Amid supply chain woes, building teams employ extreme procurement measures

Contractors

Amid supply chain woes, building teams employ extreme procurement measures

Project teams are looking to eliminate much of the guesswork around product availability and price inflation by employing early bulk-purchasing measures for entire building projects.


By David Barista, Editorial Director | March 28, 2022
Amid supply chain woes, building teams employ extreme procurement measures
Photo Pixabay

Fifty-two weeks. An entire year. That’s how long project teams are having to wait for certain building materials, systems, and equipment in the post-Covid environment. These include critical core-and-shell materials like steel, steel deck, steel joists, and roofing components such as ISO foam board insulation and fasteners. Even readily available “off-the-shelf” products like drywall, metal framing, and paint have lead times. Not to mention near-historic price inflation levels and shipping costs across almost every product category.

Faced with these immense supply chain issues—on top of the ongoing skilled labor shortage—building teams are forced to employ aggressive product procurement tactics to pull off new construction and major reconstruction programs on schedule—and anywhere close to budget. Common strategies include real-time price tracking, product availability analysis during the design and bidding phases, more-optimal project planning (duh!), and sourcing locally, when possible. 

Some project teams are looking to eliminate much of the guesswork around product availability and price inflation by employing early bulk-purchasing measures for entire building projects, even multi-build developments. This “buy-and-store” approach to product procurement has worked for several recent healthcare projects led by design and construction giant Haskell, says Denise Muth, Project Director with the firm’s Infrastructure and Transportation group. 

ALSO SEE: How building owners and developers can get ahead of the next supply chain disaster

“For one hospital project, it was determined to buy the whole project out from the start and utilize local storage leased by the hospital,” says Muth. “On another project, we accelerated roofing, MEP equipment, elevators, and steel to help jumpstart the lead time process while the balance of design is completed. Depending on the stage of design, our owners are encouraged to purchase the entire project as quickly as possible.”

AEC industry consultant Ryan Bosworth, Principal with Rider Levett Bucknall, urges project teams to take advantage of the glut in vacant or derelict retail stores, especially big boxes, to purchase building products in bulk and warehouse them locally. “Landlords are begging for revenue while they reposition properties,” he says, adding that these spaces are relatively inexpensive to rent and require little build-out.

This bulk-purchasing approach, while effective, does have its obstacles, says Muth, including added front-loaded costs for owners/developers, insurance considerations related to storage facilities, and the risk of changes to specifications or design after materials have been ordered and stored.

Related Stories

| Mar 19, 2012

Mixed-use project redefines Midtown District in Plantation, Fla.

Stiles Construction is building the residential complex, which is one of Broward County’s first multifamily rental communities designed to achieve LEED certification from the USGBC. 

| Mar 16, 2012

Temporary fix to CityCenter's Harmon would cost $2 million, contractor says

By contrast, CityCenter half-owner and developer MGM Resorts International determined last year that the Harmon would collapse in a strong quake and can't be fixed in an economical way. It favors implosion at a cost of $30 million.

| Mar 16, 2012

Work on Oxnard, Calif. shopping center resumes after a three-year hiatus

Stalled since 2009, developers of the Collection at RiverPark decided to restart construction on the outdoor mall. 

| Mar 16, 2012

Stego embarks on HPD Pilot Program

Vapor barrier manufacturer strives to provide better green choices to designers and builders.

| Mar 16, 2012

Marvin Windows and Doors accepting entries for fourth-annual myMarvin Architect’s Challenge

Architects in U.S. and abroad offered the chance to showcase their very best work.

| Mar 14, 2012

Hearing to decide fate of unfinished Harmon in Las Vegas under way

The testimony began with CityCenter consulting engineer Chukwuma Ekwueme methodically showing photo after photo of parts of the Harmon, where he and his team had chipped away the concrete pillars and beams to examine the steel reinforcing bars inside.

| Mar 14, 2012

Firestone names 2012 Master Contractor Award Winners

Annual award acknowledges industry’s top roofing professionals.

| Mar 14, 2012

Plans for San Francisco's tallest building revamped

The glassy white high-rise would be 60 stories and 1,070 feet tall with an entrance at First and Mission streets.

| Mar 14, 2012

Hyatt joins Thornton Tomasetti as VP in Chicago

A forensic specialist, Hyatt has more than 10 years of experience performing investigations of structural failures throughout the U.S.

boombox1 - default
boombox2 -
native1 -

More In Category

Construction Costs

New download: BD+C's May 2024 Market Intelligence Report

Building Design+Construction's monthly Market Intelligence Report offers a snapshot of the health of the U.S. building construction industry, including the commercial, multifamily, institutional, and industrial building sectors. This report tracks the latest metrics related to construction spending, demand for design services, contractor backlogs, and material price trends.




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021