COVID-19: Construction completed on first phase of Chicago's McCormick Place into Alternate Care Facility

Coronavirus

COVID-19: Construction completed on first phase of Chicago's McCormick Place into Alternate Care Facility

Phase 1 construction on the first 500 beds was completed on Friday, April 3; 2,500 beds to follow.


By Walsh Construction | April 4, 2020
The first 500 patient rooms at McCormick Place Convention Center.

The first 500 patient rooms at McCormick Place Convention Center. The 10X10-foot "rooms" have a cot, folding chair, lamp, and blanket, and a bowl containing a toothbrush, surgical masks, and earplugs.

    

Walsh Construction, one of the largest contractors in the city of Chicago and in the United States, is leading the temporary conversion of a portion of the McCormick Place Convention Center into an Alternate Care Facility (ACF) for novel coronavirus patients.

Construction on the first 500 beds was completed on April 3. According to a report in the Chicago Tribune, 500 more beds (with 14 nursing stations) should be online this week and another 1,250 by April 20, with another 750 to follow. The facility will have the capacity to treat up to 3,000 low- to moderate-acuity patients across three of the convention center’s halls, where patients will be separated by level of care required.

In addition to patient rooms, the first phase has also seen installation of spaces for laundry machines, pharmacy services, medical supplies, housekeeping, and medical gas canister storage, according to the Chicago Tribune.

 

Walsh Construction at McCormick Place ACF conversionA Walsh Construction staff member views the first phase of the conversion of portion of the McCormick Place Convention Center into an alternate care facility for coronavirus patients. Photo: Press Pool

 

ARMY CORPS OF ENGINEERS, MPEA OVERSEEING CONVERSION OF THE CONVENTION FACILITY

The Metropolitan Pier and Exposition Authority (MPEA) in association with the United States Army Corps of Engineers is directing the conversion of McCormick Place into a facility focused on patient care, infection control, fire protection and life safety. The ACF is designed to relieve pressure on the hospital system by freeing up beds for more patients with severe COVID-19 cases in anticipation of the surge in positive COVID-19 diagnoses to come.

The temporary field hospital is expected to be complete by April 24, according to Walsh Construction. “We mobilized and began work immediately,” said Thomas Caplis, Vice President of Healthcare at Walsh Construction. “Walsh Construction is proud to support these extraordinary efforts of MPEA and Army Corps of Engineers that will offer essential care to our Chicago neighbors and much needed assistance to our vital healthcare system.”

Chicago-based Walsh Construction has a successful history of working directly with USACE and the Federal Emergency Management Agency to renovate and construct facilities and infrastructure on a fast-track basis. Throughout the COVID-19 pandemic, Walsh has assisted healthcare institutions with trailers, tents, cargo boxes, negative pressure rooms, and establishing other temporary measures on an as-needed basis.

 

WALSH122 YEARS IN OPERATION

Walsh Construction is the fifth largest healthcare contractor in the United States, providing construction services and delivering healing environments across North America. The Acute Care Facility at McCormick Place adds to its list of patient-first projects that include new hospitals, emergency departments, critical care units, and outpatient services.

Walsh Construction is part of The Walsh Group, a 122-year-old company providing design, build, finance and activation services across the building, transportation and water markets. The Walsh Group operates as Walsh Construction, Archer Western and Walsh Canada throughout 20 regional offices.

Related Stories

Coronavirus | Nov 9, 2020

Even now, marketing is not a four-letter word

As AEC firm leaders consider worst-case scenarios and explore possible solutions to surmount them, they learn to become nimble, quick, and ready to pivot as circumstances demand.

Coronavirus | Nov 5, 2020

Thornton Tomasetti releases 'Healthy Reentry' free software to aid safe office return

Open source app provides customizable health reporting and contact tracing capabilities.

Multifamily Housing | Oct 30, 2020

The Weekly show: Multifamily security tips, the state of construction industry research, and AGC's market update

BD+C editors speak with experts from AGC, Charles Pankow Foundation, and Silva Consultants on the October 29 episode of "The Weekly." The episode is available for viewing on demand.

Coronavirus | Oct 19, 2020

Flexible design helped the University of Kansas Strawberry Hill Behavioral Health Hospital adapt to the coronavirus

The University of Kansas Strawberry Hill Behavioral Health Hospital had been open for just over six months when it was faced with the global coronavirus pandemic.

Coronavirus | Oct 14, 2020

Altering facilities for a post-COVID-19 world

There are several possibilities when it comes to reconfiguring or adjusting a space to maintain the health and safety of workers, from reorganizing spaces to enable social distancing measures to full teardown and reconstruction of a plant.

Coronavirus | Oct 8, 2020

The Weekly show: Statue of Liberty Museum, emotional learning in K-12, LA's climate change vulnerability

The October 8 episode of BD+C's "The Weekly" is available for viewing on demand.

Coronavirus | Oct 7, 2020

AIA releases 3D models, strategies for reducing risk of COVID-19 in polling places

Awards program highlights trends in healthcare facility designs.

Coronavirus | Oct 2, 2020

With revenues drying up, colleges reexamine their student housing projects

Shifts to online learning raise questions about the value of campus residence life.

Coronavirus | Oct 1, 2020

The Weekly show: Decarbonizing Chicago, re-evaluating delayed projects, and the future of the jobsite

The October 1 episode of BD+C's "The Weekly" is available for viewing on demand.

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021