Gray lady no more: A facelift erases a landmark’s wrinkles, but not her heritage

Reconstruction Awards

Gray lady no more: A facelift erases a landmark’s wrinkles, but not her heritage

The Building Team restored the granite and terra cotta façade and reclaimed more than 500 double-hung windows.


By John Caulfield, Senior Editor | November 17, 2017
The Grand Staircase of The Gray

The Grand Staircase of The Gray, a new Kimpton hotel. The original building was designed by William Le Baron Jenney, known as the father of the skyscraper. Photo: Laure Joliet

By 2006, the New York Life Insurance Building, designed in 1893 by the father of the skyscraper, William Le Baron Jenney, had receded into obsolescence. Its owner, Hamilton Partners, was planning to demolish the 14-story landmark in Chicago’s Loop to make way for a 51-story hotel/office tower next door.

The building, once the Midwest headquarters of New York Life Insurance Company, found a savior in Kimpton Hotels & Restaurants. Kimpton, part of the Intercontinental Hotels Group, bought it from Hamilton in 2013, and worked for the next three years with its project team to execute a robust reconstruction program that preserved the integrity of Jenney’s design while creating a new use for the structure.

The Building Team restored the granite and terra cotta façade and reclaimed more than 500 double-hung windows. It moved the building’s main entrance to West Monroe Street, with a new bronze-clad canopy. The original entrance, on LaSalle Street, now serves as the portal to the Georgia Gray marble double staircase leading to Volume 39, the hotel’s lobby lounge and bar.

The hotel, now called The Gray, has 293 rooms and suites, a fitness center, 12,000 sf of meeting space, and a top-floor ballroom. One of the more stunning additions is Boleo, a South American-style bar that incorporates a 1,200-sf operable skylight.

Due to the lack of drawing documentation, the team had to engage in discovery and investigation over the course of the entire project. The building’s archaic floor framing made it difficult to create new openings for infrastructure and reconfigurations.

The building had no loading dock or space for an exterior hoist, so deliveries had to be made during off hours. An interior hoist had to be installed to move materials. Hazardous materials had to be remediated before interior demolition could begin.

As the awards jury noted, the Building Team overcame all these difficulties and, in keeping with Kimpton’s EarthCare program, executed sustainable and energy-efficient strategies throughout.

 

Project Summary

 

Gold Award Winner

Building Team: Gensler (submitting firm, architect, AOR) KHP Capital Partners (owner/developer) Stillwater Consulting (owner’s rep) Kimpton Hotels & Restaurants (operator) Beleco Design (hotel interiors) Parts and Labor Design (restaurant/lounge interior design) Forefront Structural Engineers (SE) AMS Mechanical Systems (mechanical/plumbing engineer) JMS Electric (EE) James McHugh Construction (GC).

Details: 239,000 sf. Construction cost: ConfidentIal. Construction time: October 2014 to August 2016. Delivery method: Design-bid-build.

 

See all of the 2017 Reconstruction Award winners here

Related Stories

Reconstruction Awards | Jan 6, 2021

University of Pennsylvania’s Stemmler Hall forgoes retrofit in favor of complete renovation

The Edward J. Stemmler Hall project has won a Bronze Award in BD+C’s 2020 Reconstruction Awards.

Reconstruction Awards | Dec 29, 2020

The reenvisioned Sazerac House: A delectable cocktail that's just perfect for the Big Easy

The 51,987-sf Sazerac House is an interactive cocktail museum, active distillery, corporate headquarters, and event venue, all under one roof, next to the historic French Quarter of New Orleans.

Reconstruction Awards | Dec 18, 2020

Can converting a landmark office to a clinic raise up a downtrodden Philadelphia neighborhood?

BD+C’s Reconstruction Awards recognize the adaptive reuse of the Kensington Trust building.

Reconstruction Awards | Dec 18, 2020

Spokane Riverfront Park U.S. Pavilion project creates a refreshed gathering place in Spokane

The project has won a Bronze Award in BD+C's 2020 Reconstruction Awards.

Reconstruction Awards | Dec 16, 2020

Voters resuscitate an abandoned high school in northern California

A 2014 bond issue provided financing to seismically stabilize and modernize Historic Alameda High School, a 2020 Silver Reconstruction Award winner.

Reconstruction Awards | Dec 14, 2020

Wyoming Capitol Square renovation project is all about the details

The Wyoming Capitol Square project has won a Gold Award in BD+C's 2020 Reconstruction Awards.

Reconstruction Awards | Dec 12, 2020

A famed dome of a historic glasshouse is revived to its rightful glory

Scaffolding played a critical role in the repair and restoration of the Enid A. Haupt Conservatory’s Palm Dome at the New York Botanical Gardens, a Gold winner of BD&C’s 2020 Reconstruction Awards

Reconstruction Awards | Dec 8, 2020

A synagogue in Toronto is renewed while preserving its history

Holy Blossom Temple is a Platinum winner in BD+C’s 2020 Reconstruction Awards.

boombox1 - default
boombox2 -
native1 -

More In Category


Giants 400

BD+C Awards Programs

Entry information and past winners for Building Design+Construction's two major awards programs: 40 Under 40 and Giants 400



halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021