishes greatly improved indoor air quality.

Adding to its distinctions, the Ken Soble Tower will become a teaching laboratory. CityHousing Hamilton, the University of Toronto, ERA Architects, and PCL Construction will, over the next two years, measure the impacts of the building on its residents and the surrounding environment, including building performance, occupant health and safety, and economic benefit.

PROJECT TEAM | KEN SOBLE TOWER
Owner: CityHousing Hamilton  
Lead Architect/Interiors/Landscape Design: ERA Architects  
Structural Engineer/Building Envelope Consultant: Entuitive  
Mechanical Engineer: Reinbold Engineering Group  
Electrical Engineer: Nemetz (S/A) & Associates  
Passive House Consultants: JMV Consulting; Transsolar  
Passive House Certifier: Herz & Lang GmbH  
Building Envelope Testing: Engineering Link  
Commissioning Consultant: CFMS Consulting Inc.  
Elevators: Soberman Engineering  
Building Code Consultant: LMDG Security/Telecoms Zerobit  
Construction Consultant: SCR Consulting  
Construction Manager: PCL Construction

Related Stories

High-rise Construction | Mar 22, 2017

Porsche Design Tower is, unsurprisingly, a car lover’s dream

The idea behind the residential tower was to provide residents with a full single family home in the sky, complete with a private garage and pool.

High-rise Construction | Mar 20, 2017

The world’s longest skyscraper

As supertall skyscrapers continue to pop up around NYC, an architecture firm based in New York and Athens asks, ‘What if we substituted height with length?’

High-rise Construction | Mar 3, 2017

Detroit's tallest tower to rise at site of former J.L Hudson's Department Store

SHoP Architects and Hamilton Anderson Associates will design the 52-story building.

Mixed-Use | Mar 1, 2017

New hotel and residential tower coming to San Francisco’s Transbay neighborhood

The ground-up development will feature 255 hotel rooms and 69 residential units.

Mixed-Use | Feb 27, 2017

Tallest tower in Miami to begin construction in January 2019

The tower will reach a height of 1,049 feet, the maximum height permitted by the FAA in Miami.

High-rise Construction | Feb 17, 2017

What makes a supertall tower super?

As new technologies fuel the race to build higher, three primal drivers simultaneously enable progress and keep it in check.

High-rise Construction | Feb 17, 2017

Zaha Hadid Architects-designed building to have the world’s tallest atrium

A 190-meter atrium will rise the full height of the building between two twisting sections.

High-rise Construction | Feb 8, 2017

Shanghai Tower nabs three world records for its elevators

The second tallest building in the world is officially home to the world’s fastest elevator, the tallest elevator in a building, and the fastest double-deck elevator.

Office Buildings | Feb 8, 2017

London office building employs transitional forms to mediate between the varied heights of surrounding buildings

Friars Bridge Court will provide a transition between the unvarying height of the buildings to the south and the more varied heights of the northern buildings.

High-rise Construction | Feb 6, 2017

Flexing their vanity muscles: Some of the world’s tallest buildings have hundreds of feet of non-occupiable space

The amount of the Burj Khalifa’s height that is non-occupiable is taller than most skyscrapers.

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021