Mount Sinai Health System signs first healthcare IPD IFOA contract in New York City

Healthcare Facilities

Mount Sinai Health System signs first healthcare IPD IFOA contract in New York City

Francis Cauffman, Syska Hennessy, Turner Construction are the primary parties in agreement.


By Peter Fabris, Contributing Editor | January 15, 2016
Mount Sinai Health System signs first healthcare IPD IFOA contract in New York City

Photo: David Edwards/Creative Commons

Mount Sinai Health System (MSHS) became the first health system in New York City to execute an Integrated Form of Agreement (IFOA) for their capital program at Mount Sinai St. Luke’s Hospital.  

Other signatories to the IFOA include Francis Cauffman (architect), Syska Hennessy (engineer), and Turner Construction Company (contractor). Trade subcontractors that signed adjoining agreements as part of the Integrated Project Delivery (IPD) team are: EJ Electric, Fresh Meadows Mechanical, Heritage Mechanical, Cardoza Plumbing, Jacobsen Carpentry, Sirina Fire Protection, and Skyline Controls. 

The Integrated Project Delivery (IPD) process is new to the New York healthcare construction market, though it has been used for several years elsewhere. CBRE Healthcare, retained to provide IPD advisory services, collaborated with Mount Sinai on the delivery model development beginning in 2015. Though the details of the contract were just recently finalized, the IPD team, operating collaboratively, began work on various projects over a year ago.

“The team has proven the value of the IPD process and the results thus far are leading us to consider wider adoption of the delivery model for capital programs at our other facilities,” said Ken Holden, Chief Facilities Officer for Mount Sinai Health System. 

Related Stories

| Oct 13, 2010

Maryland replacement hospital expands care, changes name

The new $120 million Meritus Regional Medical Center in Hagerstown, Md., has 267 beds, 17 operating rooms with high-resolution video screens, a special care level II nursery, and an emergency room with 53 treatment rooms, two trauma rooms, and two cardiac rooms.

| Oct 13, 2010

Cancer hospital plans fifth treatment center

Construction is set to start in December on the new Cancer Treatment Centers of America’s $55 million hospital in Newnan, Ga. The 225,000-sf facility will have 25 universal inpatient beds, two linear accelerator vaults, an HDR/Brachy therapy vault, and a radiology and imaging unit.

| Oct 13, 2010

New health center to focus on education and awareness

Construction is getting pumped up at the new Anschutz Health and Wellness Center at the University of Colorado, Denver. The four-story, 94,000-sf building will focus on healthy lifestyles and disease prevention.

| Oct 13, 2010

Community center under way in NYC seeks LEED Platinum

A curving, 550-foot-long glass arcade dubbed the “Wall of Light” is the standout architectural and sustainable feature of the Battery Park City Community Center, a 60,000-sf complex located in a two-tower residential Lower Manhattan complex. Hanrahan Meyers Architects designed the glass arcade to act as a passive energy system, bringing natural light into all interior spaces.

| Oct 12, 2010

Holton Career and Resource Center, Durham, N.C.

27th Annual Reconstruction Awards—Special Recognition. Early in the current decade, violence within the community of Northeast Central Durham, N.C., escalated to the point where school safety officers at Holton Junior High School feared for their own safety. The school eventually closed and the property sat vacant for five years.

| Sep 13, 2010

Palos Community Hospital plans upgrades, expansion

A laboratory, pharmacy, critical care unit, perioperative services, and 192 new patient beds are part of Palos (Ill.) Community Hospital's 617,500-sf expansion and renovation.

| Sep 13, 2010

China's largest single-phase hospital planned for Shanghai

RTKL's Los Angles office is designing the Shanghai Changzheng New Pudong Hospital, which will be the largest new hospital built in China in a single phase.

| Sep 13, 2010

'A Model for the Entire Industry'

How a university and its Building Team forged a relationship with 'the toughest building authority in the country' to bring a replacement hospital in early and under budget.

| Sep 13, 2010

Data Centers Keeping Energy, Security in Check

Power consumption for data centers doubled from 2000 and 2006, and it is anticipated to double again by 2011, making these mission-critical facilities the nation's largest commercial user of electric power. With major technology companies investing heavily in new data centers, it's no wonder Building Teams see these mission-critical facilities as a golden opportunity, and why they are working hard to keep energy costs at data centers in check.

| Aug 11, 2010

Green Guide for Health Care launches pilot program, looks for participants

In first quarter 2010, the Green Guide for Health Care, in collaboration with Practice Greenhealth, is launching a one-year Green Guide for Health Care Operations Pilot Program for healthcare organizations engaged in any or all aspects of green operations initiatives, based on Green Guide v2.2 Operations section.

boombox1 - default
boombox2 -
native1 -

More In Category


Healthcare Facilities

Advancing Healthcare: Medical Office Buildings at the Forefront of Access and Safety

This article explores the pivotal shift from traditional hospital settings to Medical Office Buildings (MOBs), focusing on how these facilities enhance patient access. Discover the key drivers of this transformation, including technological advancements, demographic trends, and a growing emphasis on integrated, patient-centered care. Learn how MOBs are not only adapting to modern healthcare demands but are also leveraging modern access control and safety innovations.



halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021