Located at the base of the Gateway Arch, this underground museum explores seminal events in American history, such as the Louisiana Purchase and the Lewis and Clark expedition. The 46,000-sf addition and 100,000-sf renovation represented the facility’s first reconstruction work since the Museum of Westward Expansion opened in 1976.
The project team had to work mostly below ground and within the National Register–listed landscape. The Mississippi River flooded twice during construction.
The team traveled to Germany to review and approve the glass fabricator’s mockup of the canopy enclosure system for the new 2,000-sf west entrance. A reinforced cast-in-place post-tensioned concrete lid beam and slab system spans 80 feet over the museum addition.
Alper Audi and McCarthy Building Companies co-developed a concrete mockup with sensors that enabled the team to make sure that temperatures achieved during curing were within recommended tolerances for the 2,400 cubic yards of concrete that were used.
The mezzanine features a giant map of North America where visitors can walk the path of explorers Lewis and Clark.
The project team routed ductwork and piping through a mechanical tunnel from the existing mechanical room to and through the exhibit level, up a vertical cast-in-place concrete chase in the mezzanine, and across an underground duct system at entry level.
MEP systems were overhauled and reconfigured, resulting in the removal of 11 of 15 heating units and adding new systems inside ground-level mechanical rooms for easier maintenance.
GOLD AWARD WINNER
BUILDING TEAM IMEG Corp. (submitting firm, ME, telecommunications engineer) National Park Service, Gateway Arch Park Foundation (owners) Michael Van Valkenburgh Associates (architect for City Arch River Initiative) Cooper Robertson (museum design architect) James Carpenter Design Associates, Trivers Associates (associate architects) Alper Audi (SE) KAI (PE) Castle Contracting (earthwork/utilities contractor) David Mason + Associates (CE) National Park Service Denver Service Center (PM) Eckersley O’Callaghan (façade engineer) Haley Sharpe Design (exhibit designer) Shen Milsom & Wilke (A/V) Tillotson Design Associates (lighting) Jaffe Holden (acoustics) Alpha Corporation (CM) McCarthy Building Companies (GC) DETAILS 146,000 sf Total cost $176.4 million Construction time April 2015 to June 2018 Delivery method Design-bid-build
Related Stories
Reconstruction Awards | Nov 26, 2018
Yarn works: Neverending yarn
111-year-old mill becomes a mixed-income multifamily community.
Reconstruction Awards | Nov 20, 2018
Wiseburn High School: New kind of P3
A California school district and a charter school system join forces to open a skills-based high school.
Reconstruction Awards | Nov 19, 2018
Kehoe Iron Works: Industrial strength makeover
A project team turns a toxic site into a civic treasure.
Reconstruction Awards | Nov 19, 2018
Weiser Hall, University of Michigan: Campus upgrade
A Mid-century building becomes home to a new International Institute.
Reconstruction Awards | Nov 16, 2018
Mass MoCA Building 6: The Robert W. Wilson Building
A textile mill becomes an arts center that energizes a New England town and its region.
Reconstruction Awards | Nov 15, 2018
Charles L. Tutt Library, Colorado College: Net-zero in the Rockies
Library expansion reinforces Colorado College’s commitment to carbon neutrality.
Reconstruction Awards | Nov 14, 2018
National Arts Centre: O, Canada
Three new wings and a flashy AV display add luster to the nation’s cultural gem.
Reconstruction Awards | Nov 13, 2018
20 Times Square: Conquering Times Square
The 20 Times Square mixed-used project at the corner of 47th and Seventh Avenue is indicative of the great lengths Building Teams will go in order to maximize real estate and media opportunities in Times Square.
Reconstruction Awards | Nov 12, 2018
Crosstown Concourse: An 'organic' urban village
Memphians band together to rebuild a gigantic Sears distribution facility into a multifaceted community crossroads.
Reconstruction Awards | Nov 12, 2018
Cincinnati Music Hall: Saving a cultural anchor
Cincinnati uses ‘skillful triage’ to bring its endangered Music Hall up to date.