MILITARY GIANTS: Cross-laminated timber construction gets a salute from the Army

MILITARY GIANTS: Cross-laminated timber construction gets a salute from the Army

By privatizing the construction, renovation, operation, maintenance, and ownership of its hotels the Army expects to cut a 20-year timetable for repairs and replacement of its lodging down to eight years.


By David Malone, Associate Editor | August 15, 2016

A construction crew installs one of 1,200 prefabricated cross-laminated timber (CLT) wall panels that make up the 92-room Candlewood Suites at Redstone Arsenal, Huntsville, Ala. Leadlease was the GC, developer, and owner on the project. It is the nation’s first all-CLT hotel project. Photo courtesy of Lendlease.

The United States Army has enough on its plate without having to worry about operating as a hotel manager, too.  

TOP 30 MILITARY ARCHITECTURE FIRMS
Rank, Firm, 2015 Revenue
1. HDR $24,971,124
2. Clark Nexsen $13,005,940
3. Guernsey $10,279,317
4. EwingCole $8,541,000
5. RS&H $8,100,000
6. Integrus Architecture $8,054,265
7. Leo A Daly $6,179,243
8. VOA Associates $4,600,000
9. Morris Architects $4,227,000
10. Emersion Design $4,095,748

SEE FULL LIST 

 

TOP 40 MILITARY CONSTRUCTION FIRMS
Rank, Firm, 2015 Revenue
1. Fluor Corp. $823,562,993
2. Walsh Group, The $382,116,917
3. Hensel Phelps $340,673,000
4. Gilbane Building Co. $303,821,000
5. Lendlease $269,240,000
6. Whiting-Turner Contracting Co., The $180,266,105
7. Balfour Beatty US $167,548,244
8. Turner Construction Co. $137,117,144
9. McCarthy Holdings $121,411,531
10. Haskell $81,252,088

SEE FULL LIST

 

TOP 40 MILITARY ENGINEERING FIRMS
Rank, Firm, 2015 Revenue
1. Jacobs $67,384,666
2. AECOM $50,000,000
3. Burns & McDonnell $41,464,789
4. Benham Design $15,481,228
5. Sherlock, Smith & Adams $14,439,000
6. Thornton Tomasetti $10,840,435
7. Jensen Hughes $8,068,991
8. Dewberry $5,353,171
9. RMF Engineering $5,028,000
10. Woolpert $4,083,332

SEE FULL LIST

On the heels of a U.S. Government Accountability Office report that showed that more than 80% of Army lodging needed repairs or replacement—at an estimated price tag of $1.8 billion over 20 years—the Army kicked its Privatization of Army Lodging (PAL) program into high gear.

By privatizing the construction, renovation, operation, maintenance, and ownership of its hotels (it is the only military branch to do so), the Army expects to cut that 20-year timetable down to eight years. 

Lendlease is a key partner in the PAL program, serving as the exclusive developer and owner of the hotels (the Army owns the land). InterContinental Hotels Group (IHG) is the PAL hotel operator under the Holiday Inn Express brand (for renovated Army hotels) and Candlewood Suites name (for newly constructed hotels).

The relationship between the Department of Defense, the Army, Lendlease, and IHG has produced lodging that has far exceeded anything created before PAL went into effect. For instance, the 310-room extended-stay hotel built on Joint Base San Antonio, completed in 2014, is the largest Candlewood Suites in the world.

The recently completed 92-room Candlewood Suites at Redstone Arsenal in Huntsville, Ala., is the first cross-laminated timber structure on a U.S. military installation and the first all-CLT hotel under any ownership type in the country.

Lendlease’s use of CLT, which is made of several layers of pressed lumber board stacked in alternating directions, is not a surprise. The company has committed $1 billion over the next five years to its Sydney, Australia-based startup, Design Make, which is dedicated to manufacturing prefabricated building components such as CLT.

Despite some early obstacles, such as meeting the highly restrictive military Anti-Terrorism and Force Protection requirements, the Building Team found that CLT construction was a great solution for the Redstone Arsenal project. Testing showed that the material performed well against the ATFP requirements due to its ability to carry load in varying directions.

“Labor scarcity, labor cost issues, schedule concerns, and foundation issues are all challenges that make CLT an attractive proposition,” says Lendlease’s Murray Woolcock, Executive General Manager, Strategic Business Units.

The Candlewood Suites on Redstone Arsenal totals 62,688 sf and can house 492 occupants. The structure used 1,200 CLT wall panels and 200,000 CLT fasteners. It is the first PAL structure to use prefabricated bathroom pods, which further helped to accelerate the construction schedule and reduce on-site waste.

By using prefabricated CLT, the Candlewood Suites was erected in just 10 working weeks by an 11-person crew, a 37% speed increase compared to conventional framing materials and methods for a similar-sized structure, according to Lendlease. 

The Redstone Arsenal hotel represents a small portion of the PAL program, which encompasses 12,492 guestrooms across 41 Army installations. Because CLT lends itself to structures with a repetitive room types, such as hotels, there is a good chance the Redstone Arsenal project will not be the only building on an Army base to utilize the material.

“Lendlease is currently evaluating numerous sites in our PAL portfolio to implement the use of CLT,” says Woolcock. “We are confident that CLT will gain traction in many areas, and Lendlease is well positioned to grow our platform off the back of the successful delivery of Redstone Arsenal.”

House approves $81B military Construction bill

With a vote of 277 to 147, the House on May 19 passed the Military Construction and Veterans Affairs bill, which, if enacted, would provide $81.6 billion in discretionary funding for the sectors in 2017. The total is $1.8 billion more than the 2016 budget, but $1.2 billion short of what President Obama requested.

Contained within the bill is funding to house, train, and equip military personnel, provide housing and services to military families, and maintain infrastructure. 

Nearly 10% of the total ($7.9 billion) would be used for large- and small-scale military construction projects at military bases in the U.S. and abroad. The allocation marks a $305 million decrease from fiscal year 2016, but is $250 million more than the President’s request. 

Other allocations of note: 

• $172 million for Overseas Contingency Operations and European Reassurance Initiative projects involving overseas bases

• $1.3 billion for the construction, operation, and maintenance of military family housing; while meeting the President’s budget request, it is $84 million off the budgeted amount in FY2015

• $304 million for the construction and alteration of military medical facilities

• $673 million for construction projects at National Guard and Reserve facilities across 21 states

• $900 million for VA construction projects

• $246 million for safety improvements and infrastructure work at DOD Education Activities facilities.

More on the bill at: http://bit.ly/28L8vwb.

 

RETURN TO THE GIANTS 300 LANDING PAGE

Related Stories

| Aug 11, 2010

Utah research facility reflects Native American architecture

A $130 million research facility is being built at University of Utah's Salt Lake City campus. The James L. Sorenson Molecular Biotechnology Building—a USTAR Innovation Center—is being designed by the Atlanta office of Lord Aeck & Sargent, in association with Salt-Lake City-based Architectural Nexus.

| Aug 11, 2010

San Bernardino health center doubles in size

Temecula, Calif.-based EDGE was awarded the contract for California State University San Bernardino's health center renovation and expansion. The two-phase, $4 million project was designed by RSK Associates, San Francisco, and includes an 11,000-sf, tilt-up concrete expansion—which doubles the size of the facility—and site and infrastructure work.

| Aug 11, 2010

Goettsch Partners wins design competition for Soochow Securities HQ in China

Chicago-based Goettsch Partners has been selected to design the Soochow Securities Headquarters, the new office and stock exchange building for Soochow Securities Co. Ltd. The 21-story, 441,300-sf project includes 344,400 sf of office space, an 86,100-sf stock exchange, classrooms, and underground parking.

| Aug 11, 2010

New hospital expands Idaho healthcare options

Ascension Group Architects, Arlington, Texas, is designing a $150 million replacement hospital for Portneuf Medical Center in Pocatello, Idaho. An existing facility will be renovated as part of the project. The new six-story, 320-000-sf complex will house 187 beds, along with an intensive care unit, a cardiovascular care unit, pediatrics, psychiatry, surgical suites, rehabilitation clinic, and ...

| Aug 11, 2010

Colonnade fixes setback problem in Brooklyn condo project

The New York firm Scarano Architects was brought in by the developers of Olive Park condominiums in the Williamsburg section of Brooklyn to bring the facility up to code after frame out was completed. The architects designed colonnades along the building's perimeter to create the 15-foot setback required by the New York City Planning Commission.

| Aug 11, 2010

Wisconsin becomes the first state to require BIM on public projects

As of July 1, the Wisconsin Division of State Facilities will require all state projects with a total budget of $5 million or more and all new construction with a budget of $2.5 million or more to have their designs begin with a Building Information Model. The new guidelines and standards require A/E services in a design-bid-build project delivery format to use BIM and 3D software from initial ...

| Aug 11, 2010

Opening night close for Kent State performing arts center

The curtain opens on the Tuscarawas Performing Arts Center at Kent State University in early 2010, giving the New Philadelphia, Ohio, school a 1,100-seat multipurpose theater. The team of Legat & Kingscott of Columbus, Ohio, and Schorr Architects of Dublin, Ohio, designed the 50,000-sf facility with a curving metal and glass façade to create a sense of movement and activity.

| Aug 11, 2010

Residence hall designed specifically for freshman

Hardin Construction Company's Austin, Texas, office is serving as GC for the $50 million freshman housing complex at the University of Houston. Designed by HADP Architecture, Austin, the seven-story, 300,000-sf facility will be located on the university's central campus and have 1,172 beds, residential advisor offices, a social lounge, a computer lab, multipurpose rooms, a fitness center, and a...

boombox1
boombox2
native1

More In Category

Multifamily Housing

AEC inspections are the key to financially viable office to residential adaptive reuse projects

About a year ago our industry was abuzz with an idea that seemed like a one-shot miracle cure for both the shockingly high rate of office vacancies and the worsening housing shortage. The seemingly simple idea of converting empty office buildings to multifamily residential seemed like an easy and elegant solution. However, in the intervening months we’ve seen only a handful of these conversions, despite near universal enthusiasm for the concept. 




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021