BIM 2.0: AEC firms share their vision for the great leap forward in BIM/VDC implementation [2013 Giants 300 Report]

BIM 2.0: AEC firms share their vision for the great leap forward in BIM/VDC implementation [2013 Giants 300 Report]

We reached out to dozens of AEC firms that made our annual BIM Giants lists and asked one simple question: What does BIM 2.0 look like to you? Here’s what they had to offer.


By David Barista, Editor-in-Chief | July 19, 2013
SmithGroupJJR used BIM with its design of the 230,000-sf Facility for Rare Isoto
SmithGroupJJR used BIM with its design of the 230,000-sf Facility for Rare Isotope Beams (FRIB) at Michigan State University. The level of detail and coordination required from each of the firms disciplines was unprecedented. FRIB will be a new national user facility for nuclear science, funded by the Department of Energy Office of Science, Michigan State University, and the state of Michigan. PHOTO: SMITHGROUPJJR

Automated clash detection. Been there, done that. Quantity takeoffs. Mastered it. Virtual construction coordination. Old news.

More than 25 years after the first BIM software tools came to market, the U.S. construction industry has largely mastered the BIM/VDC learning curve and is implementing 3D BIM coordination on a regular basis. According to Building Design+Construction’s 2013 Giants 300 survey, 80% of the nation’s largest architecture, engineering, and construction firms have adopted BIM/VDC tools and report having earned revenue working on BIM-driven projects.

Let’s face it: Most of what’s discussed in the BIM/VDC arena today is yesterday’s news. So BD+C set out to identify the next big developments in BIM/VDC technology and implementation. We reached out to dozens of AEC firms that made our annual BIM Giants lists and asked one simple question: What does BIM 2.0 look like to you? Here’s what they had to offer:

 

Precise field-placing using robotic total stations

Structural steel items embedded in cast-in-place concrete are often misaligned or omitted in the field due to poor coordination between the structural engineer, concrete subcontractor, and steel erector. In a broader sense, the use of meta data in a building model promises great benefits, but it has not found a place in general practice because of questions of accuracy, responsibility, and liability for use of the data.

TOP BIM ARCHITECTURE FIRMS

 
2012 BIM Revenue ($)
1 Gensler $484,286,130
2 HOK $385,700,000
3 HDR Architecture $299,828,000
4 Perkins+Will $270,225,000
5 Skidmore, Owings & Merrill $267,601,700
6 HKS $216,000,000
7 Stantec $197,000,000
8 Cannon Design $165,000,000
9 RTKL $131,834,9509
10 SmithGroupJJR $105,598,000
11 EYP $85,381,169

TOP BIM ENGINEERING FIRMS

 
2012 BIM Revenue ($)
1 Jacobs Engineering Group $4,465,746,000
2 URS Corp. $292,864,749
3 Science Applications International Corp. $131,066,235
4 Arup $123,364,028
5 Merrick & Co. $106,000,000
6 SSOE Group $99,560,561
7 Thornton Tomasetti $93,431,545
8 Buro Happold Consulting Engineers $78,006,000
9 Middough $60,000,000
9 KPFF Consulting Engineers $60,000,000

TOP BIM CONSTRUCTION FIRMS

 
2012 BIM Revenue ($)
1 Turner Corporation, The $5,924,000,000
2 Clark Group $2,224,508,127
3 DPR Construction $2,175,000,000
4 Hoffman Construction $2,155,377,276
5 Hensel Phelps $2,089,180,000
6 Mortenson Construction $1,992,450,000
7 Balfour Beatty $1,902,988,332
8 McCarthy Holdings $1,879,000,000
9 JE Dunn Construction $1,513,283,005
10 Walsh Group, The $1,313,656,333
Sophisticated field placement methods exist using equipment such as robotic total stations. In conjunction with geospatial data incorporated into the BIM model, these tools can be used to accurately place items and record their as-built condition to high precision.

Even though hardware and software are available today, we lack a standard practice outlining the responsibilities of each stakeholder to create, verify, and utilize geospatial data in the BIM model.

—Steve Wilkerson, Associate Vice President, Haynes Whaley Associates

 

Extracting data for FM operations

The next “big trend” in BIM is the set-up, coordination, and extraction of data in COBie (Construction Operations Building Information Exchange) format so that more information can be pulled from the BIM model for use in client-based FM software, such as Maximo and AiM. The primary obstacle is figuring out how to do this when so much information for a project resides in multiple models. Programs such as BIMLink will be developed to help with the management of these “data buckets” and with the flow of that data out of and back into BIM models.

This trend will also push the AEC industry closer together, and new ways of collaborating—such as IPD multiple-party, single-contract delivery methods—will continue to evolve to help remove the obstacles to integrating data from all of the necessary parties involved.

—Sam Boyd, Quality Assurance Director, Cooper Carry

 

BIM on the go

Mobility is becoming more important. Multi-disciplinary teams in multiple locations collaborating on one model will require faster data networks and the use of cloud computing. Take that to the next step and design teams will be expected to instantly communicate with the construction and fabrication in the field through the model in the cloud.

We’re also going to see teams untethered from their desktops using more mobile tools (tablets, smartphones, etc.) to modify, navigate, and display the model. We are starting to work with tools that allow us to open BIM models on an iPad or iPhone to share with clients on the go.

—Don Ghent, Principal and Global Technical Leader, Gensler

 

Creating a common BIM language

The Industry Foundation Classes (IFC) being developed by buildingSmart International will eventually define actual data elements of a building model and standardize them industrywide. The group is working to develop and promote a standard data format that can be used across all platforms (Revit, Tekla, Bentley, etc.) so that data can be transferred and read across all model authoring and audit software programs. The walls of proprietary software will be broken down by IFC. All models will soon be able to interact with each other in ways not possible before.

—Aleisha Jaeger, LEED AP, Operations Manager-Construction, Epstein

 

The rise of virtual reality

The integration of BIM with virtual reality technologies is a promising development. For example, use of augmented reality—where both graphical and contextual information are overlaid onto building systems in the real world to produce the effect of x-ray vision—will allow the operator to see the utilities installed in a wall cavity, ceiling space, and even underground. The possibility of cost savings using these applications is fascinating, and the execution and user experience are quite simple (e.g., Google Glass viewer or mobile device such as an iPad).

—Andre Zoldan, Chief Information Officer, Albert Kahn Associates

 

Other ideas offered by the group include:

• Use of early phase database programs, such as Trelligence’s Affinity, to do programming and planning in a database-rich environment that can be directly imported into BIM programs.

• Automating code compliance review with the BIM model. The International Code Council is leading and funding the buildingSMART initiative to develop SMARTcodes, which could allow teams to automate the entire code review process.

• Establishing central project control. Building models, along with the use of RFID, barcode technology, and GPS will soon facilitate “smart” job sites. For example, materials arriving on site will automatically be sensed and recorded by the model as delivered. No paperwork will be required.

Related Stories

| Feb 15, 2012

Skanska secures $87M contract for subway project

The construction value of the project is $261.9 M. Skanska will include its full share, $87 M, in the bookings for Skanska USA Civil for the first quarter 2012.

| Feb 15, 2012

Code allowance offers retailers and commercial building owners increased energy savings and reduced construction costs

Specifying air curtains as energy-saving, cost-cutting alternatives to vestibules in 3,000-square-foot buildings and larger has been a recent trend among consulting engineers and architects.

| Feb 15, 2012

Englewood Construction announces new projects with Destination Maternity, American Girl

Englewood’s newest project for Wisconsin-based doll retailer American Girl, the company will combine four vacant storefronts into one large 15,000 square-foot retail space for American Girl.

| Feb 14, 2012

Angelo State University opens doors to new recreation center expansion

  Designed by SmithGroup, the JJR_Center for Human Performance offers enhanced fitness options, dynamic gathering space.

| Feb 14, 2012

SAIC selected for architectural and engineering design services at Lajes Field, Azores

SAIC’s services will include a broad variety of new construction projects and maintenance and repair projects

| Feb 14, 2012

Skanska promotes Aparicio and hires Leintz in Southern California

Aparicio and Leintz are both based in Skanska’s Los Angeles office.

| Feb 14, 2012

The Jackson Laboratory announces Gilbane Building Co. as program manager for Connecticut facility

Gilbane to manage program for new genomic medicine facility that will create 300 jobs in Connecticut.

| Feb 14, 2012

Thornton Tomasetti names Al Hashimi vice president for its Middle East Operations

Al Hashimi is joining the company to help expand Thornton Tomasetti’s business in the region and support clients locally.

| Feb 13, 2012

WHR Architects renovation of Morristown Memorial Hospital Simon Level 5 awarded LEED Gold

Located in the Simon Building, which serves as the main entrance leading into the Morristown Memorial Hospital campus, the project comprises three patient room wings connected by a centralized nursing station and elevator lobby.

| Feb 13, 2012

Center for Sustainable Building Research launches CommercialWindows.org

Resource aims at reducing commercial operating costs and energy consumption.

boombox1 - default
boombox2 -
native1 -

More In Category


AEC Tech

Lack of organizational readiness is biggest hurdle to artificial intelligence adoption

Managers of companies in the industrial sector, including construction, have bought the hype of artificial intelligence (AI) as a transformative technology, but their organizations are not ready to realize its promise, according to research from IFS, a global cloud enterprise software company. An IFS survey of 1,700 senior decision-makers found that 84% of executives anticipate massive organizational benefits from AI. 


Codes and Standards

Updated document details methods of testing fenestration for exterior walls

The Fenestration and Glazing Industry Alliance (FGIA) updated a document serving a recommended practice for determining test methodology for laboratory and field testing of exterior wall systems. The document pertains to products covered by an AAMA standard such as curtain walls, storefronts, window walls, and sloped glazing. AAMA 501-24, Methods of Test for Exterior Walls was last updated in 2015. 


MFPRO+ News

World’s largest 3D printer could create entire neighborhoods

The University of Maine recently unveiled the world’s largest 3D printer said to be able to create entire neighborhoods. The machine is four times larger than a preceding model that was first tested in 2019. The older model was used to create a 600 sf single-family home made of recyclable wood fiber and bio-resin materials.

halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021