It only took 26 days to complete construction on the Crowne Plaza Changi Airport hotel extension

Hotel Facilities

It only took 26 days to complete construction on the Crowne Plaza Changi Airport hotel extension

PPVC techniques allowed the project to save time and manpower.


By David Malone, Associate Editor | July 5, 2017

Photo: Patrick Bingham-Hall

The Singapore Changi Airport is, according to the most recent numbers from the Airports Council International, the 17th busiest airport in the world by passenger traffic. With so many people passing through on a daily basis, it was important for the new addition to the Crowne Plaza Changi Airport hotel to be built in as little time as possible.

The new building was Singapore’s first private sector commercial project to use pre-fabricated, pre-finished volumetric construction (PPVC), which led to the addition being built in just 26 days. WOHA designed the original 320-room hotel as well as the 243-room, 103,495-sf addition.

 

Photo: Patrick Bingham-Hall.

 

The use of the PPVC method slashed manpower requirements on site by as much as 45%, reduced overall construction time by 17%, and accomplished both of these with about 40% in manpower savings.

 

Photo: Patrick Bingham-Hall.

 

“The Crowne Plaza Changi Airport hotel extension (CPEX) demonstrates that it is possible to significantly reduce the number of workers required, shorten construction time, improve building quality and even overcome site constraints by changing the way we build,” says Singapore’s Building and Construction Authority CEO John Keung in a release.

 

Photo: Patrick Bingham-Hall.

Related Stories

Hotel Facilities | Feb 12, 2018

Circular hotel will be world’s first energy positive hotel concept above the Arctic Circle

The hotel will provide 360-degree views of the Svartisen glacier and the surrounding arctic nature.

Hotel Facilities | Feb 8, 2018

Nashville hotel takes authenticity to the extreme with dedicated recording studio, performance spaces

Music City has experienced a hotel construction boom in recent years, making for a more competitive market.

Hotel Facilities | Jan 24, 2018

U.S. hotel markets with the largest construction pipelines

Dallas, Houston, and New York lead the way, with more than 460 hotel projects in the works.

Hotel Facilities | Nov 10, 2017

The hotel of the future has just the right amount of tech

CallisonRTKL’s recent survey helps shed some light on how the hotel of the future might strike a balance between tech and the human touch.

Hotel Facilities | Oct 6, 2017

This year’s Radical Innovation Award winners showcase portable and flexible hotel designs

The grand prize hotel concept gives new meaning to “back to nature.” 

Adaptive Reuse | Oct 5, 2017

Wexford’s latest innovation center breaks ground in Providence

The campus is expected to include an Aloft hotel. 

Giants 400 | Sep 22, 2017

Welcome home: Hotels want guests to feel more like residents than visitors

Because hotels can take as long as six years to complete, spotting trends—and differentiating them from fads—is tough when tastes and systems change so rapidly.

Giants 400 | Sep 22, 2017

Top 80 hotel construction firms

Turner Construction Co., Swinerton, and The Whiting-Turner Contracting Co. top BD+C’s ranking of the nation’s largest hotel sector contractor and construction management firms, as reported in the 2017 Giants 300 Report.

Giants 400 | Sep 22, 2017

Top 30 hotel engineering firms

NV5 Global, WSP, and DeSimone Consulting Engineers top BD+C’s ranking of the nation’s largest hotel sector engineering and EA firms, as reported in the 2017 Giants 300 Report.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021