How bulletproof is your construction contract?

Contractors

How bulletproof is your construction contract?

Three Dykema Gossett attorneys discuss how supply-chain problems are complicating these agreements.


By John Caulfield, Senior Editor | October 28, 2022
Supply chain snags complicate construction contracts
A knotty supply chain heightens the importance of well-crafted construction contracts. Image: Pixabay

Global supply-chain delays and shortages have had an impact on construction contracts in terms of enforceability and risk, and have increased the likelihood of litigation to settle differences between parties, as well as the need to negotiate contracts that anticipate and minimize potential disputes.

“The allocation of risk is paramount to [achieving] the best possible outcome,” stated David Vanderhider, a Partner in the San Antonio office of Dykema Gossett, a Detroit-based national law firm with a substantial construction litigation practice.

During an October 26 webinar that explored the legal considerations of supply-chain impacts on contracts, Vanderhider was joined by two Partners from Dykema Gossett’s Chicago office: Steven Mroczkowski, who is Co-leader of the firm’s Construction Group; and Melanie Chico, Asset Practice Group Leader.

Chico predicted that supply-chain problems, including those related to costs and labor, are likely to spill into 2023. To which Vanderhider followed that earlier attention to planning will be needed to prepare for delays and cost overruns. Mroczkowksi added that collaboration is the key to allocating risk fairly, and he’s been seeing fewer take-it-or-leave-it clauses on contracts. But he also noted that “there’s no one-size-fits-all” solution.

Contractual risk and reward

The bulk of the webinar was taken up with the partners discussing different contract clauses. For example, Mroczkowski has seen an uptick in litigation over the applicability of force majeure, which is intended to excuse nonperformance following a particular event. (This is commonly known as the “Act of God” provision.) Such clauses are enforceable when the event is beyond the reasonable control of the party. And what is often being litigated, he said, is whether the affected party took sufficient steps to reduce its risk.

Mroczkowski cautioned that force majeure can vary by jurisdiction and how a project’s financing is structured, which is why he advises clients to customize the language of their contracts to the realities of the given project. “Sometimes, risk allocation boils down to an amendment in a contract,” observed Chico.

Another growing area of dispute, the partners said, is a contract’s Notice requirement, which spells out when a party is entitled to additional compensation or time. Chico said that too many notice clauses are loosely drawn up, and lack specificity when it comes to who, what, when, and why.

Indeed, the partners agreed that the precision of a particular clause’s language usually determines each party’s level of protection in a contract, especially at a time when outside forces that affect contractual agreements are in flux.

Litigate or arbitrate

Contracts are still being written too loosely
Construction contracts are still being written too loosely, leaving doors open for interpretation.
 

During the webinar, the partners touched on suspension and termination provisions, limitation of liability clauses, waivers for consequential damages (which owners are generally interested in), safety requirements, and insurance requirements. (Vanderhider said that insurance policies covering errors and omissions/professional liability “are trending,” and revolve around notice provisions.)

He said he’s been seeing contracts with more provisions that allow owners to withhold payments, with a notorious change in emphasis from “pay when paid” to “pay if paid,” which shifts more risk onto subcontractors. Chico added there are options “to be creative here,” such as payment clauses that kick in or are capped at certain thresholds, are limited to certain building materials, are tied to index pricing, or offer early payment for supply and storage actions.

The partners also took some time to debate how best to resolve disputes in general.

Vanderhider typically favors litigation, claiming that arbitration doesn’t always save time or money, and can place limits on the presentation of evidence and witnesses. “Many of the more common contract forms don’t reflect the reality of today’s economic climate,” he asserted. But Vanderhider also conceded that arbitration makes it easier for parties to keep evidence private

Chico, on the other hand, prefers arbitration, “mostly because it’s faster” than letting a lawsuit play out. She and Vanderhider agreed that dispute clauses in contracts are most effective when they are consistent throughout the construction chain. Mroczkowski recommended, too, that contracts include a provision mandating some level of arbitration so as not to halt the project while the parties try to resolve differences.

In conclusion, Mroczkowski cited four takeaways for contractual risk mitigation:

•Focus on your priorities

•Be proactive anticipating supply-chain impacts

•Ensure consistency in certain key contract terms

•Ensure compliance with local laws.

Related Stories

| Dec 5, 2011

SchenkelShultz Architecture designs Dr. Phillips Charities Headquarters building in Orlando

The building incorporates sustainable architectural features, environmentally friendly building products, energy-efficient systems, and environmentally-sensitive construction practices.

| Dec 2, 2011

What are you waiting for? BD+C's 2012 40 Under 40 nominations are due Friday, Jan. 20

Nominate a colleague, peer, or even yourself. Applications available here.

| Dec 2, 2011

Legrand joins White House initiative to spur energy efficiency in commercial buildings

Company agrees to aggressive energy savings and reporting.

| Dec 2, 2011

Goody Clancy awarded Ohio State residential project

The project, which is focused on developing a vibrant on-campus community of learning for OSU undergraduates.

| Dec 1, 2011

Nauset Construction breaks ground on Massachusetts health care center

The $20 million project is scheduled to be completed by December 2012. 

| Dec 1, 2011

Ground broken on first LEED Platinum designed school house built by volunteers

Phoenix public school receives the generous gift of a state-of-the-art building for student and community use.

| Dec 1, 2011

VLK Architects’ office receives LEED certification

The West 7th development, which houses the firm’s office, was designed to be LEED for Core & Shell, which gave VLK the head start on finishing out the area for LEED Silver Certification CI.

| Nov 29, 2011

First EPD awarded to exterior roof and wall products manufacturer

EPD is a standardized, internationally recognized tool for providing information on a product’s environmental impact. 

| Nov 29, 2011

Suffolk Construction breaks ground on Boston residential tower

Millennium Place III is a $220 million, 256-unit development that will occupy a full city block in Boston’s Downtown Crossing.

boombox1 - default
boombox2 -
native1 -

More In Category

Construction Costs

New download: BD+C's May 2024 Market Intelligence Report

Building Design+Construction's monthly Market Intelligence Report offers a snapshot of the health of the U.S. building construction industry, including the commercial, multifamily, institutional, and industrial building sectors. This report tracks the latest metrics related to construction spending, demand for design services, contractor backlogs, and material price trends.




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021