COVID-19 alert: Missouri’s first Alternate Care Facility ready for coronavirus patients

Coronavirus

COVID-19 alert: Missouri’s first Alternate Care Facility ready for coronavirus patients

Tarlton Corp. completes hotel convertion in less than 100 hours to support hospitals in case more beds are needed.


By TARLTON CORP. | April 14, 2020
USACE general Mark Toy briefed by Tarlton Corp. officials

U.S. Army Corps of Engineers Maj. Gen. R. Mark Toy is briefed by Tarlton construction executives on the site of the alternate care facility. From left: Senior Project Manager Cameron Denison, who managed the night team; Vice President Joe Scarfino, who led the effort and managed the day team; and EVP John Doerr. 

ST. LOUIS (April 14, 2020) – The design-build team of Tarlton Corp., a St. Louis-based general contracting and construction management firm, working for the U.S. Army Corps of Engineers, completed conversion April 11 of a Florissant, Mo., hotel into an alternate healthcare facility to treat non-acute COVID-19 patients. The facility, if needed, would serve as backup for patients referred by St. Louis-area hospitals and would be staffed by members of the Missouri National Guard.

The project yielded more than 100 patient rooms on the four floors of the 130-room hotel. The team built a nurses’ station on each floor and turned the existing phone system into a nurse call system. Beds and furniture were moved. Extra furniture was put into temporary storage. PTAC units in rooms were inspected and repaired or replaced as necessary. Hardware was changed on hotel room doors and bathroom doors to disable locks. All rooms were deep cleaned. In 13 rooms, carpet was removed and walls and ceilings were painted.

Project scope also included steps to ensure proper ventilation for a patient care facility: inspection and cleaning of HVAC units; relocation of exhaust fans within 25 feet of HVAC intakes; extension of plumbing vents within 25 feet of HVAC intakes; and construction of isolation barriers in the corridors (three per floor) to separate the elevator/nurse station areas from the three patient wings.

 

100+ WORKERS ON THE DESIGN-BUILD TEAM

More than 100 employees from the design-build team, including 50 from Tarlton, worked on site at the Quality Inn from April 8 to 11 to help USACE complete its mission in less than 100 hours. The team consisted of Tarlton (design-build contractor), Ross & Baruzzini (architectural/engineering services), Rock Hill Mechanical Corp., and Guarantee Electrical Co. 

Subcontractors working on the conversion included C&R Mechanical’s Plumbing Division, Collins & Hermann, Dynamic Air Solutions, Flooring Systems Inc., Jos. Ward Painting Co., Midwest Elevator, Stanley Steemer, Tech Electronics, Waterhout Construction, and Woodard Cleaning and Restoration.

 

Workers inspect rooftop units in support of ensuring healthy air circulation in the facility

Workers inspect rooftop units in support of ensuring healthy air circulation in the alternate care facility. 

 

Government, health, and hospital officials toured the facility at 55 Dunn Road over the weekend and Monday morning. USACE Maj. Gen. R. Mark Toy recognized all the participants for their work. State agencies involved included the Missouri National Guard, Department of Public Safety, State Emergency Management Agency, Department of Health and Senior Services, Office of Administration and the Missouri Hospital Association, in partnership with FEMA and the U.S. Department of Health and Human Services.

“I’m proud of the quick and thorough response our team put together and executed,” said Tracy Hart, President of Tarlton. “We feel honored to be trusted by the Army Corps of Engineers for this critical project that is so important to our community.”

Becky Mehaffy, Tarlton workforce manager, said, “Our group jumped right in there with the single goal to get it done safely and on time. I’ve seen a lot in my years in this industry—never anything like this.”

“Our design-build partners, subcontractors, and consultants were critical to the project’s success,” said Tarlton COO Dirk Elsperman. “Everyone brought ideas and the will to succeed—a strong commitment to the 12:01 a.m. Sunday turnover."

"It was an extraordinary integrated design-build effort,” said Michael Shea, AIA, Ross & Baruzzini SVP/Director of Government. Guarantee Electrical President Dave Gralike added: “We are especially proud of our team and all the contractors and tradespeople involved in this quick turnaround project.”

 

Individual room at ACF in Florissant, Mo.

Individual patient room at ACF in Florissant, Mo.

Related Stories

Coronavirus | Mar 19, 2020

Positive vibes: Let's take a look at the brighter side of these crazy times

Perhaps now is a good time to take a page from Monty Python's book and look on the bright side of life. So let's push aside the doom and gloom for a bit and bring a little positivity to these strange times we all currently find ourselves in.

Coronavirus | Mar 19, 2020

Force Majeure and COVID-19 in construction contracts - What you need to know

With the onset of the COVID-19 pandemic, we are all taking a closer look at many portions of our contracts.

Coronavirus | Mar 19, 2020

Technology crucial during COVID-19 social distancing

Technology can help bridge the gap during the Coronavirus pandemic as higher education institutes and corporations are moving to a remote work model.

Coronavirus | Mar 18, 2020

Coronavirus latest: Short-term pain but strong rebound likely, says Oxford Economics

Once the disruption and uncertainty fade, the rebound in global economic activity will be strong. It’s important for firms to position themselves for such a recovery.

Coronavirus | Mar 18, 2020

We are in the midst of a paradigm shift for higher education

The question for higher education is, what will the university of the future look like?

Coronavirus | Mar 17, 2020

AIA: Design services saw increase in February, but economic footings are rapidly shifting

"The rapid pull-back in activity throughout the economy will obviously be felt in the design and construction sector, and architecture firms will be one of the first to see how these events play out,” said AIA Chief Economist, Kermit Baker, Hon. AIA, PhD.

Coronavirus | Mar 17, 2020

AGC to government officials: Shutting down construction projects is an unnecessary step

Construction firms are already taking steps to protect employees, most of whom already wear protective equipment, while halting work will undermine efforts to add hospital capacity.

Coronavirus | Mar 16, 2020

Boston mayor orders shut down of construction sites due to coronavirus

Boston Mayor Martin Walsh has ordered that all construction projects in the city be suspended in response to the spread of the coronavirus.

Coronavirus | Mar 16, 2020

Effective remote workforce: Key steps and strategies for success

As the potential scope of the COVID-19 outbreak has become more clear in the United States and Canada, public and private organizations from all industries, sectors and geographies are encouraging their teams to work remotely to reduce the spread of the virus.

Coronavirus | Mar 16, 2020

Coronavirus and the water cycle—here is what treatment professionals need to know

As the global health community tracks the spread of this virus, it’s important for water and wastewater professionals to keep updated on potential impacts.

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021