From power plant to office: Ambler Boiler House conversion

From power plant to office: Ambler Boiler House conversion

The shell of a 19th-century industrial plant is converted into three levels of modern office space. 


By Julie Higginbotham, Senior Editor | October 9, 2013
Located adjacent to a regional rail stop and near good roads, Ambler Boiler Hous
Located adjacent to a regional rail stop and near good roads, Ambler Boiler House spent years as an abandoned, dilapidated industrial building. It now offers 48,000 sf of office space in a LEED Platinum facility. Photo: Don Pearse

Like many 19th-century industrial facilities, the Ambler Boiler House long ago outlived its initial use. Built in 1897 to generate power for an asbestos plant, the structure was abandoned when the owner folded after the Depression. In the early 2000s, Summit Realty Advisors bought the site, appreciating its proximity to a rail stop—Philadelphia is 40 minutes away by train—as well as good roads and utility services.

The 2008 crash delayed plans, but three years later, construction of an office complex began. Summit used creative financing, including state and county funds, to realize this speculative project in tough economic times.

Asbestos was remediated with the help of the Pennsylvania Department of Environmental Protection and state grants and loans. The endeavor required 760 man-hours of labor and the removal of 530 cubic yards of contaminated construction debris and waste. All that remained was a brick shell and steel roof trusses.

AMBLER BOILER HOUSE
Ambler, Pa.

 
Building Team 
Submitting firm: Heckendorn Shiles Architects 
Owner/developer: Summit Realty Advisors 
Owner’s representative: The AT Group 
Structural engineer: Elton & Thompson 
MEP engineer: PHY Engineers 
General contractor: Domus
 
General Information 
Size: 48,000 sf 
Construction cost: $16 million (core and shell) 
Construction time: 2011 to August 2013 
Delivery method: Design-bid-build

The former two-story plan entailed excessive floor-to-floor heights for offices, so the Building Team, led by Heckendorn Shiles Architects, inserted structural steel and concrete slabs to create three levels. Entryways and windows, many of which had been walled up, were reopened and infilled with high-efficiency store-front glazing. An iconic 140-foot smokestack was retained, and the original monitor roof profile, now equipped with translucent composite clerestories, enhances daylighting. Loft-style office spaces are characterized by references to the past, including exposed brick and reclaimed wood. However, the infrastructure is thoroughly modern. In particular, a 54-well geothermal system makes the building economical to operate, contributing to a LEED Platinum designation.

Since it opened in August 2012, the development has attracted a mix of tenants, including Summit Realty, Clutch (a mobile app designer), and AEC firm Core States Group. DiD, a boutique healthcare marketing agency, recently completed a two-story fit-out, with an open communicating stair and a “village green” common space. Ambler Boiler House—first an economic engine, then an eyesore—is most emphatically back in business.

Related Stories

| Apr 6, 2012

Rooftop solar energy program wins critical approval from L.A. city council

Los Angeles Business Council applauds decision allowing LADWP to create new national model for rooftop solar energy

| Apr 6, 2012

Batson-Cook breaks ground on hotel adjacent to Infantry Museum & Fort Benning

The four-story, 65,000-ft property will feature 102 hotel rooms, including 14 studio suites.

| Apr 6, 2012

Perkins Eastman unveils Qatar mixed-use sports complex

Home stadium for Lekhwiya Club a vibrant addition to Doha’s architectural identity.

| Apr 5, 2012

5 tips for a successful door and window retrofit

An exclusive tip sheet to help the Building Team manage door and window retrofits successfully.

| Apr 4, 2012

Educational facilities see long-term benefits of fiber cement cladding

Illumination panels made for a trouble-free, quick installation at a cost-effective price.

| Apr 4, 2012

HDS designs Mount Auburn Hospital’s new healthcare center in Waltham, Mass.

HDS Architecture provided design services for all the Mount Auburn Healthcare suites including coordination of HVAC and FP engineering.

| Apr 4, 2012

Bald joins the Harmon glazing team

Bald has 13 years of experience in the glazing industry, coming to Harmon from Trainor where he was the regional manager of the Mid-Atlantic region.

| Apr 4, 2012

JCJ Architecture designs New York City's first casino

Aqueduct Racetrack complex transformed into modern entertainment destination.

| Apr 4, 2012

San Antonio animal hospital earns LEED Platinum certification

Middleman Construction Company builds the city?s first commercial building to earn certification.

| Apr 4, 2012

Hason joins RNL’s as MENA regional director

Hason specializes in planning and urban design, hospitality, office, corporate headquarters and transportation structures, as well as, higher education and museum facilities.

boombox1 - default
boombox2 -
native1 -

More In Category


AEC Tech

Lack of organizational readiness is biggest hurdle to artificial intelligence adoption

Managers of companies in the industrial sector, including construction, have bought the hype of artificial intelligence (AI) as a transformative technology, but their organizations are not ready to realize its promise, according to research from IFS, a global cloud enterprise software company. An IFS survey of 1,700 senior decision-makers found that 84% of executives anticipate massive organizational benefits from AI. 


Codes and Standards

Updated document details methods of testing fenestration for exterior walls

The Fenestration and Glazing Industry Alliance (FGIA) updated a document serving a recommended practice for determining test methodology for laboratory and field testing of exterior wall systems. The document pertains to products covered by an AAMA standard such as curtain walls, storefronts, window walls, and sloped glazing. AAMA 501-24, Methods of Test for Exterior Walls was last updated in 2015. 


MFPRO+ News

World’s largest 3D printer could create entire neighborhoods

The University of Maine recently unveiled the world’s largest 3D printer said to be able to create entire neighborhoods. The machine is four times larger than a preceding model that was first tested in 2019. The older model was used to create a 600 sf single-family home made of recyclable wood fiber and bio-resin materials.

halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021