flexiblefullpage -
billboard - default
interstitial1 - interstitial
catfish1 - bottom
Currently Reading

School officials and parents are asking one question: Can design prevent another Sandy Hook? [2013 Giants 300 Report]

School officials and parents are asking one question: Can design prevent another Sandy Hook? [2013 Giants 300 Report]

The second deadliest mass shooting by a single person in U.S. history galvanizes school officials, parents, public officials, and police departments, as they scrambled to figure out how to prevent a similar incident in their communities. 


By Robert Cassidy, Editorial Director | July 22, 2013
Cherry Crest Elementary, Bellevue, Wash., is integrated with the landscape to cr
Cherry Crest Elementary, Bellevue, Wash., is integrated with the landscape to create varied learning environments. Classrooms are arranged in grade-level houses clustered around shared spaces; courtyards are used for outdoor lessons. The Building Team was led by NAC|Architecture. PHOTO: BENJAMIN BENSCHNEIDER PHOTOGRAPHY

Since last December 14, safety has become the paramount concern of every school official and school board member in this country. December 14, 2012, was the date on which 20-year-old Adam Lanza shot and killed 20 children and six adult staff members at Sandy Hook Elementary School, in Newtown, Conn. It was the second deadliest mass shooting by a single person in U.S. history, after the Virginia Tech tragedy of 2007.

Sandy Hook galvanized school officials, parents, public officials, and police departments, as they scrambled to figure out how to prevent a similar incident in their communities. Many asked: Could better design and construction of schools—preschool, elementary, and secondary—prevent or at least mitigate the casualty rate at another Sandy Hook? And could this be done not only for schools to be built in the future, where Building Teams would be working from a blank slate, but for the tens of thousands of extant schools from Maine to Hawaii, where physical conditions are often literally set in stone?

TOP K-12 SCHOOL SECTOR ARCHITECTURE FIRMS

 
2012 K-12 Revenue ($)
1 DLR Group $38,250,000
2 SHW Group $32,328,843
3 PBK $31,760,000
4 IBI Group $27,977,860
5 HMC Architects $25,407,164
6 Stantec $21,586,209
7 Fanning/Howey Associates $20,247,000
8 Perkins+Will $19,938,211
9 Heery International $16,561,303
10 LPA $14,438,017

TOP K-12 SCHOOL SECTOR ENGINEERING FIRMS

 
2012 K-12 Revenue ($)
1 AECOM Technology Corp. $100,150,000
2 URS Corp. $55,927,778
3 STV $45,937,000
4 Jacobs Engineering Group $36,550,000
5 Parsons Brinckerhoff $19,100,000
6 TTG $9,985,300
7 Shive-Hattery $7,379,425
8 BRPH $4,900,000
9 KCI Technologies $4,200,000
10 Dewberry $3,852,971

TOP K-12 SCHOOL SECTOR CONSTRUCTION FIRMS

 
2012 K-12 Revenue ($)
1 Gilbane $947,077,000
2 Balfour Beatty $483,944,476
3 Turner Corporation, The $357,910,000
4 CORE Construction Group $284,198,375
5 Skanska USA $273,418,351
6 McCarthy Holdings $260,000,000
7 Kraus-Anderson Construction $211,000,000
8 JE Dunn Construction $169,860,436
9 Consigli Construction $148,883,468
10 Barton Malow $139,236,049

These questions inspired a gathering of public officials, school designers and contractors, safety experts, and facility directors convened last February in Washington, D.C., by the Council of Educational Facilities Planners International. The daylong CEFPI Security Summit provided a framework in which to consider what school districts can do to provide a safer environment for children, teachers, and administrative staff. Following are the recommendations of immediate interest to the design and construction community.

Infrastructure needs beefing up, says CEFPI report

Emergency preparedness and response must be woven into the very fabric of school life, according to the CEFPI Security Summit report. The report recommends creating “concentric circles of protection” through the following means:

  • Providing the ability to lock students behind doors to protect them from aggression (door hardware companies report that they cannot keep up with demand for lock systems since Sandy Hook)
  • Shielding students from large windows
  • Safeguarding children when they meet in large groups for meals and assemblies
  • Installing high-security keying systems with control measures in place for master keys
  • Securing children, teachers, and staff via secured vestibules and remote access to select exterior and interior doors (through keyless entry systems)
  • Eliminating access to unauthorized persons by improving line-of-sight conditions and installing CCTV cameras
  • Protecting entrances through the use of bollards and safeguarding the exterior and perimeter—including playgrounds, athletic fields, and parking lots—via upgraded lighting and camera monitoring

Mass notifiation high on school districts' agenda

The CEFPI report also recommends action on crisis communications, notably:

  • Providing an effective public address system, with a backup power source
  • Use of multiple communications devices, including mobile panic devices worn by key administrators
  • Installation of security cameras and use of emergency radio channels

School districts are already acting. Plainfield District 202, the fourth-largest school district in Illinois, just ordered $180,000 worth of wireless alarm systems for its 30 schools.

As the fall term approaches, design and construction firms, as well as manufacturers of safety products and systems, will be called upon to safeguard the nation’s schoolchildren even more vigorously than in the past.

Read BD+C's full Giants 300 Report

Related Stories

Museums | Aug 11, 2010

Design guidelines for museums, archives, and art storage facilities

This column diagnoses the three most common moisture challenges with museums, archives, and art storage facilities and provides design guidance on how to avoid them.

| Aug 11, 2010

Broadway-style theater headed to Kentucky

One of Kentucky's largest performing arts venues should open in 2011—that's when construction is expected to wrap up on Eastern Kentucky University's Business & Technology Center for Performing Arts. The 93,000-sf Broadway-caliber theater will seat 2,000 audience members and have a 60×24-foot stage proscenium and a fly loft.

| Aug 11, 2010

People+Firms

| Aug 11, 2010

Citizenship building in Texas targets LEED Silver

The Department of Homeland Security's new U.S. Citizenship and Immigration Services facility in Irving, Texas, was designed by 4240 Architecture and developed by JDL Castle Corporation. The focal point of the two-story, 56,000-sf building is the double-height, glass-walled Ceremony Room where new citizens take the oath.

| Aug 11, 2010

Carpenters' union helping build its own headquarters

The New England Regional Council of Carpenters headquarters in Dorchester, Mass., is taking shape within a 1940s industrial building. The Building Team of ADD Inc., RDK Engineers, Suffolk Construction, and the carpenters' Joint Apprenticeship Training Committee, is giving the old facility a modern makeover by converting the existing two-story structure into a three-story, 75,000-sf, LEED-certif...

| Aug 11, 2010

Utah research facility reflects Native American architecture

A $130 million research facility is being built at University of Utah's Salt Lake City campus. The James L. Sorenson Molecular Biotechnology Building—a USTAR Innovation Center—is being designed by the Atlanta office of Lord Aeck & Sargent, in association with Salt-Lake City-based Architectural Nexus.

| Aug 11, 2010

San Bernardino health center doubles in size

Temecula, Calif.-based EDGE was awarded the contract for California State University San Bernardino's health center renovation and expansion. The two-phase, $4 million project was designed by RSK Associates, San Francisco, and includes an 11,000-sf, tilt-up concrete expansion—which doubles the size of the facility—and site and infrastructure work.

| Aug 11, 2010

Goettsch Partners wins design competition for Soochow Securities HQ in China

Chicago-based Goettsch Partners has been selected to design the Soochow Securities Headquarters, the new office and stock exchange building for Soochow Securities Co. Ltd. The 21-story, 441,300-sf project includes 344,400 sf of office space, an 86,100-sf stock exchange, classrooms, and underground parking.

| Aug 11, 2010

New hospital expands Idaho healthcare options

Ascension Group Architects, Arlington, Texas, is designing a $150 million replacement hospital for Portneuf Medical Center in Pocatello, Idaho. An existing facility will be renovated as part of the project. The new six-story, 320-000-sf complex will house 187 beds, along with an intensive care unit, a cardiovascular care unit, pediatrics, psychiatry, surgical suites, rehabilitation clinic, and ...

| Aug 11, 2010

Colonnade fixes setback problem in Brooklyn condo project

The New York firm Scarano Architects was brought in by the developers of Olive Park condominiums in the Williamsburg section of Brooklyn to bring the facility up to code after frame out was completed. The architects designed colonnades along the building's perimeter to create the 15-foot setback required by the New York City Planning Commission.

boombox1 - default
boombox2 -
native1 -

More In Category

Construction Costs

New download: BD+C's May 2024 Market Intelligence Report

Building Design+Construction's monthly Market Intelligence Report offers a snapshot of the health of the U.S. building construction industry, including the commercial, multifamily, institutional, and industrial building sectors. This report tracks the latest metrics related to construction spending, demand for design services, contractor backlogs, and material price trends.




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021