COVID-19 alert: Missouri’s first Alternate Care Facility ready for coronavirus patients

Coronavirus

COVID-19 alert: Missouri’s first Alternate Care Facility ready for coronavirus patients

Tarlton Corp. completes hotel convertion in less than 100 hours to support hospitals in case more beds are needed.


By TARLTON CORP. | April 14, 2020
USACE general Mark Toy briefed by Tarlton Corp. officials

U.S. Army Corps of Engineers Maj. Gen. R. Mark Toy is briefed by Tarlton construction executives on the site of the alternate care facility. From left: Senior Project Manager Cameron Denison, who managed the night team; Vice President Joe Scarfino, who led the effort and managed the day team; and EVP John Doerr. 

ST. LOUIS (April 14, 2020) – The design-build team of Tarlton Corp., a St. Louis-based general contracting and construction management firm, working for the U.S. Army Corps of Engineers, completed conversion April 11 of a Florissant, Mo., hotel into an alternate healthcare facility to treat non-acute COVID-19 patients. The facility, if needed, would serve as backup for patients referred by St. Louis-area hospitals and would be staffed by members of the Missouri National Guard.

The project yielded more than 100 patient rooms on the four floors of the 130-room hotel. The team built a nurses’ station on each floor and turned the existing phone system into a nurse call system. Beds and furniture were moved. Extra furniture was put into temporary storage. PTAC units in rooms were inspected and repaired or replaced as necessary. Hardware was changed on hotel room doors and bathroom doors to disable locks. All rooms were deep cleaned. In 13 rooms, carpet was removed and walls and ceilings were painted.

Project scope also included steps to ensure proper ventilation for a patient care facility: inspection and cleaning of HVAC units; relocation of exhaust fans within 25 feet of HVAC intakes; extension of plumbing vents within 25 feet of HVAC intakes; and construction of isolation barriers in the corridors (three per floor) to separate the elevator/nurse station areas from the three patient wings.

 

100+ WORKERS ON THE DESIGN-BUILD TEAM

More than 100 employees from the design-build team, including 50 from Tarlton, worked on site at the Quality Inn from April 8 to 11 to help USACE complete its mission in less than 100 hours. The team consisted of Tarlton (design-build contractor), Ross & Baruzzini (architectural/engineering services), Rock Hill Mechanical Corp., and Guarantee Electrical Co. 

Subcontractors working on the conversion included C&R Mechanical’s Plumbing Division, Collins & Hermann, Dynamic Air Solutions, Flooring Systems Inc., Jos. Ward Painting Co., Midwest Elevator, Stanley Steemer, Tech Electronics, Waterhout Construction, and Woodard Cleaning and Restoration.

 

Workers inspect rooftop units in support of ensuring healthy air circulation in the facility

Workers inspect rooftop units in support of ensuring healthy air circulation in the alternate care facility. 

 

Government, health, and hospital officials toured the facility at 55 Dunn Road over the weekend and Monday morning. USACE Maj. Gen. R. Mark Toy recognized all the participants for their work. State agencies involved included the Missouri National Guard, Department of Public Safety, State Emergency Management Agency, Department of Health and Senior Services, Office of Administration and the Missouri Hospital Association, in partnership with FEMA and the U.S. Department of Health and Human Services.

“I’m proud of the quick and thorough response our team put together and executed,” said Tracy Hart, President of Tarlton. “We feel honored to be trusted by the Army Corps of Engineers for this critical project that is so important to our community.”

Becky Mehaffy, Tarlton workforce manager, said, “Our group jumped right in there with the single goal to get it done safely and on time. I’ve seen a lot in my years in this industry—never anything like this.”

“Our design-build partners, subcontractors, and consultants were critical to the project’s success,” said Tarlton COO Dirk Elsperman. “Everyone brought ideas and the will to succeed—a strong commitment to the 12:01 a.m. Sunday turnover."

"It was an extraordinary integrated design-build effort,” said Michael Shea, AIA, Ross & Baruzzini SVP/Director of Government. Guarantee Electrical President Dave Gralike added: “We are especially proud of our team and all the contractors and tradespeople involved in this quick turnaround project.”

 

Individual room at ACF in Florissant, Mo.

Individual patient room at ACF in Florissant, Mo.

Related Stories

Coronavirus | Apr 15, 2020

COVID-19 alert: 93% of renters in professionally managed multifamily housing paid some or all of their rent, says NMHC

In its second survey of 11.5 million units of professionally managed apartment units across the country, the National Multifamily Housing Council (NMHC) found that 84% of apartment households made a full or partial rent payment by April 12, up 15 percentage points from April 5.

Coronavirus | Apr 15, 2020

DCAMM teams with SLAM and Gilbane Building Company to re-occupy Newton Pavilion for temporary quarantine of homeless during COVID-19 pandemic

First and only quarantine shelter in Boston-area to convert a shuttered hospital for homeless patient occupancy.

Coronavirus | Apr 15, 2020

3D printing finds its groove fabricating face shields during COVID-19 crisis

The architecture firm Krueck + Sexton is producing 100 shields for a Chicago-area hospital.

Coronavirus | Apr 13, 2020

COVID-19 alert: City conducts a 'virtual building inspection' to allow Starbucks and bank to open

Bothell, Wash., issues a certificate of occupancy to developer after inspecting the property online. 

Coronavirus | Apr 13, 2020

Construction layoffs spread rapidly as coronavirus shuts down projects, in contrast to job gains through February in most metros

Association officials urge quick enactment of infrastructure investment, relief for hard-hit firms and pensions in order to save jobs in construction and supplier industries.

Coronavirus | Apr 12, 2020

How prefab can enable the design and construction industry to bring much needed beds to hospitals, faster

The outbreak of COVID-19 represents an unprecedented test for the global healthcare system. Managing the pandemic—and saving lives—depends largely on the availability of medical supplies, including the capacity of hospitals. But the United States lags behind other nations, with only 2.8 beds per thousand people compared to 4.3 in China and 12.8 in South Korea.

Coronavirus | Apr 10, 2020

HGA and The Boldt Company devise a prefabricated temporary hospital to manage surge capacity during a viral crisis

A STAAT Mod system can be ready to receive patients in less than a month.

Coronavirus | Apr 10, 2020

COVID-19: Converting existing hospitals, hotels, convention centers, and other alternate care sites for coronavirus patients

COVID-19: Converting existing unused or underused hospitals, hotels, convention centers, and other alternate care sites for coronavirus patients 

Coronavirus | Apr 9, 2020

COVID-19 Design Innovation Grant: IDA offers $14,000 to spur design innovation for combating the coronavirus pandemic

The International Design Awards is looking for innovations in low-cost ventilators, in-home isolation pods, and reusable masks.

Coronavirus | Apr 9, 2020

COVID-19 alert: Robins & Morton to convert Miami Beach Convention Center into a 450-bed field hospital

COVID-19 alert: Robins & Morton to convert Miami Beach Convention Center into a 450-bed field hospital

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021