5 tips for running a successful BIM coordination meeting

5 tips for running a successful BIM coordination meeting

Make the most of BIM coordination meetings by following these helpful tips.


By Jared Krieger, AIA, LEED AP, Gensler | May 30, 2013

Building information modeling tools are great, but if you can't run efficient, productive coordination meetings, the Building Team will never realize the benefits of true BIM coordination. Here are some helpful tips for making the most of BIM coordination meetings based on my experience working on BIM/VDC-driven projects:

1. Practice and prepare. Yes, practice for a meeting. The more you do it the more productive your meetings can be. It takes some skill to be able to navigate the model and have the correct models loaded and visibility settings. Spending 15 minutes before loading models and opening views for the areas of focus will save you a lot of waiting and down time during the meeting.

2. Assign a "designated driver.” This person needs to be familiar with the model and savvy with the software platform. Models can be quite cumbersome, and it can slow down the meeting when a group of people have to watch someone poorly navigating the model. That will quickly kill your productivity.

SEE JARED KRIEGER AT THE 2013 AIA NATIONAL CONVENTION
Jared Krieger, Project Architect in Gensler’s Washington, D.C., office, will speak on “Maximizing BIM: How to Successfully Execute a Fully Integrated BIM Project,” at the AIA National Convention in Denver on Friday, June 21, 6:00-7:00 p.m. More information: http://convention.aia.org.

3. Use your team’s time wisely. You don’t always have to have the full team in the room at the same time. Consider splitting the meeting into structured trades. For example, meet with the structural engineer for the first portion of the meeting to review structural specific coordination. Then have some overlap time with MEP and structural for common coordination. Finish the meeting with MEP-specific coordination.

4. Use meeting notes to stay focused. Open action items and homework from the previous meeting should be the basis for discussion in your current meeting. Use this structure to keep yourself on track, and resolve open coordination issues before moving on to new items.

5. Talk about this process early in the project. For most people, using a collaboratively focused process leveraging technology will be a new process. It may sound like a large time commitment, but if done correctly it will save you time in the long run. Educate the team early on and set/manage expectations.

Jared Krieger, AIA, LEED AP, is a Project Architect and BIM/VDC expert based in Gensler's Washington, D.C., office. He can be reached at jared_krieger@gensler.com.

Related Stories

| Apr 12, 2012

Solar PV carport, electrical charging stations unveiled in California

Project contractor Oltman Construction noted that the carport provides shaded area for 940 car stalls and generates 2 MW DC of electric power.

| Apr 11, 2012

Shawmut appoints Tripp as business development director

Tripp joined Shawmut in 1998 and previously held the positions of assistant superintendent, superintendent, and national construction manager.

| Apr 11, 2012

Corgan & SOM awarded contract to design SSA National Support Center

The new SSA campus is expected to meet all Federal energy and water conservation goals while achieving LEED Gold Certification from the United States Green Building Council.

| Apr 11, 2012

C.W. Driver completes Rec Center on CSUN campus

The state-of-the-art fitness center supports university’s goal to encourage student recruitment and retention.

| Apr 10, 2012

JE Dunn completes two medical office buildings at St. Anthony’s Lakewood, Colo. campus

Designed by Davis Partnership Architects, P.C., Medical Plaza 1 and 2 are four-story structures totaling 96,804-sf and 101,581-sf respectively.

| Apr 10, 2012

THINK [about architecture] Scholarship enters 15th year

Students are invited to submit two-minute creative videos that illustrate how they interact with their school's design and what the space makes possible.

| Apr 10, 2012

Structured Development & Bucksbaum close on new retail site in Chicago

The site is the location of New City, a mixed-use development that will feature 370,000-sf of retail space and 280 residential rental units.

| Apr 10, 2012

Moriarty & Associates selected as GC for Miami’s BrickellHouse Condo

Construction of the 46-story development is schedule to get underway this summer and be completed in 2014.

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021