Sharp jump in owners cancelling or delaying construction projects across the country, new survey finds

Coronavirus

Sharp jump in owners cancelling or delaying construction projects across the country, new survey finds

After 42 states added jobs in February, coronavirus is taking a swift and severe toll on the industry, prompting association officials to call for additional measures to help workers and firms recover.


By AGC | March 27, 2020

Courtesy Pixabay

Thirty-nine percent of contractors report that project owners have halted or canceled current construction projects amid deteriorating economic conditions, according to a survey released today by the Associated General Contractors of America. Association officials warned that these cancellations mean massive job losses are likely soon unless Congress passes targeted recovery measures to boost infrastructure funding, compensate firms for lost or delayed federally funded work and provide needed pension relief. The project cancellations are particularly severe in light of new data showing that 42 states added construction jobs through February.

“The abrupt plunge in economic activity is taking a swift and severe toll on construction,” said Ken Simonson, the association’s chief economist, noting that only 18% of respondents have been ordered to halt work by elected officials. “The sudden drop in demand stands in sharp contrast to the strong employment levels this industry was experiencing just a few weeks ago.” Click here for additional video comments from Mr. Simonson.

In the association’s latest online survey, conducted between March 23 and 26, 45% of the 1,640 respondents reported experiencing project delays or disruptions. Shortages of material, parts and equipment, including vital personal protective equipment for workers such as respirators, were reported by 23% of respondents. Eighteen percent reported shortages of craftworkers, while 16% said projects were delayed by shortages of government workers needed for inspections, permits and other actions. Thirteen percent said delay or disruption had occurred because a potentially infected person had visited a jobsite.

The survey also found that 35% of firms said suppliers had notified them or their subcontractors that some deliveries would be delayed or canceled, the economist added. He noted that only 22% reported similar supply chain challenges last week. That survey was conducted between March 17-19. However, 8% of firms did report they have added new work expanding health care and other facilities needed to respond to the growing health crisis.

In contrast to the rapidly deteriorating current market conditions, the association also released new construction employment data showing that most states – 42 – added construction jobs between February 2019 and February 2020. Industry employment declined over the year in eight states and the District of Columbia. From January to February, 37 states and D.C. added construction jobs, while 11 states shed jobs and two states had no change.

Association officials warned that while the coronavirus relief measure scheduled for a vote in the House today will provide some immediate help for construction workers and their employers, Congress must do more to protect high-paying construction jobs. They said new investments in infrastructure, relief from losses incurred on delayed or canceled federally funded projects and protections for multi-employer pensions will help the industry recover from the economic impacts of the pandemic.

“The steps firms are taking to protect workers from the coronavirus unfortunately won’t be enough to save many of them from the economic damage the pandemic is creating,” said Stephen E. Sandherr, the association’s chief executive officer. “Construction workers and employers need more than a lifeline, they need a recovery plan.”

View the state employment datarankings, and map. View AGC’s coronavirus resources and survey.

Related Stories

Coronavirus | Apr 9, 2020

COVID-19 alert: Robins & Morton to convert Miami Beach Convention Center into a 450-bed field hospital

COVID-19 alert: Robins & Morton to convert Miami Beach Convention Center into a 450-bed field hospital

Coronavirus | Apr 8, 2020

AIA task force launches tool for assessing COVID-19 alternative care sites

The tool is intended to assist non-healthcare design professionals with identifying alternative sites suitable for patient care.

Coronavirus | Apr 8, 2020

COVID-19 alert: Most U.S. roofing contractors hit by coronavirus, says NRCA

NRCA survey shows 52% of roofing contractor said COVID-19 pandemic was having a significant or very significant impact on their businesses.

Coronavirus | Apr 8, 2020

Navigate supply chain and manufacturing challenges during disruption

First, most important and most complex: Create an extensive safety plan for your facilities and job sites that protects both the personnel onsite and the end users of your product.

Coronavirus | Apr 7, 2020

How to turn a high school into a patient care center in 15 days

HKS’s concept paper presents three scenarios.

Coronavirus | Apr 7, 2020

New Trump administration guidance now allows firms with 500 of fewer employees to qualify for paycheck protection program loans

Associated General Contractors of America secures fix to loan qualifications after alerting administration officials to small business administration language that excluded many firms.

Coronavirus | Apr 6, 2020

New small business administration loan guidance appears to exclude many construction firms that employ fewer than 500 people

Construction officials urge agency to make clear that firms that employ 500 or fewer people to qualify for paycheck protection program loans, regardless of revenue.

Coronavirus | Apr 6, 2020

Pandemic preparedness: How hospitals can adapt buildings to address worst-case scenarios

A Canadian healthcare architect looks at how hospital staff can act now to modify facilities and contain a pandemic.

Coronavirus | Apr 5, 2020

COVID-19: Most multifamily contractors experiencing delays in projects due to coronavirus pandemic

The NMHC Construction Survey is intended to gauge the magnitude of the disruption caused by the COVID-19 outbreak on multifamily construction.

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021