Museum at the Gateway Arch: Subterranean sensation

Reconstruction Awards

Museum at the Gateway Arch: Subterranean sensation

The project team used its creativity to overcome floods and other obstacles to construction.


By John Caulfield, Senior Editor | November 14, 2019
The museum's west entrance

The west entrance of the museum is laid onto the landscape and inserted into the topography. All photos: Paul Colletti Photography/©IMEG Corp

Located at the base of the Gateway Arch, this underground museum explores seminal events in American history, such as the Louisiana Purchase and the Lewis and Clark expedition. The 46,000-sf addition and 100,000-sf renovation represented the facility’s first reconstruction work since the Museum of Westward Expansion opened in 1976.

The project team had to work mostly below ground and within the National Register–listed landscape. The Mississippi River flooded twice during construction.

The team traveled to Germany to review and approve the glass fabricator’s mockup of the canopy enclosure system for the new 2,000-sf west entrance. A reinforced cast-in-place post-tensioned concrete lid beam and slab system spans 80 feet over the museum addition.

Alper Audi and McCarthy Building Companies co-developed a concrete mockup with sensors that enabled the team to make sure that temperatures achieved during curing were within recommended tolerances for the 2,400 cubic yards of concrete that were used.

 

The mezzanineThe mezzanine features a giant map of North America where visitors can walk the path of explorers Lewis and Clark.

 

The project team routed ductwork and piping through a mechanical tunnel from the existing mechanical room to and through the exhibit level, up a vertical cast-in-place concrete chase in the mezzanine, and across an underground duct system at entry level.

MEP systems were overhauled and reconfigured, resulting in the removal of 11 of 15 heating units and adding new systems inside ground-level mechanical rooms for easier maintenance.

 

GOLD AWARD WINNER

BUILDING TEAM IMEG Corp. (submitting firm, ME, telecommunications engineer) National Park Service, Gateway Arch Park Foundation (owners) Michael Van Valkenburgh Associates (architect for City Arch River Initiative) Cooper Robertson (museum design architect) James Carpenter Design Associates, Trivers Associates (associate architects) Alper Audi (SE) KAI (PE) Castle Contracting (earthwork/utilities contractor) David Mason + Associates (CE) National Park Service Denver Service Center (PM) Eckersley O’Callaghan (façade engineer) Haley Sharpe Design (exhibit designer) Shen Milsom & Wilke (A/V) Tillotson Design Associates (lighting) Jaffe Holden (acoustics) Alpha Corporation (CM) McCarthy Building Companies (GC) DETAILS 146,000 sf Total cost $176.4 million Construction time April 2015 to June 2018 Delivery method Design-bid-build

Related Stories

Reconstruction Awards | Nov 16, 2015

Lumberyard turned into Chicago charter school

While the existing structures were in poor condition, the Building Team preserved and restored 75% of the spaces and incorporated historic elements in the final design of the Intrinsic School on Chicago's Northwest side.

Reconstruction Awards | Nov 12, 2015

Columbia Grammar and Preparatory School grows with the times

The 251-year-old NYC school was a design-build project that overcame issues like tight space and zoning appeals during its redevelopment.

Reconstruction Awards | Nov 10, 2015

Restoration of the Whitney Building provides hope for Detroit

Four years ago, Whitney Partners purchased the 253,000-sf Whitney for $3.3 million. Their mission was to turn the 19-story structure into a mixed-use hotel, rental apartment, and retail center that would serve as a reminder of more prosperous times in Detroit’s past.

Reconstruction Awards | Nov 9, 2015

University of Chicago uses space economically with Saieh Hall

The five-story, 100,000-sf seminary was converted into a modern education facility that would be fully integrated into the university’s Hyde Park campus. The project demonstrated the university’s commitment to finding a balance between new construction and adaptive reuse of historically significant buildings.

Reconstruction Awards | Nov 9, 2015

King of kings: Classic brooklyn movie theater stages a return engagement

The theater, which withstood vacancy, neglect and vandalism, has been redeveloped with a goal: balance preservation with the creation of a modern performance space.

boombox1 - default
boombox2 -
native1 -

More In Category


Giants 400

BD+C Awards Programs

Entry information and past winners for Building Design+Construction's two major awards programs: 40 Under 40 and Giants 400



halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021