BIM on Target

BIM on Target

By using BIM for the design of its new San Clemente, Calif., store, big-box retailer Target has been able to model the entire structural steel package, including joists, in 3D, chopping the timeline for shop drawings from as much as 10 weeks down to an ‘unheard of’ three-and-a-half weeks.


By By Jeff Yoders, Contributing Editor | January 7, 2011
This article first appeared in the January 2011 issue of BD+C.

Minneapolis-based Target Corp. has always put the design of its stores high up on its list of corporate priorities. Target was one of the original participants in the U.S Green Building Council’s Pilot Portfolio certification program, which allows prototype designs of multiple similar buildings to be LEED-certified as variations of a single prototype. Five Target stores have been LEED-certified to date.

Over the last year Target fully transitioned its new store design from 2D (using Bentley Microstation) to 3D (utilizing the Autodesk Revit BIM platform). Early in 2010, as Target began planning a new 142,206-sf store for San Clemente, Calif., the retailer decided to take prototype design to an even higher level, using both 3D BIM and integrated project delivery.

“Right now we maintain a general merchandise P [for “prototype”] store,” said Brad Koland, group manager of structural engineering at Target. However, this month the company will be releasing its Revit prototype. “Right now it doesn’t really get to a deeper level of integration,” said Koland. “We’re trying to find out the viability of how deeply embedded we can take this 3D information into our prototype.”

One goal of the San Clemente investigation was to figure out how better to utilize the space around the structural steel joists in its stores, space that typically houses some HVAC and electrical lines. There is a sense among Target’s architects and engineers that this space could be used more effectively if they were to know early enough in the design process exactly where the joist web framing lays out, so that they could plan how pipes, ducts, and electrical lines would go around them. Koland said Target’s Building Teams need to know how all the elements of the steel joists and the joist girders come into play early in the design phase to effectively utilize that space.

“With BIM analysis tools we knew we could reduce conflicts and increase utilization of the space within our box,” said Koland. “We wanted to move beyond that. We wanted to use BIM as a way to figure out what was in there, and then establish that and build in protocols for how we could start to utilize that space to reduce the height of our buildings, or maximize the amount of space we have, or minimize the amount of structure we have to put up.”

To do that, the integrated team on the San Clemente store—including IPD engineer and steel detailer Meyer Borgman Johnson (MBJ), general contractor Whiting-Turner, and the in-house architects and engineers at Target—met at strategic times near the end of the design phase of the Orange County store. Whiting-Turner created a comprehensive virtual design and construction (VDC) execution plan that was sent out as part of the bidding package for all subcontractors. It defined what Whiting-Turner would be providing, what was expected of each subcontractor, and why and how the 3D model would be used. Because the joist design was such an important part of the overall process, bidding was opened in September for the steel joist fabrication package. The pre-qualification process included a requirement to work as an integrated team using a parametric 3D model.

The steel joist fabrication package went to New Millennium Building Systems, largely because of its BIM capabilities. MBJ created a construction BIM model using Target’s Revit model as a starting point, converting to Tekla Structures using the IFC file format. After quality control checking, this model was delivered to New Millennium in lieu of 2D drawings. The structural joist fabricator was able to use the generic joist elements, rather than having to redraw them, to begin the process for exact steel joist design and modeling.

Using New Millennium’s Dynamic Joist design component, a plug-in for Tekla Structures that helps automate this integrated process, the Fort Wayne, Ind., fabricator was able to quickly design the steel joists, insert “real” fabrication-ready joists and bridge in the shared Tekla model, and produce 2D shop drawings. The geometry and profiles of the joists were determined by New Millennium’s design, detailing, and fabrication standards.

“The parametric Dynamic Joist plug-in will model a joist from user-specified points,” said Ricky Gillenwater, IT director at New Millennium and developer of the plug-in. “What users have initially is a generic representation of a joist, consisting of generic material and geometry. The component transforms into an as-built representation as it goes through the joist detailing and design process, which is what we gave MBJ.”

The time period from the award of the steel joist package to the approval of shop drawings sent back to New Millennium for fabrication from the integrated design team, including calculations and integrated 3D geometry, was three-and-half weeks.

“That’s unheard of to have an approved set of calculations and shop drawings back in the joist manufacturer’s hands ready for fabrication,” said Jerod Hoffman, principal and structural engineer at MBJ. Referring to the structural steel package (including miscellaneous metals), Hoffman said this is the first Target store ever bid to steel fabricators off of completed shop drawings.

“Instead of providing just 2D construction documents, we gave Whiting-Turner the model, the bill of materials that listed every nut and bolt, and approved shop drawings, which the fabricator could use to supersede the 2D drawings and specifications,” Hoffman said. “The hope is that because we’re providing them exact quantities, the quality, competitiveness, and value of the bids they receive will be better than using 2D design drawings only.” Hoffman says he expects “zero change orders” with regard to coordination issues in the steel because “they’ve all been worked out.”

Through the integrated design process, MBJ also discovered early on that some of the load-bearing steel joists had to be fabricated and scoped in a way that changed the original plan for the steel embeds in the store’s concrete walls. As a result, the new embeds were correctly put out on the bid documents for the structural steel and concrete packages and will, therefore, be bid on as an already-coordinated first competitive cost.

Grading and site work on the project began in late December, and Whiting-Turner is already working with its subcontractors on 4D scheduling and cost estimation. The contractor plans to use Navisworks to coordinate the Tekla Structures steel model, as well as other models for the mechanical, electrical, and other subcontractors. Although Revit is not the model being used to create shop drawings and other deliverables for the subcontractors, Whiting-Turner will use the Revit design model in conjunction with fabrication models to perform clash detection and check quality control.

 “The type of sub we’re seeing bid on the project is more sophisticated,” said Reema Zuberi, project manager and regional VDC coordinator at Whiting-Turner. “They are able to work with 3D models and are comfortable working together earlier in the process.”

The store is expected to be ready for its grand opening in October. BD+C

Target: Expanding BIM Design Horizons

Target’s in-house property development operation includes more than 60 architects, 80 engineers, and 30 construction managers. The retailer, with 1,743 stores in every state except Vermont, has cut back its new openings due to the weak economy, but still expects to open 30 new stores in 2011, including the San Clemente, Calif., project. Store design is overseen by senior vice president Rich Varda, an architect whose work outside of Target includes the recently opened Musical Instrument Museum in Phoenix.

Utilizing BIM and prototype designs for efficient design and construction is a key part of Target’s expansion strategy. “Twenty-ten was a demarcation from a 2D design deliverable to a fully 3D design for all store designs,” said Brad Koland, group manager of structural engineering at Target. “We definitely saw that the first incremental benefit of using Revit came from clash detection. There was a cost savings associated with moving from a 2D platform to a 3D one.”

Target has, over the years, experimented with many different ways of procuring construction materials. Getting a better idea of how to use the area around steel joists was one area where, Koland said, Target wanted to build a foundation of knowledge for what is possible.

“We have a really robust owner-provided construction material and equipment program,” he said. “We source some general construction materials but not too many. So, this isn’t necessarily a strong drive toward materials sourcing, but we wanted to see what technology would allow us to do. Sourcing is one of the possible outcomes, but really getting better clarity around what’s inside our building is the primary driver for this investigation.”

Related Stories

Office Buildings | Apr 2, 2024

SOM designs pleated façade for Star River Headquarters for optimal daylighting and views

In Guangzhou, China, Skidmore, Owings & Merrill (SOM) has designed the recently completed Star River Headquarters to minimize embodied carbon, reduce energy consumption, and create a healthy work environment. The 48-story tower is located in the business district on Guangzhou’s Pazhou Island.

K-12 Schools | Apr 1, 2024

High school includes YMCA to share facilities and connect with the broader community

In Omaha, Neb., a public high school and a YMCA come together in one facility, connecting the school with the broader community. The 285,000-sf Westview High School, programmed and designed by the team of Perkins&Will and architect of record BCDM Architects, has its own athletic facilities but shares a pool, weight room, and more with the 30,000-sf YMCA.

Market Data | Apr 1, 2024

Nonresidential construction spending dips 1.0% in February, reaches $1.179 trillion

National nonresidential construction spending declined 1.0% in February, according to an Associated Builders and Contractors analysis of data published today by the U.S. Census Bureau. On a seasonally adjusted annualized basis, nonresidential spending totaled $1.179 trillion.

Affordable Housing | Apr 1, 2024

Biden Administration considers ways to influence local housing regulations

The Biden Administration is considering how to spur more affordable housing construction with strategies to influence reform of local housing regulations.

Affordable Housing | Apr 1, 2024

Chicago voters nix ‘mansion tax’ to fund efforts to reduce homelessness

Chicago voters in March rejected a proposed “mansion tax” that would have funded efforts to reduce homelessness in the city.

Standards | Apr 1, 2024

New technical bulletin covers window opening control devices

A new technical bulletin clarifies the definition of a window opening control device (WOCD) to promote greater understanding of the role of WOCDs and provide an understanding of a WOCD’s function.

Adaptive Reuse | Mar 30, 2024

Hotel vs. office: Different challenges in commercial to residential conversions

In the midst of a national housing shortage, developers are examining the viability of commercial to residential conversions as a solution to both problems.

Sustainability | Mar 29, 2024

Demystifying carbon offsets vs direct reductions

Chris Forney, Principal, Brightworks Sustainability, and Rob Atkinson, Senior Project Manager, IA Interior Architects, share the misconceptions about carbon offsets and identify opportunities for realizing a carbon-neutral building portfolio.

Reconstruction & Renovation | Mar 28, 2024

Longwood Gardens reimagines its horticulture experience with 17-acre conservatory

Longwood Gardens announced this week that Longwood Reimagined: A New Garden Experience, the most ambitious revitalization in a century of America’s greatest center for horticultural display, will open to the public on November 22, 2024.

Office Buildings | Mar 27, 2024

A new Singapore office campus inaugurates the Jurong Innovation District, a business park located in a tropical rainforest

Surbana Jurong, an urban, infrastructure and managed services consulting firm, recently opened its new headquarters in Singapore. Surbana Jurong Campus inaugurates the Jurong Innovation District, a business park set in a tropical rainforest.

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021